Data center campus
Meta Prometheus Data Center (New Albany)
Meta Prometheus Data Center is an AI data center campus developed by Meta Platforms in Ohio, New Albany. 1 GW of capacity has been announced; 0.50 GW is energized. The gap is what this page tracks: what is claimed versus what is actually built, each figure dated and sourced.
Partially energized · Meta Platforms · Private land · PJM · New Albany, Ohio, United States
Capacity: announced vs energized
Announced-to-energized gap: 0.50 GW. Every figure below is a single dated, sourced claim. Current best per series resolves by evidence tier, then date. See the methodology.
Promised online: 2026. Energized capacity is now on record. Claimed by Mark Zuckerberg / Meta (source).
| Source | ||||
|---|---|---|---|---|
| Announced | 1 GW | 2026-05-01 | claimed | journalist report |
| Energized | 0.50 GW | 2026-05-01 | reported | journalist report |
Construction evidence
Dated satellite imagery of the site itself, oldest to newest, with the campus milestones that landed in each window. This is what the site looked like from orbit while announcements, permits, and energizations were dated into our ledger, so bare land, grading, and building mass tell their own story alongside the paper trail. Sentinel-2 true color, 10 m resolution, cloud-free scenes; click any frame to expand it.
Delivery paceAnnounced Q2 2026 · live Q2 2026 · 0 mo build
Dated Sentinel-2 imagery, gated to hand-verified site coordinates. Milestones synthesized from the campus's own capacity ledger, financial claims, and lifecycle events; each chip links to its source. How we source and verify it: satellite construction evidence.
Per-building manifest tied to the site polygons and imagery. When we know a building's outline we render it; when we know only its year and capacity we still surface those as first-class rows so the campus total is auditable, not a headline claim. Sorted largest-first; 6 on record.
Manifest totals: 2,405,553 sqft. Rolled from the per-building rows above.
Key facts
Lifecycle
Announced
Energized
Developer
Location
Grid
Land
Facilities tracked
On the data center map
Every tracked data center is on this map, centered on Meta Prometheus Data Center. Pan or zoom out to see how close rivals are building.
- Announced capex
- $1.5B
- Tenant
- Meta Platforms
- Cost per MW
- $2M/MW
Every figure is one row in the ledger below with its source. Derived rows are pure arithmetic on the rows above (not new claims). Absent lines mean the fact isn't on record yet.
In clusterOhio(141)
The deal
- utility
- AEP Ohio · Grid interconnection utility.
- grid operator
- PJM · AEP Ohio operates within PJM Interconnection.
- construction
- Williams Companies · Building the Socrates South behind-the-meter gas facility.
- utility
- Vistra / Constellation / Oklo / TerraPower · Nuclear power counterparties (PPAs and future SMR/advanced-reactor deals).
- developer
- Meta Platforms · Owner-operator; New Albany campus.
- tenant
- Meta Platforms · Self-tenant; AI supercluster compute.
Power
- Power source
- mixed
- Grid operator
- PJM
- Interconnection
Williams Socrates South (behind-the-meter gas), 0.20 GW gas, Under construction. ~307.5 MW nameplate, ~258 MW at design ambient, 200 MW firm; construction began June 2025, targeted before end of 2026.
Vistra Ohio nuclear PPA, 2.10 GW nuclear, Financed. Meta to buy >2.1 GW from two Vistra nuclear plants in Ohio plus expansions; also TerraPower, Oklo (Aurora Powerhouse, Pike County) and Constellation agreements.
Contracted renewables (Ohio solar / Indiana wind), 0.80 GW solar storage, Financed. Over 800 MW of renewable energy contracted.
The PJM grid demand right now: 74.6 GW (EIA-930, 2026-09-27 05:00). Meta Prometheus Data Center's announced 1 GW would be 1.3% of the grid's current load.
County water status: No drought in Licking County, week of 2026-09-22 (US Drought Monitor). Data centers are large water users for cooling; this is the neutral local water picture.
Silicon on site
Every AI chip publicly attributed to Meta Prometheus Data Center (New Albany) on the DEPLOY registry. Quantity hints are unstructured because underlying disclosures vary by an order of magnitude. Source links per row.
- as of 2025-07-14
NVIDIA Blackwell training capacity at the 1 GW Prometheus site
reported - as of 2024-04-10
Meta's own AI accelerator generation deployed alongside Nvidia at Prometheus
reported - as of 2024-03-12
Nvidia complement to MTIA for training + inference at Prometheus
reported
Why here
Meta Prometheus Data Center sits on private land in Ohio, New Albany. It connects to the PJM grid, draws on mixed power. This siting summary is composed from the record's held fields, not speculation; see methodology.
Financial structure
- Meta New Albany campus investment (to date)
- $1.5B. Cumulative since breaking ground in 2017; understates full Prometheus buildout. journalist report
Regulatory paper trail
The filings and rules on record for this site and its jurisdiction, most recent first. Each is a sourced, dated artifact you can follow to the primary document.
Facilities at this campus
- Meta New Albany Data Centerhyperscale
Timeline
- Aug 2026party addedutility: Vistra / Constellation / Oklo / TerraPower
- Sep 2026Current: Partially energized
Sources
- Meta's Prometheus and Google's Central Ohio Cluster: An AI Data Center Primer · MeasuredAI
- Meet Prometheus: World's highest capacity data center slated to open in Ohio in 2026 · NBC4 WCMH-TV
- Meta will use nuclear power for its New Albany A.I. data center · NBC4 WCMH-TV
d7c13110-4def-4903-9828-a30b405f3afb · Tracked with DEPLOY's verified-vs-claimed methodology. Every term is defined in the glossary. Announced numbers are claims, not built capacity.
Head-to-head
Common questions
What is Meta Prometheus Data Center (New Albany)?
How much power will Meta Prometheus Data Center (New Albany) use?
Who is building Meta Prometheus Data Center (New Albany)?
Is Meta Prometheus Data Center (New Albany) operating yet?
How verified is the data on Meta Prometheus Data Center (New Albany)?
Deploy Watch
Track Meta Prometheus Data Center (New Albany) on Deploy.
We notify you when energized capacity, lifecycle state, or a new dated capacity claim changes against primary-source evidence, not when the developer issues a press release.
Cite this page
DEPLOY. (2026). Meta Prometheus Data Center (New Albany): AI data center campus record. Retrieved September 27, 2026, from https://registry.deploy.report/datacenters/meta-prometheus-ohio
More citation formats (MLA, Chicago, BibTeX) →The verified data on this page is available under a Creative Commons Attribution 4.0 license: reuse the facts freely, with attribution to DEPLOY (deploy.report). The prose, design, and any imagery are not included and keep their own rights.
Machine-readable surfaces
- Markdown mirror: /datacenters/meta-prometheus-ohio.md
- JSON-LD: embedded in this page’s head
- REST API: /v1/datacenters/meta-prometheus-ohio
- Data documentation: /data
- Query this programmatically: Deploy MCP