Project Jade (Crusoe / Tallgrass) AI Data Center Campus vs Stargate Abilene

Announced-vs-energized capacity, lifecycle, developer, and location for two AI data center campuses, side by side and individually sourced.


Side by side

Project Jade (Crusoe / Tallgrass) AI Data Center CampusStargate Abilene
Announced capacity10 GW1.20 GW
Energized capacitynot recorded0.30 GW
Announced-to-energized gap10 GW0.90 GW
Lifecyclepermittedpartially energized
DeveloperCrusoeOpenAI
LocationCheyenne, Wyoming, United StatesAbilene, Texas, United States
GridWECCERCOT
Acreage600 acres875 acres

On the map

Common questions

Which is bigger, Project Jade (Crusoe / Tallgrass) AI Data Center Campus or Stargate Abilene?
By announced capacity, Project Jade (Crusoe / Tallgrass) AI Data Center Campus is larger: 10 GW versus 1.20 GW. Announced figures are claims, not built capacity.
Which is further along, Project Jade (Crusoe / Tallgrass) AI Data Center Campus or Stargate Abilene?
Project Jade (Crusoe / Tallgrass) AI Data Center Campus is permitted; Stargate Abilene is partially energized. Energized capacity: not recorded versus 0.30 GW. DEPLOY tracks the announced-to-energized gap, so "further along" means more energized, not more announced.
Where are Project Jade (Crusoe / Tallgrass) AI Data Center Campus and Stargate Abilene?
Project Jade (Crusoe / Tallgrass) AI Data Center Campus is in Cheyenne, Wyoming, United States; Stargate Abilene is in Abilene, Texas, United States. Each record on DEPLOY is sourced and dated.

Compare more on the data center index or the national map. Announced numbers are claims, not built capacity; see the methodology.