Project Jade (Crusoe / Tallgrass) AI Data Center Campus

Project Jade (Crusoe / Tallgrass) AI Data Center Campus is an AI data center campus developed by Crusoe in Wyoming, Cheyenne. 10 GW of capacity has been announced; none is energized yet. The gap is what this page tracks: what is claimed versus what is actually built, each figure dated and sourced.

Permitted · Crusoe · greenfield · WECC · Cheyenne, Wyoming, United States


Capacity: announced vs energized

Announced-to-energized gap: 10 GW. Every figure below is a single dated, sourced claim. Current best per series resolves by evidence tier, then date. See the methodology.

Promised online: 2027. 15 months away. Claimed by Crusoe / Tallgrass (developer statements at county approval) (source).

Project Jade (Crusoe / Tallgrass) AI Data Center Campus capacity claims
Source
Announced10 GW2026-01-01reportedjournalist report
Announced1.80 GW2025-07-24reportedpress release

Construction evidence

Dated satellite imagery of the site itself, oldest to newest, with the campus milestones that landed in each window. This is what the site looked like from orbit while announcements, permits, and energizations were dated into our ledger, so bare land, grading, and building mass tell their own story alongside the paper trail. Sentinel-2 true color, 10 m resolution, cloud-free scenes; click any frame to expand it.

Delivery paceAnnounced Q1 2026 · not yet energized

2018-07-01Contains modified Copernicus Sentinel data 2018
2020-07-10Contains modified Copernicus Sentinel data 2020
2022-08-29Contains modified Copernicus Sentinel data 2022
2024-07-31Contains modified Copernicus Sentinel data 2024
2025-08-20Contains modified Copernicus Sentinel data 2025

Dated Sentinel-2 imagery, gated to hand-verified site coordinates. Milestones synthesized from the campus's own capacity ledger, financial claims, and lifecycle events; each chip links to its source. How we source and verify it: satellite construction evidence.

Key facts

permitted

Lifecycle

10 GW

Announced

0 GW

Energized

Crusoe

Developer

WECC

Grid

2

Facilities tracked

On the data center map

Every tracked data center is on this map, centered on Project Jade (Crusoe / Tallgrass) AI Data Center Campus. Pan or zoom out to see how close rivals are building.

Free to use on your site, with a link back to DEPLOY.
The story of Project Jade (Crusoe / Tallgrass) AI Data Center Campus
Announced capex
$50B
Cooling
closed-loop cooling
Grid
WECC · Bring your own power: the campus is paired with the Cheyenne Power Hub, a dedicated 2.7 GW gas plant Tallgrass is building beside it inside the same industrial park, so the compute build does not wait on new grid capacity.
Derived
Cost per MW
$5M/MW

Every figure is one row in the ledger below with its source. Derived rows are pure arithmetic on the rows above (not new claims). Absent lines mean the fact isn't on record yet.

In clusterWyoming(26)

The deal

utility
Tallgrass Energy · Builds BFC Power / Cheyenne Power Hub and CO2 sequestration hub
financier
Blackstone Inc. · Listed by Global Energy Monitor as parent/owner behind Tallgrass Energy on the BFC Power / Cheyenne Power Hub. Tracker-sourced.
developer
Crusoe · Develops the AI data center campus

Power

Power source
behind the meter gas
Grid operator
WECC
Interconnection
Bring your own power: the campus is paired with the Cheyenne Power Hub, a dedicated 2.7 GW gas plant Tallgrass is building beside it inside the same industrial park, so the compute build does not wait on new grid capacity.
Water
On-site deep groundwater wells drilled below the aquifers that supply Laramie County; closed-loop cooling to minimize consumption. Reported initial fill roughly equivalent to 20 households and ongoing annual use less than three households (Cowboy State Daily).

BFC Power / Cheyenne Power Hub, 2.70 GW gas, Permitted. 2.7 GW natural gas-fired generation on 659 acres, built by Tallgrass; $7B investment.

Bloom Energy fuel cells, other, Announced. Fuel cells cited in bring-your-own-power model; capacity unspecified.

BFC Power and Cheyenne Power Hub, 2.70 GW gas, Permitted. 2.7 GW new on-site natural gas generation dedicated to the campus; per Global Energy Monitor configured as two ~1,350 MW combined-cycle units plus aeroderivative turbines. Laramie County site plan approved 2026-01-05; developed by Tallgrass Energy; CO2 sequestration reported up to ~10.6M metric tons/yr. GEM status: pre-construction.

