DEPLOY

Data center campus

Cologix Johnstown Campus

Cologix Johnstown Campus is an AI data center campus developed by Cologix in Ohio, Johnstown. 0.80 GW of capacity has been announced; none is energized yet. The gap is what this page tracks: what is claimed versus what is actually built, each figure dated and sourced.

Announced · Cologix · greenfield · PJM · Johnstown, Ohio, United States


Capacity: announced vs energized

Announced-to-energized gap: 0.80 GW. Every figure below is a single dated, sourced claim. Current best per series resolves by evidence tier, then date. See the methodology.

Promised online: 2025. 9 months past the claimed date, with no energized capacity on record. Claimed by Cologix (source).

Cologix Johnstown Campus capacity claims
Source
Announced0.80 GW2024-11-01claimedpress release

Key facts

announced

Lifecycle

0.80 GW

Announced

0 GW

Energized

Cologix

Developer

PJM

Grid

4

Facilities tracked

On the data center map

Every tracked data center is on this map, centered on Cologix Johnstown Campus. Pan or zoom out to see how close rivals are building.

Approximate pin. We hold a city-level coordinate for this campus, not a verified site coordinate, so the marker shows the city rather than the parcel. The satellite strip and building outlines stay off until the site coordinate is sourced.

Free to use on your site, with a link back to DEPLOY.
The story of Cologix Johnstown Campus
Announced capex
$7B
Land owner
Johnstown Land Company
Derived
Cost per MW
$9M/MW

Every figure is one row in the ledger below with its source. Derived rows are pure arithmetic on the rows above (not new claims). Absent lines mean the fact isn't on record yet.

In clusterOhio(141)

The deal

financier
JobsOhio · state economic-development backing cited
developer
Cologix
land owner
Johnstown Land Company · Affiliate of the New Albany Company; sold the 154 acres (price undisclosed).
utility
AEP Ohio · Local electric utility (PJM footprint) serving Licking County / Johnstown.

Power

Power source
grid
Grid operator
PJM
Interconnection

The PJM grid demand right now: 82.8 GW (EIA-930, 2026-09-27 18:00). Cologix Johnstown Campus's announced 0.80 GW would be 1.0% of the grid's current load.

County water status: No drought in Licking County, week of 2026-09-22 (US Drought Monitor). Data centers are large water users for cooling; this is the neutral local water picture.

Silicon on site

Every AI chip publicly attributed to Cologix Johnstown Campus on the DEPLOY registry. Quantity hints are unstructured because underlying disclosures vary by an order of magnitude. Source links per row.

  1. NVIDIA Blackwell capacity for AI-training tenants at the Johnstown campus

    inferredMulti-tenant hyperscale campus; NVIDIA Blackwell tenants inferred from CoreWeave-generation posture.

    Cologix

Why here

Cologix Johnstown Campus sits on greenfield in Ohio, Johnstown. It connects to the PJM grid, draws on grid power. This siting summary is composed from the record's held fields, not speculation; see methodology.

Financial structure

Planned campus investment
$7B. Cologix plans to invest more than $7 billion to develop the Johnstown campus. company filing

Regulatory paper trail

The filings and rules on record for this site and its jurisdiction, most recent first. Each is a sourced, dated artifact you can follow to the primary document.

NHTSA Recall: Zoox Robotaxi Software Update for Heavy Smoke Visibility (26E044)operational restriction · 2026-07-15 · United States
FCC Proposed Fines Against Drone Companies (July 2026)other · 2026-07-10 · United States
FAA Proposed Rule: Enabling Supersonic Overland Flight (July 2026)operational restriction · 2026-07-02 · United States

Facilities at this campus

Timeline

  1. Aug 2026
    party added
    utility: AEP Ohio
  2. Sep 2026
    Current: Announced

Sources

6f07a860-1b32-475f-b4ff-bc63bb17ca86 · Tracked with DEPLOY's verified-vs-claimed methodology. Every term is defined in the glossary. Announced numbers are claims, not built capacity.

Head-to-head

Common questions

What is Cologix Johnstown Campus?
Cologix Johnstown Campus is an AI data center campus tracked on the DEPLOY registry, located in Johnstown. DEPLOY records its capacity as a dated, sourced ledger: announced gigawatts versus actually energized gigawatts, never a press-release total.
How much power will Cologix Johnstown Campus use?
Cologix Johnstown Campus has 0.80 GW of announced capacity on the DEPLOY registry; no energized capacity is yet recorded. Each figure is individually dated and sourced.
Who is building Cologix Johnstown Campus?
Cologix is recorded as a party to Cologix Johnstown Campus on the DEPLOY registry. The full party list, with each role, is on the record.
Is Cologix Johnstown Campus operating yet?
As of the most recent verification on the DEPLOY registry, Cologix Johnstown Campus is announced but not yet built. DEPLOY tracks the lifecycle from announced through energized, so the current state reflects sourced evidence, not the original announcement.
How verified is the data on Cologix Johnstown Campus?
A human editor has reviewed this record for the indexed registry. Every capacity figure is an append-only, dated claim resolved to the highest-evidence tier; superseded claims are kept but excluded from the current view.

Deploy Watch

Track Cologix Johnstown Campus on Deploy.

We notify you when energized capacity, lifecycle state, or a new dated capacity claim changes against primary-source evidence, not when the developer issues a press release.

Cite this page

DEPLOY. (2026). Cologix Johnstown Campus: AI data center campus record. Retrieved September 27, 2026, from https://registry.deploy.report/datacenters/cologix-johnstown-ohio

More citation formats (MLA, Chicago, BibTeX) →
CC BY 4.0

The verified data on this page is available under a Creative Commons Attribution 4.0 license: reuse the facts freely, with attribution to DEPLOY (deploy.report). The prose, design, and any imagery are not included and keep their own rights.

Machine-readable surfaces