Data center campus
Crusoe Childress Campus
Crusoe Childress Campus is an AI data center campus developed by Crusoe in Texas, Childress. 1 GW of capacity has been announced; none is energized yet. The gap is what this page tracks: what is claimed versus what is actually built, each figure dated and sourced.
Announced · Crusoe · Private land · ERCOT · Childress, Texas, United States
Capacity: announced vs energized
Announced-to-energized gap: 1 GW. Every figure below is a single dated, sourced claim. Current best per series resolves by evidence tier, then date. See the methodology.
Promised online: Q3 2026. 0 months away. Claimed by Crusoe / Lancium (source).
| Source | ||||
|---|---|---|---|---|
| Announced | 1.40 GW | 2026-07-15 | claimed | journalist report |
| Announced | 1 GW | 2026-07-01 | reported | press release |
| Energized | 0 GW | 2026-07-15 | reported | journalist report |
Key facts
Lifecycle
Announced
Energized
Developer
Location
Grid
Land
Facilities tracked
On the data center map
Every tracked data center is on this map, centered on Crusoe Childress Campus. Pan or zoom out to see how close rivals are building.
Approximate pin. We hold a city-level coordinate for this campus, not a verified site coordinate, so the marker shows the city rather than the parcel. The satellite strip and building outlines stay off until the site coordinate is sourced.
- Jobs
- 100 permanent reported
- Cooling
- Closed-loop, non-evaporative liquid cooling
- Grid
- ERCOT · Grid connected, on land the power partner owns: the 270 acre campus belongs to Lancium, which secures the power interconnect and runs energy orchestration, while Crusoe designs, builds and operates the data center. Behind-the-meter solar and storage sit alongside the grid supply. The announcement does not state the interconnect's approval status.
Every figure is one row in the ledger below with its source. Derived rows are pure arithmetic on the rows above (not new claims). Absent lines mean the fact isn't on record yet.
In clusterTexas(607)
The deal
Power
- Power source
- solar storage
- Grid operator
- ERCOT
- Interconnection
- Grid connected, on land the power partner owns: the 270 acre campus belongs to Lancium, which secures the power interconnect and runs energy orchestration, while Crusoe designs, builds and operates the data center. Behind-the-meter solar and storage sit alongside the grid supply. The announcement does not state the interconnect's approval status.
- Water
- Closed-loop, non-evaporative liquid cooling to reduce water use.
Behind-the-meter solar + battery storage (Lancium), solar storage, Announced. Lancium develops/manages behind-the-meter solar and storage; specific generation capacity not disclosed. 1 GW ERCOT-approved grid interconnect.
Behind-the-meter solar, solar, Announced. On-site solar resource developed and managed by Lancium; capacity not disclosed.
On-site energy storage, storage, Announced. Behind-the-meter energy storage for grid reliability; capacity not disclosed.
The Texas (ERCOT) grid demand right now: 62.3 GW (EIA-930, 2026-09-27 16:00). Crusoe Childress Campus's announced 1 GW would be 1.6% of the grid's current load.
County water status: Extreme drought (D3) in Childress County, week of 2026-09-22 (US Drought Monitor). Data centers are large water users for cooling; this is the neutral local water picture.
Silicon on site
Every AI chip publicly attributed to Crusoe Childress Campus on the DEPLOY registry. Quantity hints are unstructured because underlying disclosures vary by an order of magnitude. Source links per row.
Why here
Crusoe Childress Campus sits on private land in Texas, Childress. It connects to the ERCOT grid, draws on solar storage power, interconnection is Grid connected, on land the power partner owns: the 270 acre campus belongs to Lancium, which secures the power interconnect and runs energy orchestration, while Crusoe designs, builds and operates the data center. Behind-the-meter solar and storage sit alongside the grid supply. The announcement does not state the interconnect's approval status.. This siting summary is composed from the record's held fields, not speculation; see methodology.
Regulatory paper trail
The filings and rules on record for this site and its jurisdiction, most recent first. Each is a sourced, dated artifact you can follow to the primary document.
Investment, workforce and specs
Facilities at this campus
- Crusoe Childress AI Data Center Campushyperscale
- Crusoe Childress Campus1000 MW
Timeline
- Aug 2026capacity changedannounced: 1.4 to 1
- Sep 2026Current: Announced
Sources
- Crusoe to develop 1.4GW data center campus in Childress, Texas · DataCenterDynamics
- Crusoe and Lancium Announce 1.0 Gigawatt AI Data Center Campus in Childress, Texas · Crusoe
- Crusoe and Lancium Announce 1.0 Gigawatt AI Data Center Campus in Childress, Texas · Lancium
405e9627-7a7b-4bf2-8ae1-275248cdb27e · Tracked with DEPLOY's verified-vs-claimed methodology. Every term is defined in the glossary. Announced numbers are claims, not built capacity.
Head-to-head
Common questions
What is Crusoe Childress Campus?
How much power will Crusoe Childress Campus use?
Who is building Crusoe Childress Campus?
Is Crusoe Childress Campus operating yet?
How verified is the data on Crusoe Childress Campus?
Deploy Watch
Track Crusoe Childress Campus on Deploy.
We notify you when energized capacity, lifecycle state, or a new dated capacity claim changes against primary-source evidence, not when the developer issues a press release.
Cite this page
DEPLOY. (2026). Crusoe Childress Campus: AI data center campus record. Retrieved September 27, 2026, from https://registry.deploy.report/datacenters/crusoe-childress-texas
More citation formats (MLA, Chicago, BibTeX) →The verified data on this page is available under a Creative Commons Attribution 4.0 license: reuse the facts freely, with attribution to DEPLOY (deploy.report). The prose, design, and any imagery are not included and keep their own rights.
Machine-readable surfaces
- Markdown mirror: /datacenters/crusoe-childress-texas.md
- JSON-LD: embedded in this page’s head
- REST API: /v1/datacenters/crusoe-childress-texas
- Data documentation: /data
- Query this programmatically: Deploy MCP