Bloom Energy fuel cell yard, other, Announced. Bloom Energy fuel cells cited as supplemental on-site generation alongside gas turbines.

County water status: Extreme drought (D3) in Laramie County, week of 2026-09-22 (US Drought Monitor). Data centers are large water users for cooling; this is the neutral local water picture.

Why here

Project Jade (Crusoe / Tallgrass) AI Data Center Campus sits on greenfield in Wyoming, Cheyenne. It connects to the WECC grid, draws on behind the meter gas power, interconnection is Bring your own power: the campus is paired with the Cheyenne Power Hub, a dedicated 2.7 GW gas plant Tallgrass is building beside it inside the same industrial park, so the compute build does not wait on new grid capacity.. This siting summary is composed from the record's held fields, not speculation; see methodology.

Financial structure

Total campus capex (Crusoe/Project Jade)
$50B. Reported as 'more than $50 billion' total capital expenditure across full build-out. journalist report
Tallgrass energy infrastructure investment
$7B. $7 billion for on-site natural gas power generation (BFC Power / Cheyenne Power Hub). journalist report

Regulatory paper trail

The filings and rules on record for this site and its jurisdiction, most recent first. Each is a sourced, dated artifact you can follow to the primary document.

NHTSA Recall: Zoox Robotaxi Software Update for Heavy Smoke Visibility (26E044)operational restriction · 2026-07-15 · United States
FCC Proposed Fines Against Drone Companies (July 2026)other · 2026-07-10 · United States
FAA Proposed Rule: Enabling Supersonic Overland Flight (July 2026)operational restriction · 2026-07-02 · United States

Investment, workforce and specs

Capex
more than $50 billion total campus capex source
Cooling
closed-loop cooling source
Construction jobs
as many as 5,000 construction workers source

Facilities at this campus

Timeline

  1. Aug 2026
    party added
    financier: Blackstone Inc.
  2. Sep 2026
    Current: Permitted

Sources

8848cb50-2254-4805-99ad-f2236513df2c · Tracked with DEPLOY's verified-vs-claimed methodology. Every term is defined in the glossary. Announced numbers are claims, not built capacity.

Head-to-head

Common questions

What is Project Jade (Crusoe / Tallgrass) AI Data Center Campus?
Project Jade (Crusoe / Tallgrass) AI Data Center Campus is an AI data center campus tracked on the DEPLOY registry, located in Cheyenne. DEPLOY records its capacity as a dated, sourced ledger: announced gigawatts versus actually energized gigawatts, never a press-release total.
How much power will Project Jade (Crusoe / Tallgrass) AI Data Center Campus use?
Project Jade (Crusoe / Tallgrass) AI Data Center Campus has 10 GW of announced capacity on the DEPLOY registry; no energized capacity is yet recorded. Each figure is individually dated and sourced.
Who is building Project Jade (Crusoe / Tallgrass) AI Data Center Campus?
Crusoe is recorded as a party to Project Jade (Crusoe / Tallgrass) AI Data Center Campus on the DEPLOY registry. The full party list, with each role, is on the record.
Is Project Jade (Crusoe / Tallgrass) AI Data Center Campus operating yet?
As of the most recent verification on the DEPLOY registry, Project Jade (Crusoe / Tallgrass) AI Data Center Campus is permitted. DEPLOY tracks the lifecycle from announced through energized, so the current state reflects sourced evidence, not the original announcement.
How verified is the data on Project Jade (Crusoe / Tallgrass) AI Data Center Campus?
A human editor has reviewed this record for the indexed registry. Every capacity figure is an append-only, dated claim resolved to the highest-evidence tier; superseded claims are kept but excluded from the current view.

Deploy Watch

Track Project Jade (Crusoe / Tallgrass) AI Data Center Campus on Deploy.

We notify you when energized capacity, lifecycle state, or a new dated capacity claim changes against primary-source evidence, not when the developer issues a press release.

Cite this page

DEPLOY. (2026). Project Jade (Crusoe / Tallgrass) AI Data Center Campus: AI data center campus record. Retrieved September 27, 2026, from https://registry.deploy.report/datacenters/crusoe-tallgrass-project-jade-cheyenne