Data center campus
Project Cardinal Data Center Campus — Yorkville
Project Cardinal Data Center Campus — Yorkville is an AI data center campus developed by Pioneer Development, LLC in Illinois, Yorkville. 1.80 GW of capacity has been announced; none is energized yet. The gap is what this page tracks: what is claimed versus what is actually built, each figure dated and sourced.
Permitted · Pioneer Development, LLC · greenfield · PJM · Yorkville, Illinois, United States
Capacity: announced vs energized
Announced-to-energized gap: 1.80 GW. Every figure below is a single dated, sourced claim. Current best per series resolves by evidence tier, then date. See the methodology.
Promised online: 2029. 39 months away. Claimed by Pioneer Development, LLC (source).
| Source | ||||
|---|---|---|---|---|
| Announced | 1.80 GW | 2026-03-11 | reported | journalist report |
Construction evidence
Dated satellite imagery of the site itself, oldest to newest, with the campus milestones that landed in each window. This is what the site looked like from orbit while announcements, permits, and energizations were dated into our ledger, so bare land, grading, and building mass tell their own story alongside the paper trail. Sentinel-2 true color, 10 m resolution, cloud-free scenes; click any frame to expand it.
Delivery paceAnnounced Q1 2026 · not yet energized
Dated Sentinel-2 imagery, gated to hand-verified site coordinates. Milestones synthesized from the campus's own capacity ledger, financial claims, and lifecycle events; each chip links to its source. How we source and verify it: satellite construction evidence.
Key facts
Lifecycle
Announced
Energized
Pioneer Development, LLC
Developer
Location
Grid
Land
Announced-to-energized gap
On the data center map
Every tracked data center is on this map, centered on Project Cardinal Data Center Campus — Yorkville. Pan or zoom out to see how close rivals are building.
- Water
- 170K gal/day (654 households)
- Cooling
- 14 two-story data center buildings, ~17M sq ft total (11 bldgs ~1.9M sq ft each + 3 bldgs ~940,000 sq ft); two on-site substations and a switchyard
- Grid
- PJM · Waiting on the utility: ComEd had not granted the site a full power allocation as of March 2026, which the council was told must happen before the project can be finalised. Yorkville approved a development agreement on 10 March 2026 carrying a $51 million up-front payment over four years.
Every figure is one row in the ledger below with its source. Derived rows are pure arithmetic on the rows above (not new claims). Absent lines mean the fact isn't on record yet.
In clusterIllinois(168)
The deal
- developer
- Pioneer Development, LLC · contract purchaser; end user undisclosed
- utility
- ComEd · full power allocation still pending
Power
- Power source
- grid
- Grid operator
- PJM
- Interconnection
- Waiting on the utility: ComEd had not granted the site a full power allocation as of March 2026, which the council was told must happen before the project can be finalised. Yorkville approved a development agreement on 10 March 2026 carrying a $51 million up-front payment over four years.
- Water
- Domestic use quantified, cooling makeup water not yet. Burns & McDonnell, the engineer of record, told Yorkville on 5 September 2025 that domestic demand is a draft 0.17 million gallons a day on average with air-cooled chillers, or 0.25 with water-cooled chillers and dry coolers, peaking at 0.31 and 0.44 respectively on a 1.8 peaking factor. Makeup water for the closed-loop system is explicitly undetermined at this stage, depending on end-user design and water quality, and no ongoing irrigation is assumed. Fire flow is estimated at 2,000 gallons per minute minimum at 20 psi.
The PJM grid demand right now: 84.0 GW (EIA-930, 2026-09-27 20:00). Project Cardinal Data Center Campus — Yorkville's announced 1.80 GW would be 2.1% of the grid's current load.
County water status: No drought in Kendall County, week of 2026-09-22 (US Drought Monitor). Data centers are large water users for cooling; this is the neutral local water picture.
Why here
Project Cardinal Data Center Campus — Yorkville sits on greenfield in Illinois, Yorkville. It connects to the PJM grid, draws on grid power, interconnection is Waiting on the utility: ComEd had not granted the site a full power allocation as of March 2026, which the council was told must happen before the project can be finalised. Yorkville approved a development agreement on 10 March 2026 carrying a $51 million up-front payment over four years.. This siting summary is composed from the record's held fields, not speculation; see methodology.
Financial structure
- Host-community payment (developer to City of Yorkville)
- $51M. $51M upfront commitment from Pioneer Development to the city, paid over four years, per the development agreement approved March 11, 2026 journalist report
- Up-front payment to Yorkville under the development agreement
- $51M. Paid over four years; agreed 10 March 2026. journalist report
Regulatory paper trail
The filings and rules on record for this site and its jurisdiction, most recent first. Each is a sourced, dated artifact you can follow to the primary document.
Investment, workforce and specs
Timeline
- Aug 2026claim recordedmetric:water_gpd=170000
- Sep 2026Current: Permitted
Sources
- Project Cardinal Data Center Campus (case PZC 2025-08)
- Yorkville data center approval comes after nearly 6-hour meeting
- Yorkville data center approval comes after almost 6-hour contentious City Council meeting · Shaw Local
- Project Cardinal - Water Usage memo, Burns & McDonnell · City of Yorkville
1b2f6d79-9113-487a-aa09-6819682ce056 · Tracked with DEPLOY's verified-vs-claimed methodology. Every term is defined in the glossary. Announced numbers are claims, not built capacity.
Common questions
What is Project Cardinal Data Center Campus — Yorkville?
How much power will Project Cardinal Data Center Campus — Yorkville use?
Who is building Project Cardinal Data Center Campus — Yorkville?
Is Project Cardinal Data Center Campus — Yorkville operating yet?
How verified is the data on Project Cardinal Data Center Campus — Yorkville?
Deploy Watch
Track Project Cardinal Data Center Campus — Yorkville on Deploy.
We notify you when energized capacity, lifecycle state, or a new dated capacity claim changes against primary-source evidence, not when the developer issues a press release.
Cite this page
DEPLOY. (2026). Project Cardinal Data Center Campus — Yorkville: AI data center campus record. Retrieved September 27, 2026, from https://registry.deploy.report/datacenters/pioneer-project-cardinal-yorkville-illinois
More citation formats (MLA, Chicago, BibTeX) →The verified data on this page is available under a Creative Commons Attribution 4.0 license: reuse the facts freely, with attribution to DEPLOY (deploy.report). The prose, design, and any imagery are not included and keep their own rights.
Machine-readable surfaces
- Markdown mirror: /datacenters/pioneer-project-cardinal-yorkville-illinois.md
- JSON-LD: embedded in this page’s head
- REST API: /v1/datacenters/pioneer-project-cardinal-yorkville-illinois
- Data documentation: /data
- Query this programmatically: Deploy MCP