Data center campus
Homer City Energy Campus
Homer City Energy Campus is an AI data center campus developed by Homer City Redevelopment (HCR) in Pennsylvania, Homer City. 4.50 GW of capacity has been announced; none is energized yet. The gap is what this page tracks: what is claimed versus what is actually built, each figure dated and sourced.
Under construction · Homer City Redevelopment (HCR) · Brownfield · PJM · Homer City, Pennsylvania, United States
Capacity: announced vs energized
Announced-to-energized gap: 4.50 GW. Every figure below is a single dated, sourced claim. Current best per series resolves by evidence tier, then date. See the methodology.
Promised online: 2027. 15 months away. Claimed by Homer City Redevelopment / Kiewit (source).
| Source | ||||
|---|---|---|---|---|
| Announced | 4.50 GW | 2025-04-02 | claimed | press release |
| Energized | 0 GW | 2026-08-17 | reported | journalist report |
Construction evidence
Dated satellite imagery of the site itself, oldest to newest, with the campus milestones that landed in each window. This is what the site looked like from orbit while announcements, permits, and energizations were dated into our ledger, so bare land, grading, and building mass tell their own story alongside the paper trail. Sentinel-2 true color, 10 m resolution, cloud-free scenes; click any frame to expand it.
Delivery paceAnnounced Q2 2025 · live Q3 2026 · 1 yr 5 mo build
Dated Sentinel-2 imagery, gated to hand-verified site coordinates. Milestones synthesized from the campus's own capacity ledger, financial claims, and lifecycle events; each chip links to its source. How we source and verify it: satellite construction evidence.
Per-building manifest tied to the site polygons and imagery. When we know a building's outline we render it; when we know only its year and capacity we still surface those as first-class rows so the campus total is auditable, not a headline claim. Sorted largest-first; 3 on record.
Manifest totals: 184,067 sqft. Rolled from the per-building rows above.
Key facts
Lifecycle
Announced
Energized
Homer City Redevelopment (HCR)
Developer
Location
Grid
Land
Announced-to-energized gap
On the data center map
Every tracked data center is on this map, centered on Homer City Energy Campus. Pan or zoom out to see how close rivals are building.
- Announced capex
- $10B
- Cooling
- Surface water from Two Lick Creek; intake volume not disclosed, as cooling decisions are left to data center tenants
- Grid
- PJM · Connection already in place: the campus reuses a retired coal plant site that holds firm interconnections to both PJM and NYISO, so the generation build does not depend on a new queue position.
- Cost per MW
- $2M/MW
Every figure is one row in the ledger below with its source. Derived rows are pure arithmetic on the rows above (not new claims). Absent lines mean the fact isn't on record yet.
In clusterPennsylvania(95)
The deal
- grid operator
- PJM · Site sits in PJM territory with existing high-capacity transmission/substations from the former coal plant.
- developer
- Homer City Redevelopment (HCR) · Owner/developer of the former coal-plant brownfield site.
- construction
- Kiewit Power Constructors · EPC contractor.
- construction
- GE Vernova · Turbine supplier: seven 7HA.02 hydrogen-capable gas turbines.
- financier
- Knighthead Capital Management · Financial backer of the redevelopment.
Power
- Power source
- behind the meter gas
- Grid operator
- PJM
- Interconnection
- Connection already in place: the campus reuses a retired coal plant site that holds firm interconnections to both PJM and NYISO, so the generation build does not depend on a new queue position.
- Water
- Two Lick Creek, volume undisclosed. The creek is fed by Two Lick Reservoir, which holds 5 billion gallons at capacity. The permit application does not state how much water the plant will draw, and the operator has said it cannot answer for the campus because different data center tenants have different water needs.
7x GE Vernova 7HA.02 hydrogen-capable gas turbines, 4.50 GW gas, Under construction. Turbine order placed with GE Vernova; first deliveries 2026, generation by 2027. Kiewit is EPC contractor. Interconnects to PJM.
The PJM grid demand right now: 71.6 GW (EIA-930, 2026-09-27 09:00). Homer City Energy Campus's announced 4.50 GW would be 6.3% of the grid's current load.
County water status: No drought in Indiana County, week of 2026-09-22 (US Drought Monitor). Data centers are large water users for cooling; this is the neutral local water picture.
Silicon on site
Every AI chip publicly attributed to Homer City Energy Campus on the DEPLOY registry. Quantity hints are unstructured because underlying disclosures vary by an order of magnitude. Source links per row.
- as of 2025-04-01
Planned 4.5 GW gas-fed AI campus targeting NVIDIA Blackwell tenants
inferredAnnounced as an AI-first campus. Chip mix not yet published; Blackwell inferred from AI-training positioning.
Why here
Homer City Energy Campus sits on brownfield in Pennsylvania, Homer City. It connects to the PJM grid, draws on behind the meter gas power, interconnection is Connection already in place: the campus reuses a retired coal plant site that holds firm interconnections to both PJM and NYISO, so the generation build does not depend on a new queue position.. This siting summary is composed from the record's held fields, not speculation; see methodology.
Financial structure
- Total project investment
- $10B press release
- Announced cost of the on-site generating project
- $10B journalist report
Regulatory paper trail
The filings and rules on record for this site and its jurisdiction, most recent first. Each is a sourced, dated artifact you can follow to the primary document.
Investment, workforce and specs
- Cooling
- Surface water from Two Lick Creek; intake volume not disclosed, as cooling decisions are left to data center tenants source
Timeline
- Aug 2026claim recordedmetric:cooling_type
- Sep 2026Current: Under construction
Sources
- Project Overview | Homer City Redevelopment · Homer City Redevelopment
- Largest US gas-fired power plant planned for data centers in Pennsylvania · Utility Dive
- GE Vernova wins turbine order for 4.5 GW gas-powered data center campus (US) · Enerdata
- Former Homer City Plant to Become a $10 Billion AI Data Center Campus · Construction Review Online
- In Western Pennsylvania, a former coal town gets a gas-fired data center · The Allegheny Front
- Homer City power plant water usage remains unclear · TribLive
1c60d653-887c-4221-ac49-ed56853a4c66 · Tracked with DEPLOY's verified-vs-claimed methodology. Every term is defined in the glossary. Announced numbers are claims, not built capacity.
Head-to-head
Common questions
What is Homer City Energy Campus?
How much power will Homer City Energy Campus use?
Who is building Homer City Energy Campus?
Is Homer City Energy Campus operating yet?
How verified is the data on Homer City Energy Campus?
Deploy Watch
Track Homer City Energy Campus on Deploy.
We notify you when energized capacity, lifecycle state, or a new dated capacity claim changes against primary-source evidence, not when the developer issues a press release.
Cite this page
DEPLOY. (2026). Homer City Energy Campus: AI data center campus record. Retrieved September 27, 2026, from https://registry.deploy.report/datacenters/homer-city-pennsylvania
More citation formats (MLA, Chicago, BibTeX) →The verified data on this page is available under a Creative Commons Attribution 4.0 license: reuse the facts freely, with attribution to DEPLOY (deploy.report). The prose, design, and any imagery are not included and keep their own rights.
Machine-readable surfaces
- Markdown mirror: /datacenters/homer-city-pennsylvania.md
- JSON-LD: embedded in this page’s head
- REST API: /v1/datacenters/homer-city-pennsylvania
- Data documentation: /data
- Query this programmatically: Deploy MCP