Data center campus
Poolside Project Horizon (West Texas)
Poolside Project Horizon is an AI data center campus developed by Poolside AI in Texas, Fort Stockton. 2 GW of capacity has been announced; none is energized yet. The gap is what this page tracks: what is claimed versus what is actually built, each figure dated and sourced.
Stalled · Poolside AI · Private land · ERCOT · Fort Stockton, Texas, United States
Capacity: announced vs energized
Announced-to-energized gap: 2 GW. Every figure below is a single dated, sourced claim. Current best per series resolves by evidence tier, then date. See the methodology.
| Source | ||||
|---|---|---|---|---|
| Announced | 2 GW | 2025-10-15 | reported | press release |
| Contracted | 0.25 GW | 2025-10-15 | reported | journalist report |
| Energized | 0 GW | 2026-04-01 | reported | journalist report |
Key facts
Lifecycle
Announced
Energized
Poolside AI
Developer
Location
Grid
Land
Announced-to-energized gap
On the data center map
Every tracked data center is on this map, centered on Poolside Project Horizon. Pan or zoom out to see how close rivals are building.
- Grid
- ERCOT · Behind the meter with the grid kept as backup: on-site aero-derivative turbines with SCR emissions control and battery storage for load balancing, plus grid interconnect redundancy. The 568 acre site on Longfellow Ranch sits next to a major Permian gas hub, and the 2 GW campus is planned in eight phases of 250 MW, the first of which is 250 MW gross with an option on 500 MW more.
- GPUs
- 40K 40,000+ NVIDIA GB300 NVL72 GPUs (CoreWeave, phase 1)
Every figure is one row in the ledger below with its source. Derived rows are pure arithmetic on the rows above (not new claims). Absent lines mean the fact isn't on record yet.
In clusterTexas(607)
The deal
- developer
- Poolside AI · Campus owner/developer; ~$2B Series C reportedly failed to close, contributing to anchor collapse
- chip supplier
- NVIDIA · 40,000+ GB300 NVL72 GPUs planned; also a Poolside backer
- financier
- Mitchell family (Longfellow Ranch) · Landowner of the ~568-acre site
- offtaker
- CoreWeave · Original anchor tenant (15-yr, 250 MW) and GPU provider; TERMINATED lease ~late March 2026
Power
- Power source
- behind the meter gas
- Grid operator
- ERCOT
- Interconnection
- Behind the meter with the grid kept as backup: on-site aero-derivative turbines with SCR emissions control and battery storage for load balancing, plus grid interconnect redundancy. The 568 acre site on Longfellow Ranch sits next to a major Permian gas hub, and the 2 GW campus is planned in eight phases of 250 MW, the first of which is 250 MW gross with an option on 500 MW more.
- Water
- Established water and processing infrastructure on Longfellow Ranch, adjacent to a Permian Basin natural gas hub.
On-site aero-derivative gas turbines (Permian Basin gas), 2 GW gas, Announced. Behind-the-meter aero-derivative turbines with SCR emissions control plus on-site battery storage; campus designed to run islanded from the ERCOT grid
Behind-the-meter aeroderivative gas turbines + battery storage, gas, Announced. On-site aeroderivative turbines with SCR emissions control plus battery storage for load-balancing and grid-interconnect redundancy; adjacent to Permian Basin gas hub.
The Texas (ERCOT) grid demand right now: 71.7 GW (EIA-930, 2026-09-27 18:00). Poolside Project Horizon's announced 2 GW would be 2.8% of the grid's current load.
County water status: Moderate drought (D1) in Pecos County, week of 2026-09-22 (US Drought Monitor). Data centers are large water users for cooling; this is the neutral local water picture.
Why here
Poolside Project Horizon sits on private land in Texas, Fort Stockton. It connects to the ERCOT grid, draws on behind the meter gas power, interconnection is Behind the meter with the grid kept as backup: on-site aero-derivative turbines with SCR emissions control and battery storage for load balancing, plus grid interconnect redundancy. The 568 acre site on Longfellow Ranch sits next to a major Permian gas hub, and the 2 GW campus is planned in eight phases of 250 MW, the first of which is 250 MW gross with an option on 500 MW more.. This siting summary is composed from the record's held fields, not speculation; see methodology.
Regulatory paper trail
The filings and rules on record for this site and its jurisdiction, most recent first. Each is a sourced, dated artifact you can follow to the primary document.
Investment, workforce and specs
Estimated compute: the claimed 40,000+ NVIDIA GB300 NVL72 GPUs (CoreWeave, phase 1) chips are on the order of 30x the compute used to train a GPT-4-class model. Derived from the chip-count claim, not measured (basis).
Timeline
- Aug 2026party linkedofftaker: linked externalName "CoreWeave" to company coreweave
- Sep 2026Current: Stalled
Sources
- How CoreWeave and Poolside Are Teaming Up in West Texas to Build the Next Generation of AI Data Centers
- CoreWeave Announces Partnership with Foundation Model Company Poolside to Deliver AI Cloud Services
- Plans Unveiled for 2 GW Artificial Intelligence Campus in West Texas
- AI startup Poolside teams up with CoreWeave on 2GW data center in Texas
- CoreWeave Ends 2 GW Texas Data Center Deal With Poolside
92f624bd-bd8f-423b-a90b-1e2601a92712 · Tracked with DEPLOY's verified-vs-claimed methodology. Every term is defined in the glossary. Announced numbers are claims, not built capacity.
Head-to-head
Common questions
What is Poolside Project Horizon (West Texas)?
How much power will Poolside Project Horizon (West Texas) use?
Who is building Poolside Project Horizon (West Texas)?
Is Poolside Project Horizon (West Texas) operating yet?
How verified is the data on Poolside Project Horizon (West Texas)?
Deploy Watch
Track Poolside Project Horizon (West Texas) on Deploy.
We notify you when energized capacity, lifecycle state, or a new dated capacity claim changes against primary-source evidence, not when the developer issues a press release.
Cite this page
DEPLOY. (2026). Poolside Project Horizon (West Texas): AI data center campus record. Retrieved September 27, 2026, from https://registry.deploy.report/datacenters/poolside-project-horizon-pecos-texas
More citation formats (MLA, Chicago, BibTeX) →The verified data on this page is available under a Creative Commons Attribution 4.0 license: reuse the facts freely, with attribution to DEPLOY (deploy.report). The prose, design, and any imagery are not included and keep their own rights.
Machine-readable surfaces
- Markdown mirror: /datacenters/poolside-project-horizon-pecos-texas.md
- JSON-LD: embedded in this page’s head
- REST API: /v1/datacenters/poolside-project-horizon-pecos-texas
- Data documentation: /data
- Query this programmatically: Deploy MCP