Data center campus
Compass Datacenters Red Oak Campus (DFW III)
Compass Datacenters Red Oak Campus is an AI data center campus developed by Compass Datacenters in Texas, Red Oak. 0.36 GW of capacity has been announced; 0.36 GW is energized. The gap is what this page tracks: what is claimed versus what is actually built, each figure dated and sourced.
Partially energized · Compass Datacenters · Private land · ERCOT · Red Oak, Texas, United States
Capacity: announced vs energized
Announced-to-energized gap: 0 GW. Every figure below is a single dated, sourced claim. Current best per series resolves by evidence tier, then date. See the methodology.
Construction evidence
Dated satellite imagery of the site itself, oldest to newest, with the campus milestones that landed in each window. This is what the site looked like from orbit while announcements, permits, and energizations were dated into our ledger, so bare land, grading, and building mass tell their own story alongside the paper trail. Sentinel-2 true color, 10 m resolution, cloud-free scenes; click any frame to expand it.
Delivery paceAnnounced Q2 2025 · live Q1 2026 · 7 mo build
Dated Sentinel-2 imagery, gated to hand-verified site coordinates. Milestones synthesized from the campus's own capacity ledger, financial claims, and lifecycle events; each chip links to its source. How we source and verify it: satellite construction evidence.
Per-building manifest tied to the site polygons and imagery. When we know a building's outline we render it; when we know only its year and capacity we still surface those as first-class rows so the campus total is auditable, not a headline claim. Sorted largest-first; top 6 shown by default of 14.
Manifest totals: 3,672,488 sqft. Rolled from the per-building rows above.
Key facts
Lifecycle
Announced
Energized
Developer
Location
Grid
Land
Facilities tracked
On the data center map
Every tracked data center is on this map, centered on Compass Datacenters Red Oak Campus. Pan or zoom out to see how close rivals are building.
- Announced capex
- $300M
- Cooling
- Air-cooled, N+1 redundancy
- Cost per MW
- $833K/MW
Every figure is one row in the ledger below with its source. Derived rows are pure arithmetic on the rows above (not new claims). Absent lines mean the fact isn't on record yet.
In clusterTexas(607)
The deal
- developer
- Compass Datacenters · Entity Compass Datacenters DFW III, LLC
- utility
- Hilco Electric Cooperative · Grid power provider to the Red Oak (DFW III) campus at 300 Houston School Road; TCEQ Federal Operating Permit O4679
Power
- Power source
- grid
- Grid operator
- ERCOT
- Interconnection
- Water
- Closed-loop water-cooling system that is not connected to the city utility line and, per city staff, uses less water annually than a Walmart Supercenter.
The Texas (ERCOT) grid demand right now: 62.3 GW (EIA-930, 2026-09-27 16:00). Compass Datacenters Red Oak Campus's announced 0.36 GW would be 0.6% of the grid's current load.
County water status: Extreme drought (D3) in Ellis County, week of 2026-09-22 (US Drought Monitor). Data centers are large water users for cooling; this is the neutral local water picture.
Silicon on site
Every AI chip publicly attributed to Compass Datacenters Red Oak Campus (DFW III) on the DEPLOY registry. Quantity hints are unstructured because underlying disclosures vary by an order of magnitude. Source links per row.
- as of 2025-01-01
H100/H200-generation hyperscaler capacity at the Red Oak DFW III campus
inferredCompass DFW III hosts multiple hyperscalers with H100/H200 fleets; per-tenant chip counts not published.
Why here
Compass Datacenters Red Oak Campus sits on private land in Texas, Red Oak. It connects to the ERCOT grid, draws on grid power. This siting summary is composed from the record's held fields, not speculation; see methodology.
Financial structure
- DFW III expansion (up to 3 additional buildings)
- $300M. Combined construction cost of up to three more facilities announced Sept 2024 journalist report
Regulatory paper trail
The filings and rules on record for this site and its jurisdiction, most recent first. Each is a sourced, dated artifact you can follow to the primary document.
Investment, workforce and specs
- Cooling
- Air-cooled, N+1 redundancy source
Facilities at this campus
- Compass Red Oak Campus (830-acre)hyperscale
- Compass Red Oak Campus Expansion (buildings 6-8)hyperscale
- Dallas-Fort Worth (Red Oak)hyperscale
- Red Oak campus expansion (buildings 6-8)colocation
Timeline
- Aug 2026party addedutility: Hilco Electric Cooperative
- Sep 2026Current: Partially energized
Sources
- Compass Datacenters Lands Refi on 5 Red Oak Facilities to Add Three More
- DFW - Red Oak (facility profile)
- Red Oak Data Center Meets Community Resistance · Dallas Observer
43a07716-a21a-44dc-96de-1421aa5d186b · Tracked with DEPLOY's verified-vs-claimed methodology. Every term is defined in the glossary. Announced numbers are claims, not built capacity.
Head-to-head
Common questions
What is Compass Datacenters Red Oak Campus (DFW III)?
How much power will Compass Datacenters Red Oak Campus (DFW III) use?
Who is building Compass Datacenters Red Oak Campus (DFW III)?
Is Compass Datacenters Red Oak Campus (DFW III) operating yet?
How verified is the data on Compass Datacenters Red Oak Campus (DFW III)?
Deploy Watch
Track Compass Datacenters Red Oak Campus (DFW III) on Deploy.
We notify you when energized capacity, lifecycle state, or a new dated capacity claim changes against primary-source evidence, not when the developer issues a press release.
Cite this page
DEPLOY. (2026). Compass Datacenters Red Oak Campus (DFW III): AI data center campus record. Retrieved September 27, 2026, from https://registry.deploy.report/datacenters/compass-red-oak-dfw3-ellis-texas
More citation formats (MLA, Chicago, BibTeX) →The verified data on this page is available under a Creative Commons Attribution 4.0 license: reuse the facts freely, with attribution to DEPLOY (deploy.report). The prose, design, and any imagery are not included and keep their own rights.
Machine-readable surfaces
- Markdown mirror: /datacenters/compass-red-oak-dfw3-ellis-texas.md
- JSON-LD: embedded in this page’s head
- REST API: /v1/datacenters/compass-red-oak-dfw3-ellis-texas
- Data documentation: /data
- Query this programmatically: Deploy MCP