Data center campus
Google Midlothian Campus (Alamo Mission)
Google Midlothian Campus is a tracked AI data center campus in Texas, Midlothian. Google's Ellis County hyperscale/AI campus (developed via Alamo Mission LLC, project 'Sharka'; ~266 MW at 3441 Railport Parkway, Midlothian) holds a TCEQ Federal Operating Permit and is expanding as part of Google's stat
Partially energized · Google · Private land · ERCOT · Midlothian, Texas, United States
Capacity: announced vs energized
Promised online: 2027-02-24. Energized capacity is now on record. Claimed by Google (via TDLR filing) (source).
| Source | ||||
|---|---|---|---|---|
| Energized | 0.27 GW | 2026-03-01 | verified | permit |
Construction evidence
Dated satellite imagery of the site itself, oldest to newest, with the campus milestones that landed in each window. This is what the site looked like from orbit while announcements, permits, and energizations were dated into our ledger, so bare land, grading, and building mass tell their own story alongside the paper trail. Sentinel-2 true color, 10 m resolution, cloud-free scenes; click any frame to expand it.
Dated Sentinel-2 imagery, gated to hand-verified site coordinates. Milestones synthesized from the campus's own capacity ledger, financial claims, and lifecycle events; each chip links to its source. How we source and verify it: satellite construction evidence.
Per-building manifest tied to the site polygons and imagery. When we know a building's outline we render it; when we know only its year and capacity we still surface those as first-class rows so the campus total is auditable, not a headline claim. Sorted largest-first; top 6 shown by default of 11.
Manifest totals: 3,106,626 sqft. Rolled from the per-building rows above.
Key facts
Lifecycle
Energized
Developer
Location
Grid
Land
Facilities tracked
On the data center map
Every tracked data center is on this map, centered on Google Midlothian Campus. Pan or zoom out to see how close rivals are building.
- Announced capex
- $880M
Every figure is one row in the ledger below with its source. Derived rows are pure arithmetic on the rows above (not new claims). Absent lines mean the fact isn't on record yet.
In clusterTexas(607)
The deal
Power
- Power source
- grid
- Grid operator
- ERCOT
- Interconnection
The Texas (ERCOT) grid demand right now: 58.7 GW (EIA-930, 2026-09-27 06:00).
County water status: Extreme drought (D3) in Ellis County, week of 2026-09-22 (US Drought Monitor). Data centers are large water users for cooling; this is the neutral local water picture.
Why here
Google Midlothian Campus sits on private land in Texas, Midlothian. It connects to the ERCOT grid, draws on grid power. This siting summary is composed from the record's held fields, not speculation; see methodology.
Financial structure
- Sharka Building 5 (fifth Midlothian data center)
- $880M. One-story, 288,000 sq ft data center at 3441 Railport Parkway; TDLR project registered Dec 8, 2025 (estimates subject to change) journalist report
Regulatory paper trail
The filings and rules on record for this site and its jurisdiction, most recent first. Each is a sourced, dated artifact you can follow to the primary document.
Investment, workforce and specs
- Capex
- Fifth data center building (project Sharka), 288,000 sq ft source
Facilities at this campus
- Google Midlothian Data Center (5th building)hyperscale
- Midlothian Data Centerhyperscale
Timeline
- Aug 2026party addeddeveloper: Alamo Mission LLC
- Sep 2026Current: Partially energized
Sources
- Google files for fifth data center at Midlothian campus in Texas
- Google — Red Oak, TX (facility profile)
242adcda-ceef-4893-a70a-153273e218ab · Tracked with DEPLOY's verified-vs-claimed methodology. Every term is defined in the glossary. Announced numbers are claims, not built capacity.
Head-to-head
Common questions
What is Google Midlothian Campus (Alamo Mission)?
Who is building Google Midlothian Campus (Alamo Mission)?
Is Google Midlothian Campus (Alamo Mission) operating yet?
How verified is the data on Google Midlothian Campus (Alamo Mission)?
Deploy Watch
Track Google Midlothian Campus (Alamo Mission) on Deploy.
We notify you when energized capacity, lifecycle state, or a new dated capacity claim changes against primary-source evidence, not when the developer issues a press release.
Cite this page
DEPLOY. (2026). Google Midlothian Campus (Alamo Mission): AI data center campus record. Retrieved September 27, 2026, from https://registry.deploy.report/datacenters/google-alamo-mission-midlothian-ellis-texas
More citation formats (MLA, Chicago, BibTeX) →The verified data on this page is available under a Creative Commons Attribution 4.0 license: reuse the facts freely, with attribution to DEPLOY (deploy.report). The prose, design, and any imagery are not included and keep their own rights.
Machine-readable surfaces
- Markdown mirror: /datacenters/google-alamo-mission-midlothian-ellis-texas.md
- JSON-LD: embedded in this page’s head
- REST API: /v1/datacenters/google-alamo-mission-midlothian-ellis-texas
- Data documentation: /data
- Query this programmatically: Deploy MCP