Data center campus

Poolside Project Horizon (West Texas)

Poolside Project Horizon is an AI data center campus developed by Poolside AI in Texas, Fort Stockton. 2 GW of capacity has been announced; none is energized yet. The gap is what this page tracks: what is claimed versus what is actually built, each figure dated and sourced.

Stalled · Poolside AI · Private land · ERCOT · Fort Stockton, Texas, United States


Capacity: announced vs energized

Announced-to-energized gap: 2 GW. Every figure below is a single dated, sourced claim. Current best per series resolves by evidence tier, then date. See the methodology.

Poolside Project Horizon (West Texas) capacity claims
Source
Announced2 GW2025-10-15reportedpress release
Contracted0.25 GW2025-10-15reportedjournalist report
Energized0 GW2026-04-01reportedjournalist report

Key facts

stalled

Lifecycle

2 GW

Announced

0 GW

Energized

Poolside AI

Developer

ERCOT

Grid

2 GW

Announced-to-energized gap

On the data center map

Every tracked data center is on this map, centered on Poolside Project Horizon. Pan or zoom out to see how close rivals are building.

Free to use on your site, with a link back to DEPLOY.
The story of Poolside Project Horizon (West Texas)
Grid
ERCOT · Behind the meter with the grid kept as backup: on-site aero-derivative turbines with SCR emissions control and battery storage for load balancing, plus grid interconnect redundancy. The 568 acre site on Longfellow Ranch sits next to a major Permian gas hub, and the 2 GW campus is planned in eight phases of 250 MW, the first of which is 250 MW gross with an option on 500 MW more.
GPUs
40K 40,000+ NVIDIA GB300 NVL72 GPUs (CoreWeave, phase 1)

Every figure is one row in the ledger below with its source. Derived rows are pure arithmetic on the rows above (not new claims). Absent lines mean the fact isn't on record yet.

In clusterTexas(607)

The deal

developer
Poolside AI · Campus owner/developer; ~$2B Series C reportedly failed to close, contributing to anchor collapse
chip supplier
NVIDIA · 40,000+ GB300 NVL72 GPUs planned; also a Poolside backer
financier
Mitchell family (Longfellow Ranch) · Landowner of the ~568-acre site
offtaker
CoreWeave · Original anchor tenant (15-yr, 250 MW) and GPU provider; TERMINATED lease ~late March 2026

Power

Power source
behind the meter gas
Grid operator
ERCOT
Interconnection
Behind the meter with the grid kept as backup: on-site aero-derivative turbines with SCR emissions control and battery storage for load balancing, plus grid interconnect redundancy. The 568 acre site on Longfellow Ranch sits next to a major Permian gas hub, and the 2 GW campus is planned in eight phases of 250 MW, the first of which is 250 MW gross with an option on 500 MW more.
Water
Established water and processing infrastructure on Longfellow Ranch, adjacent to a Permian Basin natural gas hub.

On-site aero-derivative gas turbines (Permian Basin gas), 2 GW gas, Announced. Behind-the-meter aero-derivative turbines with SCR emissions control plus on-site battery storage; campus designed to run islanded from the ERCOT grid

Behind-the-meter aeroderivative gas turbines + battery storage, gas, Announced. On-site aeroderivative turbines with SCR emissions control plus battery storage for load-balancing and grid-interconnect redundancy; adjacent to Permian Basin gas hub.

The Texas (ERCOT) grid demand right now: 71.7 GW (EIA-930, 2026-09-27 18:00). Poolside Project Horizon's announced 2 GW would be 2.8% of the grid's current load.

County water status: Moderate drought (D1) in Pecos County, week of 2026-09-22 (US Drought Monitor). Data centers are large water users for cooling; this is the neutral local water picture.

Why here

Poolside Project Horizon sits on private land in Texas, Fort Stockton. It connects to the ERCOT grid, draws on behind the meter gas power, interconnection is Behind the meter with the grid kept as backup: on-site aero-derivative turbines with SCR emissions control and battery storage for load balancing, plus grid interconnect redundancy. The 568 acre site on Longfellow Ranch sits next to a major Permian gas hub, and the 2 GW campus is planned in eight phases of 250 MW, the first of which is 250 MW gross with an option on 500 MW more.. This siting summary is composed from the record's held fields, not speculation; see methodology.

Regulatory paper trail

The filings and rules on record for this site and its jurisdiction, most recent first. Each is a sourced, dated artifact you can follow to the primary document.

NHTSA Recall: Zoox Robotaxi Software Update for Heavy Smoke Visibility (26E044)operational restriction · 2026-07-15 · United States

Investment, workforce and specs

Estimated compute: the claimed 40,000+ NVIDIA GB300 NVL72 GPUs (CoreWeave, phase 1) chips are on the order of 30x the compute used to train a GPT-4-class model. Derived from the chip-count claim, not measured (basis).

Timeline

  1. Aug 2026
    party linked
    offtaker: linked externalName "CoreWeave" to company coreweave
  2. Sep 2026
    Current: Stalled

Sources

92f624bd-bd8f-423b-a90b-1e2601a92712 · Tracked with DEPLOY's verified-vs-claimed methodology. Every term is defined in the glossary. Announced numbers are claims, not built capacity.

Head-to-head

Common questions

What is Poolside Project Horizon (West Texas)?
Poolside Project Horizon (West Texas) is an AI data center campus tracked on the DEPLOY registry, located in Fort Stockton. DEPLOY records its capacity as a dated, sourced ledger: announced gigawatts versus actually energized gigawatts, never a press-release total.
How much power will Poolside Project Horizon (West Texas) use?
Poolside Project Horizon (West Texas) has 2 GW of announced capacity on the DEPLOY registry, of which 0 GW is recorded as energized, an announced-to-energized gap of 2 GW. Each figure is individually dated and sourced.
Who is building Poolside Project Horizon (West Texas)?
Poolside AI is recorded as a party to Poolside Project Horizon (West Texas) on the DEPLOY registry.
Is Poolside Project Horizon (West Texas) operating yet?
As of the most recent verification on the DEPLOY registry, Poolside Project Horizon (West Texas) is stalled. DEPLOY tracks the lifecycle from announced through energized, so the current state reflects sourced evidence, not the original announcement.
How verified is the data on Poolside Project Horizon (West Texas)?
A human editor has reviewed this record for the indexed registry. Every capacity figure is an append-only, dated claim resolved to the highest-evidence tier; superseded claims are kept but excluded from the current view.

Deploy Watch

Track Poolside Project Horizon (West Texas) on Deploy.

We notify you when energized capacity, lifecycle state, or a new dated capacity claim changes against primary-source evidence, not when the developer issues a press release.

Cite this page

DEPLOY. (2026). Poolside Project Horizon (West Texas): AI data center campus record. Retrieved September 27, 2026, from https://registry.deploy.report/datacenters/poolside-project-horizon-pecos-texas