Data center campus
Project Jade (Crusoe / Tallgrass) AI Data Center Campus
Project Jade (Crusoe / Tallgrass) AI Data Center Campus is an AI data center campus developed by Crusoe in Wyoming, Cheyenne. 10 GW of capacity has been announced; none is energized yet. The gap is what this page tracks: what is claimed versus what is actually built, each figure dated and sourced.
Permitted · Crusoe · greenfield · WECC · Cheyenne, Wyoming, United States
Capacity: announced vs energized
Announced-to-energized gap: 10 GW. Every figure below is a single dated, sourced claim. Current best per series resolves by evidence tier, then date. See the methodology.
Promised online: 2027. 15 months away. Claimed by Crusoe / Tallgrass (developer statements at county approval) (source).
| Source | ||||
|---|---|---|---|---|
| Announced | 10 GW | 2026-01-01 | reported | journalist report |
| Announced | 1.80 GW | 2025-07-24 | reported | press release |
Construction evidence
Dated satellite imagery of the site itself, oldest to newest, with the campus milestones that landed in each window. This is what the site looked like from orbit while announcements, permits, and energizations were dated into our ledger, so bare land, grading, and building mass tell their own story alongside the paper trail. Sentinel-2 true color, 10 m resolution, cloud-free scenes; click any frame to expand it.
Delivery paceAnnounced Q1 2026 · not yet energized
Dated Sentinel-2 imagery, gated to hand-verified site coordinates. Milestones synthesized from the campus's own capacity ledger, financial claims, and lifecycle events; each chip links to its source. How we source and verify it: satellite construction evidence.
Key facts
Lifecycle
Announced
Energized
Developer
Location
Grid
Land
Facilities tracked
On the data center map
Every tracked data center is on this map, centered on Project Jade (Crusoe / Tallgrass) AI Data Center Campus. Pan or zoom out to see how close rivals are building.
- Announced capex
- $50B
- Cooling
- closed-loop cooling
- Grid
- WECC · Bring your own power: the campus is paired with the Cheyenne Power Hub, a dedicated 2.7 GW gas plant Tallgrass is building beside it inside the same industrial park, so the compute build does not wait on new grid capacity.
- Cost per MW
- $5M/MW
Every figure is one row in the ledger below with its source. Derived rows are pure arithmetic on the rows above (not new claims). Absent lines mean the fact isn't on record yet.
In clusterWyoming(26)
The deal
- utility
- Tallgrass Energy · Builds BFC Power / Cheyenne Power Hub and CO2 sequestration hub
- financier
- Blackstone Inc. · Listed by Global Energy Monitor as parent/owner behind Tallgrass Energy on the BFC Power / Cheyenne Power Hub. Tracker-sourced.
- developer
- Crusoe · Develops the AI data center campus
Power
- Power source
- behind the meter gas
- Grid operator
- WECC
- Interconnection
- Bring your own power: the campus is paired with the Cheyenne Power Hub, a dedicated 2.7 GW gas plant Tallgrass is building beside it inside the same industrial park, so the compute build does not wait on new grid capacity.
- Water
- On-site deep groundwater wells drilled below the aquifers that supply Laramie County; closed-loop cooling to minimize consumption. Reported initial fill roughly equivalent to 20 households and ongoing annual use less than three households (Cowboy State Daily).
BFC Power / Cheyenne Power Hub, 2.70 GW gas, Permitted. 2.7 GW natural gas-fired generation on 659 acres, built by Tallgrass; $7B investment.
Bloom Energy fuel cells, other, Announced. Fuel cells cited in bring-your-own-power model; capacity unspecified.
BFC Power and Cheyenne Power Hub, 2.70 GW gas, Permitted. 2.7 GW new on-site natural gas generation dedicated to the campus; per Global Energy Monitor configured as two ~1,350 MW combined-cycle units plus aeroderivative turbines. Laramie County site plan approved 2026-01-05; developed by Tallgrass Energy; CO2 sequestration reported up to ~10.6M metric tons/yr. GEM status: pre-construction.
Bloom Energy fuel cell yard, other, Announced. Bloom Energy fuel cells cited as supplemental on-site generation alongside gas turbines.
County water status: Extreme drought (D3) in Laramie County, week of 2026-09-22 (US Drought Monitor). Data centers are large water users for cooling; this is the neutral local water picture.
Why here
Project Jade (Crusoe / Tallgrass) AI Data Center Campus sits on greenfield in Wyoming, Cheyenne. It connects to the WECC grid, draws on behind the meter gas power, interconnection is Bring your own power: the campus is paired with the Cheyenne Power Hub, a dedicated 2.7 GW gas plant Tallgrass is building beside it inside the same industrial park, so the compute build does not wait on new grid capacity.. This siting summary is composed from the record's held fields, not speculation; see methodology.
Financial structure
- Total campus capex (Crusoe/Project Jade)
- $50B. Reported as 'more than $50 billion' total capital expenditure across full build-out. journalist report
- Tallgrass energy infrastructure investment
- $7B. $7 billion for on-site natural gas power generation (BFC Power / Cheyenne Power Hub). journalist report
Regulatory paper trail
The filings and rules on record for this site and its jurisdiction, most recent first. Each is a sourced, dated artifact you can follow to the primary document.
Investment, workforce and specs
Facilities at this campus
- Crusoe Cheyenne ("Jade") Campushyperscale
- Project Jadehyperscale
Timeline
- Aug 2026party addedfinancier: Blackstone Inc.
- Sep 2026Current: Permitted
Sources
- Wyoming Approves Data Center Campus That Includes 2.7 GW of New Natural Gas-Fired Generation
- Crusoe and Tallgrass announce AI data center in Wyoming
8848cb50-2254-4805-99ad-f2236513df2c · Tracked with DEPLOY's verified-vs-claimed methodology. Every term is defined in the glossary. Announced numbers are claims, not built capacity.
Head-to-head
Common questions
What is Project Jade (Crusoe / Tallgrass) AI Data Center Campus?
How much power will Project Jade (Crusoe / Tallgrass) AI Data Center Campus use?
Who is building Project Jade (Crusoe / Tallgrass) AI Data Center Campus?
Is Project Jade (Crusoe / Tallgrass) AI Data Center Campus operating yet?
How verified is the data on Project Jade (Crusoe / Tallgrass) AI Data Center Campus?
Deploy Watch
Track Project Jade (Crusoe / Tallgrass) AI Data Center Campus on Deploy.
We notify you when energized capacity, lifecycle state, or a new dated capacity claim changes against primary-source evidence, not when the developer issues a press release.
Cite this page
DEPLOY. (2026). Project Jade (Crusoe / Tallgrass) AI Data Center Campus: AI data center campus record. Retrieved September 27, 2026, from https://registry.deploy.report/datacenters/crusoe-tallgrass-project-jade-cheyenne
More citation formats (MLA, Chicago, BibTeX) →The verified data on this page is available under a Creative Commons Attribution 4.0 license: reuse the facts freely, with attribution to DEPLOY (deploy.report). The prose, design, and any imagery are not included and keep their own rights.
Machine-readable surfaces
- Markdown mirror: /datacenters/crusoe-tallgrass-project-jade-cheyenne.md