QTS Data Centers — Van Wert, Ohio Campus

QTS Data Centers — Van Wert, Ohio Campus is an AI data center campus developed by QTS Data Centers in Ohio, Van Wert. 0.50 GW of capacity has been announced; none is energized yet. The gap is what this page tracks: what is claimed versus what is actually built, each figure dated and sourced.

Announced · QTS Data Centers · Private land · PJM · Van Wert, Ohio, United States


Capacity: announced vs energized

Announced-to-energized gap: 0.50 GW. Every figure below is a single dated, sourced claim. Current best per series resolves by evidence tier, then date. See the methodology.

QTS Data Centers — Van Wert, Ohio Campus capacity claims
Source
Announced0.50 GW2026-05-29claimedjournalist report
Energized0 GW2026-05-29reportedjournalist report

Key facts

announced

Lifecycle

0.50 GW

Announced

0 GW

Energized

PJM

Grid

1

Facilities tracked

On the data center map

Every tracked data center is on this map, centered on QTS Data Centers — Van Wert, Ohio Campus. Pan or zoom out to see how close rivals are building.

Approximate pin. We hold a city-level coordinate for this campus, not a verified site coordinate, so the marker shows the city rather than the parcel. The satellite strip and building outlines stay off until the site coordinate is sourced.

Free to use on your site, with a link back to DEPLOY.
The story of QTS Data Centers — Van Wert, Ohio Campus
Announced capex
$10B
Derived
Cost per MW
$20M/MW

Every figure is one row in the ledger below with its source. Derived rows are pure arithmetic on the rows above (not new claims). Absent lines mean the fact isn't on record yet.

In clusterOhio(141)

The deal

utility
AEP Ohio · Serving utility for the campus; grid-powered.
grid operator
PJM · Northwest Ohio falls in the PJM interconnection.
developer
QTS Data Centers · Blackstone-owned hyperscale developer; site acquired via the Van Wert mega-site.

Power

Power source
grid
Grid operator
PJM
Interconnection

QTS-funded grid infrastructure upgrades (AEP / Indiana Michigan territory, PJM), 0.50 GW grid ppa, Announced. QTS to fund 100% of energy-infrastructure improvements; AEP Ohio / PJM grid.

The PJM grid demand right now: 82.8 GW (EIA-930, 2026-09-27 18:00). QTS Data Centers — Van Wert, Ohio Campus's announced 0.50 GW would be 0.6% of the grid's current load.

Why here

QTS Data Centers — Van Wert, Ohio Campus sits on private land in Ohio, Van Wert. It connects to the PJM grid, draws on grid power. This siting summary is composed from the record's held fields, not speculation; see methodology.

Financial structure

Total announced investment
$10B journalist report

Regulatory paper trail

The filings and rules on record for this site and its jurisdiction, most recent first. Each is a sourced, dated artifact you can follow to the primary document.

NHTSA Recall: Zoox Robotaxi Software Update for Heavy Smoke Visibility (26E044)operational restriction · 2026-07-15 · United States
FCC Proposed Fines Against Drone Companies (July 2026)other · 2026-07-10 · United States
FAA Proposed Rule: Enabling Supersonic Overland Flight (July 2026)operational restriction · 2026-07-02 · United States

Facilities at this campus

Timeline

  1. Aug 2026
    capacity changed
    energized: unknown to 0
  2. Sep 2026
    Current: Announced

Sources

473bb952-2e13-4eb6-91a5-08fd9f8db306 · Tracked with DEPLOY's verified-vs-claimed methodology. Every term is defined in the glossary. Announced numbers are claims, not built capacity.

Head-to-head

Common questions

What is QTS Data Centers — Van Wert, Ohio Campus?
QTS Data Centers — Van Wert, Ohio Campus is an AI data center campus tracked on the DEPLOY registry, located in Van Wert. DEPLOY records its capacity as a dated, sourced ledger: announced gigawatts versus actually energized gigawatts, never a press-release total.
How much power will QTS Data Centers — Van Wert, Ohio Campus use?
QTS Data Centers — Van Wert, Ohio Campus has 0.50 GW of announced capacity on the DEPLOY registry, of which 0 GW is recorded as energized, an announced-to-energized gap of 0.50 GW. Each figure is individually dated and sourced.
Who is building QTS Data Centers — Van Wert, Ohio Campus?
QTS Data Centers is recorded as a party to QTS Data Centers — Van Wert, Ohio Campus on the DEPLOY registry. The full party list, with each role, is on the record.
Is QTS Data Centers — Van Wert, Ohio Campus operating yet?
As of the most recent verification on the DEPLOY registry, QTS Data Centers — Van Wert, Ohio Campus is announced but not yet built. DEPLOY tracks the lifecycle from announced through energized, so the current state reflects sourced evidence, not the original announcement.
How verified is the data on QTS Data Centers — Van Wert, Ohio Campus?
A human editor has reviewed this record for the indexed registry. Every capacity figure is an append-only, dated claim resolved to the highest-evidence tier; superseded claims are kept but excluded from the current view.

Deploy Watch

Track QTS Data Centers — Van Wert, Ohio Campus on Deploy.

We notify you when energized capacity, lifecycle state, or a new dated capacity claim changes against primary-source evidence, not when the developer issues a press release.

Cite this page

DEPLOY. (2026). QTS Data Centers — Van Wert, Ohio Campus: AI data center campus record. Retrieved September 27, 2026, from https://registry.deploy.report/datacenters/qts-van-wert-ohio-campus

More citation formats (MLA, Chicago, BibTeX) →
CC BY 4.0

The verified data on this page is available under a Creative Commons Attribution 4.0 license: reuse the facts freely, with attribution to DEPLOY (deploy.report). The prose, design, and any imagery are not included and keep their own rights.

Machine-readable surfaces