Data center campus

Microsoft Fairwater Atlanta / QTS Fayetteville Campus

Microsoft Fairwater Atlanta / QTS Fayetteville Campus is an AI data center campus developed by QTS Data Centers in Georgia, Fayetteville. 1.50 GW of capacity has been announced; 0.34 GW is energized. The gap is what this page tracks: what is claimed versus what is actually built, each figure dated and sourced.

Partially energized · QTS Data Centers · greenfield · other · Fayetteville, Georgia, United States


Capacity: announced vs energized

Announced-to-energized gap: 1.16 GW. Every figure below is a single dated, sourced claim. Current best per series resolves by evidence tier, then date. See the methodology.

Promised online: 2026. Energized capacity is now on record. Claimed by Microsoft / reporting (source).

Microsoft Fairwater Atlanta / QTS Fayetteville Campus capacity claims
Source
Announced1.50 GW2025-01-01reportedutility filing
Energized0.34 GW2025-10-01reportedjournalist report

Key facts

1.50 GW

Announced

0.34 GW

Energized

other

Grid

2

Facilities tracked

On the data center map

Every tracked data center is on this map, centered on Microsoft Fairwater Atlanta / QTS Fayetteville Campus. Pan or zoom out to see how close rivals are building.

Approximate pin. We hold a city-level coordinate for this campus, not a verified site coordinate, so the marker shows the city rather than the parcel. The satellite strip and building outlines stay off until the site coordinate is sourced.

Free to use on your site, with a link back to DEPLOY.
The story of Microsoft Fairwater Atlanta / QTS Fayetteville Campus
Announced capex
$4.6B
Cooling
Closed-loop direct-to-chip liquid cooling
Grid
other · Grid connected, and deliberately grid-only: the Fairwater design strips on-site generation, UPS and dual-corded distribution out of the building entirely and treats the grid itself as the resiliency layer. Serving it took a new Ashley Park 500/230 kV substation with two autotransformers and two new 230 kV lines into the customer substations. Georgia Power treats those costs as trade secrets, so the roughly $158 million figure in circulation is an outside estimate, not a utility disclosure. Georgia Power has told regulators the wider campus approaches 1,500 MW at full build-out.
GPUs
150K >150,000 NVIDIA GB200 GPUs (Fairwater 1)
Tenant
OpenAI
Land owner
Fayette County Development Authority
Derived
Cost per MW
$3M/MW

Every figure is one row in the ledger below with its source. Derived rows are pure arithmetic on the rows above (not new claims). Absent lines mean the fact isn't on record yet.

In clusterGeorgia(161)

The deal

utility
Georgia Power / Southern Company · Ashley Park 500/230-kV substation
operator
Microsoft · Fairwater buildings
developer
QTS Data Centers · campus developer, Blackstone-owned
chip supplier
NVIDIA · GPU supplier (GB200/GB300 Blackwell).
financier
Blackstone · Owner of QTS (Blackstone-backed).
land owner
Fayette County Development Authority · Land seller (~$154M, 2022) and incentive grantor.
tenant
OpenAI · Named customer/tenant of the site (Microsoft newsroom).

Power

Power source
grid
Grid operator
other
Interconnection
Grid connected, and deliberately grid-only: the Fairwater design strips on-site generation, UPS and dual-corded distribution out of the building entirely and treats the grid itself as the resiliency layer. Serving it took a new Ashley Park 500/230 kV substation with two autotransformers and two new 230 kV lines into the customer substations. Georgia Power treats those costs as trade secrets, so the roughly $158 million figure in circulation is an outside estimate, not a utility disclosure. Georgia Power has told regulators the wider campus approaches 1,500 MW at full build-out.
Water
Closed-loop liquid cooling consuming almost zero water; initial fill equivalent to what 20 homes use in a year, no evaporation, ~6-year loop life (Microsoft). Grid-only, no on-site generation and no UPS/gen-sets.

Georgia Power Ashley Park substation + 500 kV line, grid, Under construction. $158M Georgia Power Ashley Park 500/230 kV substation plus 500 kV Ashley Park-Wansley line to serve the campus; grid infrastructure, not on-site generation.

County water status: Moderate drought (D1) in Fayette County, week of 2026-09-22 (US Drought Monitor). Data centers are large water users for cooling; this is the neutral local water picture.

Silicon on site

Every AI chip publicly attributed to Microsoft Fairwater Atlanta / QTS Fayetteville Campus on the DEPLOY registry. Quantity hints are unstructured because underlying disclosures vary by an order of magnitude. Source links per row.

