Every tracked AI data center campus interconnecting to the ERCOT grid, with combined announced-vs-energized capacity and the grid's live demand. Each figure is individually dated and sourced.


On this grid

Campuses
29
Announced (combined)
25.29 GW
Energized (combined)
1.08 GW
Grid demand now
64.5 GW

The Texas (ERCOT) grid is pulling 64.5 GW right now (EIA-930, 2026-09-27 04:00). If every announced campus on this grid energized fully, their combined 25.29 GW would be 39.2% of the grid's current load. Announced numbers are claims, not built capacity; see the methodology.

Campuses on this grid

AI data center campuses on the ERCOT grid
Data CityLaredoannounced5—
Project KilbyPecosannounced2.70—
Dove Creek Data CenterSan Angeloannounced2.41—
Alpha Digital CampusPecosannounced2—
Poolside Project HorizonFort Stocktonstalled20
Galaxy Helios CampusAftonpartially energized1.600.13
Vantage Data Centers — FrontierAlbany (Shackelford County)under construction1.400
Sandow Lakes Power / Data Center CampusBlueunder construction1.20—
Stargate Milam CountyRockdaleunder construction1.200
Stargate AbileneAbilenepartially energized1.200.30
GW RanchFort Stocktonpermitted1—
Crusoe Childress CampusChildressannounced10
Matrix Data Center CampusSulphur Springsunder construction0.80—
Nscale Barstow AI Data CenterBarstowunder construction0.70—
CyrusOne DFW10 Whitney / Thad Hill Powered LandWhitneyunder construction0.40—
Compass Datacenters Red Oak CampusRed Oakpartially energized0.360.36
Lancium Fort Stockton Clean CampusFort Stocktonpartially energized0.330.03
Project LlanoArmstrongunder construction——
Crusoe Stargate Site 2Albany (Shackelford County)under construction——
Crusoe Abilene AI Data CenterAbilenepartially energized——
Stargate Shackelford CountyAlbany (Shackelford County)announced——
Stargate Milam CountyMilam Countyannounced——
Stargate AbileneAbilenepartially energized——
Cipher Stingray Data CenterAndrewsunder construction——
Vantage TX1 San Antonio CampusSan Antoniopartially energized——
Google Midlothian CampusMidlothianpartially energized—0.27
Core Scientific / CoreWeave Denton HPC CampusDentonunder construction——
Black PearlWinkunder construction——
Barber LakeColorado Cityunder construction——