Crusoe · Childress. Every figure below is individually sourced and dated.


Part of the tracked campus Crusoe Childress Campus.

The story of Crusoe Childress Campusinherited from campus Crusoe Childress Campus
Jobs
100 permanent reported
Cooling
Closed-loop, non-evaporative liquid cooling
Grid
ERCOT · Grid connected, on land the power partner owns: the 270 acre campus belongs to Lancium, which secures the power interconnect and runs energy orchestration, while Crusoe designs, builds and operates the data center. Behind-the-meter solar and storage sit alongside the grid supply. The announcement does not state the interconnect's approval status.

Every figure is one row in the ledger below with its source. Derived rows are pure arithmetic on the rows above (not new claims). Absent lines mean the fact isn't on record yet.

In clusterTexas(607)

The deal

Inherited from campus Crusoe Childress Campus.

developer
Crusoe · Develops and operates the data center campus.
utility
Lancium · Owns the 270-acre site and develops/manages behind-the-meter energy infrastructure.
grid operator
ERCOT · 1 GW interconnect fully approved by ERCOT.

Investment, workforce and specs

Inherited from campus Crusoe Childress Campus.

Cooling
Closed-loop, non-evaporative liquid cooling source
Construction jobs
Thousands of local construction jobs source
Permanent jobs
More than 100 long-term positions source

Power

Inherited from campus Crusoe Childress Campus. Live grid demand and drought overlay only render on the campus page.

Power source
solar storage
Grid operator
ERCOT
Interconnection
Grid connected, on land the power partner owns: the 270 acre campus belongs to Lancium, which secures the power interconnect and runs energy orchestration, while Crusoe designs, builds and operates the data center. Behind-the-meter solar and storage sit alongside the grid supply. The announcement does not state the interconnect's approval status.
Water
Closed-loop, non-evaporative liquid cooling to reduce water use.

Behind-the-meter solar + battery storage (Lancium), solar storage, Announced. Lancium develops/manages behind-the-meter solar and storage; specific generation capacity not disclosed. 1 GW ERCOT-approved grid interconnect.

Behind-the-meter solar, solar, Announced. On-site solar resource developed and managed by Lancium; capacity not disclosed.

On-site energy storage, storage, Announced. Behind-the-meter energy storage for grid reliability; capacity not disclosed.

Facility record

planned

Status

hyperscale

Type

Crusoe

Operator

Childress

Location

1000 MW

Critical IT

On the data center map

Free to use on your site, with a link back to DEPLOY.

Evidence

Each fact traces to a source. This is what a verified record looks like next to an unsourced directory listing.

  • critical it mw: 1000 (claimed) · source
  • record: Crusoe Childress Campus (reported) · source
  • status: planned (reported) · source

Timeline

  1. Aug 2026
    First recorded
    Added to the DEPLOY registry as a sourced facility record
  2. Sep 2026
    Current: planned

Facility-tier record. For campus-scale announced-vs-energized tracking see the data center index. DEPLOY is neutral infrastructure: what is claimed, what is verified, and when.

Common questions

What is Crusoe Childress Campus?
Crusoe Childress Campus is a data center facility record on the DEPLOY registry, in Childress. Every fact on the record is individually sourced and dated.
Who operates Crusoe Childress Campus?
Crusoe operates Crusoe Childress Campus, per the sourced record on the DEPLOY registry.
Is Crusoe Childress Campus operating?
Crusoe Childress Campus is recorded as planned on the DEPLOY registry, with 1000 MW of critical IT capacity. Each figure traces to a source.
How verified is the data on Crusoe Childress Campus?
A human editor has reviewed this record for the indexed registry. Every rendered fact shows its source: this is what a verified record looks like next to an unsourced directory listing.

Deploy Watch

Track Crusoe Childress Campus on Deploy.

We notify you when operating status, capacity, or the operator changes against a sourced record.

Cite this page

DEPLOY. (2026). Crusoe Childress Campus: data center facility record. Retrieved September 27, 2026, from https://registry.deploy.report/datacenters/facilities/crusoe-childress-tx-campus

More citation formats (MLA, Chicago, BibTeX) →
CC BY 4.0

The verified data on this page is available under a Creative Commons Attribution 4.0 license: reuse the facts freely, with attribution to DEPLOY (deploy.report). The prose, design, and any imagery are not included and keep their own rights.

Machine-readable surfaces