AI data centers on the PJM grid

Every tracked AI data center campus interconnecting to the PJM grid, with combined announced-vs-energized capacity and the grid's live demand. Each figure is individually dated and sourced.


On this grid

Campuses
19
Announced (combined)
26.10 GW
Energized (combined)
1.41 GW
Grid demand now
77.4 GW

The PJM grid is pulling 77.4 GW right now (EIA-930, 2026-09-27 04:00). If every announced campus on this grid energized fully, their combined 26.10 GW would be 33.7% of the grid's current load. Announced numbers are claims, not built capacity; see the methodology.

Campuses on this grid

See every campus on the national data center map, browse the full campus index, or read the verified-vs-claimed methodology.