  1. Second Fairwater campus targeting Blackwell-generation compute

    reported

    Microsoft

Why here

Microsoft Fairwater Atlanta / QTS Fayetteville Campus sits on greenfield in Georgia, Fayetteville. It connects to the other grid, draws on grid power, interconnection is Grid connected, and deliberately grid-only: the Fairwater design strips on-site generation, UPS and dual-corded distribution out of the building entirely and treats the grid itself as the resiliency layer. Serving it took a new Ashley Park 500/230 kV substation with two autotransformers and two new 230 kV lines into the customer substations. Georgia Power treats those costs as trade secrets, so the roughly $158 million figure in circulation is an outside estimate, not a utility disclosure. Georgia Power has told regulators the wider campus approaches 1,500 MW at full build-out.. This siting summary is composed from the record's held fields, not speculation; see methodology.

Financial structure

QTS green bond tied to Fayetteville campus
$4.6B. ~$4.6B 10-year investment-grade green bond (April 2026). journalist report
Fayette County Development Authority abatement
Ramp schedule: facility pays 10% of tax bill in year 1, +10%/yr, reaching 100% at 10 years; no total dollar cap disclosed. journalist report
Cost of the Ashley Park 500/230 kV substation built to serve the campus
$158M. Utility-side build: substation, two autotransformers and two new 230 kV lines into the customer substations. Georgia Power treats the cost as a trade secret, so this figure is an outside estimate rather than a utility disclosure. journalist report
QTS planned campus investment
up to $1B. Characterized as 'up to $1 billion' / 'billions'. tracker
QTS campus land purchase
$154M. QTS bought the ~615-acre campus from the Fayette County Development Authority (Aug 2022). journalist report

Regulatory paper trail

The filings and rules on record for this site and its jurisdiction, most recent first. Each is a sourced, dated artifact you can follow to the primary document.

NHTSA Recall: Zoox Robotaxi Software Update for Heavy Smoke Visibility (26E044)operational restriction · 2026-07-15 · United States
FCC Proposed Fines Against Drone Companies (July 2026)other · 2026-07-10 · United States
FAA Proposed Rule: Enabling Supersonic Overland Flight (July 2026)operational restriction · 2026-07-02 · United States

Investment, workforce and specs

Cooling
Closed-loop direct-to-chip liquid cooling source
Permanent jobs
Dozens of technicians (no hard number disclosed) source

Estimated compute: the claimed >150,000 NVIDIA GB200 GPUs (Fairwater 1) chips are on the order of 90x the compute used to train a GPT-4-class model. Derived from the chip-count claim, not measured (basis).

Facilities at this campus

Timeline

  1. Aug 2026
    financial recorded
    transmission_build: Cost of the Ashley Park 500/230 kV substation built to serve the campus
  2. Sep 2026
    Current: Partially energized

Sources

ee24a4c1-dad9-4591-8bc2-dadbd2f88ba7 · Tracked with DEPLOY's verified-vs-claimed methodology. Every term is defined in the glossary. Announced numbers are claims, not built capacity.

Head-to-head

Common questions

What is Microsoft Fairwater Atlanta / QTS Fayetteville Campus?
Microsoft Fairwater Atlanta / QTS Fayetteville Campus is an AI data center campus tracked on the DEPLOY registry, located in Fayetteville. DEPLOY records its capacity as a dated, sourced ledger: announced gigawatts versus actually energized gigawatts, never a press-release total.
How much power will Microsoft Fairwater Atlanta / QTS Fayetteville Campus use?
Microsoft Fairwater Atlanta / QTS Fayetteville Campus has 1.50 GW of announced capacity on the DEPLOY registry, of which 0.34 GW is recorded as energized, an announced-to-energized gap of 1.16 GW. Each figure is individually dated and sourced.
Who is building Microsoft Fairwater Atlanta / QTS Fayetteville Campus?
QTS Data Centers is recorded as a party to Microsoft Fairwater Atlanta / QTS Fayetteville Campus on the DEPLOY registry. The full party list, with each role, is on the record.
Is Microsoft Fairwater Atlanta / QTS Fayetteville Campus operating yet?
As of the most recent verification on the DEPLOY registry, Microsoft Fairwater Atlanta / QTS Fayetteville Campus is partially energized. DEPLOY tracks the lifecycle from announced through energized, so the current state reflects sourced evidence, not the original announcement.
How verified is the data on Microsoft Fairwater Atlanta / QTS Fayetteville Campus?
A human editor has reviewed this record for the indexed registry. Every capacity figure is an append-only, dated claim resolved to the highest-evidence tier; superseded claims are kept but excluded from the current view.

Deploy Watch

Track Microsoft Fairwater Atlanta / QTS Fayetteville Campus on Deploy.

We notify you when energized capacity, lifecycle state, or a new dated capacity claim changes against primary-source evidence, not when the developer issues a press release.

Cite this page

DEPLOY. (2026). Microsoft Fairwater Atlanta / QTS Fayetteville Campus: AI data center campus record. Retrieved September 27, 2026, from https://registry.deploy.report/datacenters/microsoft-fairwater-atlanta-fayetteville-georgia