Data center campus
PowerHouse 95 (Spotsylvania) Campus
PowerHouse 95 (Spotsylvania) Campus is an AI data center campus developed by PowerHouse Data Centers in Virginia, Spotsylvania County. 0.80 GW of capacity has been announced; none is energized yet. The gap is what this page tracks: what is claimed versus what is actually built, each figure dated and sourced.
Under construction · PowerHouse Data Centers · greenfield · PJM · Spotsylvania County, Virginia, United States
Capacity: announced vs energized
Announced-to-energized gap: 0.80 GW. Every figure below is a single dated, sourced claim. Current best per series resolves by evidence tier, then date. See the methodology.
| Source | ||||
|---|---|---|---|---|
| Announced | 0.80 GW | 2024-01-01 | reported | journalist report |
| Under construction | 0.30 GW | 2025-10-01 | reported | journalist report |
| Under construction | 0.15 GW | 2024-01-23 | verified | press release |
Construction evidence
Dated satellite imagery of the site itself, oldest to newest, with the campus milestones that landed in each window. This is what the site looked like from orbit while announcements, permits, and energizations were dated into our ledger, so bare land, grading, and building mass tell their own story alongside the paper trail. Sentinel-2 true color, 10 m resolution, cloud-free scenes; click any frame to expand it.
Delivery paceAnnounced Q1 2024 · not yet energized
Dated Sentinel-2 imagery, gated to hand-verified site coordinates. Milestones synthesized from the campus's own capacity ledger, financial claims, and lifecycle events; each chip links to its source. How we source and verify it: satellite construction evidence.
Key facts
Lifecycle
Announced
Energized
PowerHouse Data Centers
Developer
Location
Grid
Land
Announced-to-energized gap
On the data center map
Every tracked data center is on this map, centered on PowerHouse 95 (Spotsylvania) Campus. Pan or zoom out to see how close rivals are building.
In clusterVirginia(338)
The deal
- financier
- Harrison Street · Equity partner
- utility
- Dominion Energy · PJM interconnection
- developer
- PowerHouse Data Centers · Division of American Real Estate Partners (AREP)
- developer
- American Real Estate Partners · Parent of PowerHouse Data Centers; PowerHouse 95 is a joint venture with Harrison Street
Power
- Power source
- grid
- Grid operator
- PJM
- Interconnection
Three 300MW utility substations, 0.90 GW grid interconnect, Permitted. Dominion/PJM interconnection via county-approved SUP
PowerHouse 95 first 300 MW substation, 0.30 GW grid, Under construction. First of three planned 300 MW substations; expected to deliver ~150 MW by Oct 2025
PowerHouse 95 substations 2 and 3 (300 MW each), 0.60 GW grid, Announced. Two additional 300 MW substations planned to reach up to 800 MW total
The PJM grid demand right now: 71.7 GW (EIA-930, 2026-09-27 10:00). PowerHouse 95 (Spotsylvania) Campus's announced 0.80 GW would be 1.1% of the grid's current load.
County water status: No drought in Spotsylvania County, week of 2026-09-22 (US Drought Monitor). Data centers are large water users for cooling; this is the neutral local water picture.
Why here
PowerHouse 95 (Spotsylvania) Campus sits on greenfield in Virginia, Spotsylvania County. It connects to the PJM grid, draws on grid power. This siting summary is composed from the record's held fields, not speculation; see methodology.
Regulatory paper trail
The filings and rules on record for this site and its jurisdiction, most recent first. Each is a sourced, dated artifact you can follow to the primary document.
Timeline
- Aug 2026party addeddeveloper: American Real Estate Partners
- Sep 2026Current: Under construction
Sources
- Special Use Permit (SUP) Cases
- PowerHouse breaks ground on 800MW data center campus in Spotsylvania County
- PowerHouse Data Centers closes on site of 800 MW campus in Spotsylvania
329e5c3e-67ac-40a4-80bb-61e67065a8f4 · Tracked with DEPLOY's verified-vs-claimed methodology. Every term is defined in the glossary. Announced numbers are claims, not built capacity.
Head-to-head
Common questions
What is PowerHouse 95 (Spotsylvania) Campus?
How much power will PowerHouse 95 (Spotsylvania) Campus use?
Who is building PowerHouse 95 (Spotsylvania) Campus?
Is PowerHouse 95 (Spotsylvania) Campus operating yet?
How verified is the data on PowerHouse 95 (Spotsylvania) Campus?
Deploy Watch
Track PowerHouse 95 (Spotsylvania) Campus on Deploy.
We notify you when energized capacity, lifecycle state, or a new dated capacity claim changes against primary-source evidence, not when the developer issues a press release.
Cite this page
DEPLOY. (2026). PowerHouse 95 (Spotsylvania) Campus: AI data center campus record. Retrieved September 27, 2026, from https://registry.deploy.report/datacenters/powerhouse-95-spotsylvania-virginia
More citation formats (MLA, Chicago, BibTeX) →The verified data on this page is available under a Creative Commons Attribution 4.0 license: reuse the facts freely, with attribution to DEPLOY (deploy.report). The prose, design, and any imagery are not included and keep their own rights.
Machine-readable surfaces
- Markdown mirror: /datacenters/powerhouse-95-spotsylvania-virginia.md
- JSON-LD: embedded in this page’s head
- REST API: /v1/datacenters/powerhouse-95-spotsylvania-virginia
- Data documentation: /data
- Query this programmatically: Deploy MCP