Data center comparison
Crusoe Childress Campus vs Stargate Abilene
Announced-vs-energized capacity, lifecycle, developer, and location for two AI data center campuses, side by side and individually sourced.
Side by side
| Crusoe Childress Campus | Stargate Abilene | |
|---|---|---|
| Announced capacity | 1 GW | 1.20 GW |
| Energized capacity | 0 GW | 0.30 GW |
| Announced-to-energized gap | 1 GW | 0.90 GW |
| Lifecycle | announced | partially energized |
| Developer | Crusoe | OpenAI |
| Location | Childress, Texas, United States | Abilene, Texas, United States |
| Grid | ERCOT | ERCOT |
| Acreage | 270 acres | 875 acres |
On the map
Common questions
Which is bigger, Crusoe Childress Campus or Stargate Abilene?
By announced capacity, Stargate Abilene is larger: 1.20 GW versus 1 GW. Announced figures are claims, not built capacity.
Which is further along, Crusoe Childress Campus or Stargate Abilene?
Crusoe Childress Campus is announced; Stargate Abilene is partially energized. Energized capacity: 0 GW versus 0.30 GW. DEPLOY tracks the announced-to-energized gap, so "further along" means more energized, not more announced.
Where are Crusoe Childress Campus and Stargate Abilene?
Crusoe Childress Campus is in Childress, Texas, United States; Stargate Abilene is in Abilene, Texas, United States. Each record on DEPLOY is sourced and dated.
Compare more on the data center index or the national map. Announced numbers are claims, not built capacity; see the methodology.