Data center campus
Crusoe Abilene Microsoft AI Factory Campus
Crusoe Abilene Microsoft AI Factory Campus is an AI data center campus developed by Crusoe in Texas, Abilene. 0.90 GW of capacity has been announced; none is energized yet. The gap is what this page tracks: what is claimed versus what is actually built, each figure dated and sourced.
Under construction · Crusoe · Private land · ERCOT · Abilene, Texas, United States
Capacity: announced vs energized
Announced-to-energized gap: 0.90 GW. Every figure below is a single dated, sourced claim. Current best per series resolves by evidence tier, then date. See the methodology.
| Source | ||||
|---|---|---|---|---|
| Announced | 0.90 GW | 2026-03-27 | claimed | company |
Key facts
Lifecycle
Announced
Energized
Developer
Location
Grid
Land
Facilities tracked
Reported facts
Structured facts sourced from citations already on this record. Each fact traces to a source in the References section below.
- Named tenant / customer
- Microsoft (large-scale AI workloads; Microsoft Cloud Operations & Innovation president quoted in Crusoe release) (Crusoe)
- Lifecycle / timeline
- Land clearing and site preparation underway at announcement (Mar 27, 2026); first building expected to energize mid-2027 (Crusoe)
- Announced campus capacity
- 900 MW campus (two buildings); each building designed for 336 MW critical IT load; combined with existing Abilene infrastructure projected ~2.1 GW (Crusoe)
- On-site power
- 900 MW behind-the-meter on-site power plant paired with medium-voltage BESS for operational reliability and grid resilience (Crusoe)
- Cooling
- Closed-loop non-evaporative liquid cooling (company) (Crusoe)
- Adjacent Abilene context
- Company: first Abilene project was two 100 MW buildings energized in under a year; second phase adds six buildings toward 1.2 GW by end of 2026 on the existing campus next door (Crusoe)
- Jobs (company claim)
- Thousands of additional construction and hundreds of permanent jobs expected in the Abilene region (company) (Crusoe)
- Related campuses
- Adjacent to / distinct from Crusoe Abilene AI Data Center (Stargate Site 1) and Stargate Abilene (Oracle/OpenAI).
On the data center map
Every tracked data center is on this map, centered on Crusoe Abilene Microsoft AI Factory Campus. Pan or zoom out to see how close rivals are building.
Approximate pin. We hold a city-level coordinate for this campus, not a verified site coordinate, so the marker shows the city rather than the parcel. The satellite strip and building outlines stay off until the site coordinate is sourced.
- Cooling
- closed-loop non-evaporative liquid cooling
- Grid
- ERCOT · live in ~10 months
- Tenant
- Microsoft
Every figure is one row in the ledger below with its source. Derived rows are pure arithmetic on the rows above (not new claims). Absent lines mean the fact isn't on record yet.
In clusterTexas(606)
The deal
Power
- Power source
- behind the meter gas
- Grid operator
- ERCOT
- Interconnection
- Water
- Crusoe closed-loop non-evaporative liquid cooling systems (company) ([Crusoe](https://www.crusoe.ai/resources/newsroom/crusoe-announces-new-900-mw-ai-factory-campus-in-abilene-texas-to-support-microsoft-ai-infrastructure)).
Abilene Microsoft campus behind-the-meter plant, 0.90 GW other, Announced. Crusoe: 900 MW behind-the-meter on-site power plant with MV BESS. Primary release does not name the fuel mix; typed as other.
Abilene Microsoft campus MV BESS, other, Announced. Medium-voltage battery energy storage paired with the on-site plant.
The Texas (ERCOT) grid demand right now: 71.1 GW (EIA-930, 2026-09-28 03:00). Crusoe Abilene Microsoft AI Factory Campus's announced 0.90 GW would be 1.3% of the grid's current load.
County water status: Severe drought (D2) in Taylor County, week of 2026-09-22 (US Drought Monitor). Data centers are large water users for cooling; this is the neutral local water picture.
Why here
Crusoe Abilene Microsoft AI Factory Campus sits on private land in Texas, Abilene. It connects to the ERCOT grid, draws on behind the meter gas power. This siting summary is composed from the record's held fields, not speculation; see methodology.
Regulatory paper trail
The filings and rules on record for this site and its jurisdiction, most recent first. Each is a sourced, dated artifact you can follow to the primary document.
Investment, workforce and specs
- Cooling
- closed-loop non-evaporative liquid cooling source
Facilities at this campus
Timeline
- Sep 2026party addedgrid_operator: ERCOT
- Sep 2026Current: Under construction
Sources
- Crusoe Announces New 900 MW AI Factory Campus in Abilene, Texas to Support Microsoft AI Infrastructure · Crusoe
- Crusoe Expands Abilene AI Campus With New 900 MW AI Factory for Microsoft · Data Center Knowledge
d7e72a52-2394-4b8e-9583-dcabc8fa0f7d · Tracked with DEPLOY's verified-vs-claimed methodology. Every term is defined in the glossary. Announced numbers are claims, not built capacity.
Head-to-head
Common questions
What is Crusoe Abilene Microsoft AI Factory Campus?
How much power will Crusoe Abilene Microsoft AI Factory Campus use?
Who is building Crusoe Abilene Microsoft AI Factory Campus?
Is Crusoe Abilene Microsoft AI Factory Campus operating yet?
How verified is the data on Crusoe Abilene Microsoft AI Factory Campus?
Deploy Watch
Track Crusoe Abilene Microsoft AI Factory Campus on Deploy.
We notify you when energized capacity, lifecycle state, or a new dated capacity claim changes against primary-source evidence, not when the developer issues a press release.
Cite this page
DEPLOY. (2026). Crusoe Abilene Microsoft AI Factory Campus: AI data center campus record. Retrieved September 28, 2026, from https://registry.deploy.report/datacenters/crusoe-abilene-microsoft-campus
More citation formats (MLA, Chicago, BibTeX) →The verified data on this page is available under a Creative Commons Attribution 4.0 license: reuse the facts freely, with attribution to DEPLOY (deploy.report). The prose, design, and any imagery are not included and keep their own rights.
Machine-readable surfaces
- Markdown mirror: /datacenters/crusoe-abilene-microsoft-campus.md
- JSON-LD: embedded in this page’s head
- REST API: /v1/datacenters/crusoe-abilene-microsoft-campus
- Data documentation: /data
- Query this programmatically: Deploy MCP