Data center campus
Microsoft Fairwater Atlanta / QTS Fayetteville Campus
Microsoft Fairwater Atlanta / QTS Fayetteville Campus is an AI data center campus developed by QTS Data Centers in Georgia, Fayetteville. 1.50 GW of capacity has been announced; 0.34 GW is energized. The gap is what this page tracks: what is claimed versus what is actually built, each figure dated and sourced.
Partially energized · QTS Data Centers · greenfield · other · Fayetteville, Georgia, United States
Capacity: announced vs energized
Announced-to-energized gap: 1.16 GW. Every figure below is a single dated, sourced claim. Current best per series resolves by evidence tier, then date. See the methodology.
Promised online: 2026. Energized capacity is now on record. Claimed by Microsoft / reporting (source).
| Source | ||||
|---|---|---|---|---|
| Announced | 1.50 GW | 2025-01-01 | reported | utility filing |
| Energized | 0.34 GW | 2025-10-01 | reported | journalist report |
Key facts
Lifecycle
Announced
Energized
Developer
Location
Grid
Land
Facilities tracked
On the data center map
Every tracked data center is on this map, centered on Microsoft Fairwater Atlanta / QTS Fayetteville Campus. Pan or zoom out to see how close rivals are building.
Approximate pin. We hold a city-level coordinate for this campus, not a verified site coordinate, so the marker shows the city rather than the parcel. The satellite strip and building outlines stay off until the site coordinate is sourced.
- Announced capex
- $4.6B
- Cooling
- Closed-loop direct-to-chip liquid cooling
- Grid
- other · Grid connected, and deliberately grid-only: the Fairwater design strips on-site generation, UPS and dual-corded distribution out of the building entirely and treats the grid itself as the resiliency layer. Serving it took a new Ashley Park 500/230 kV substation with two autotransformers and two new 230 kV lines into the customer substations. Georgia Power treats those costs as trade secrets, so the roughly $158 million figure in circulation is an outside estimate, not a utility disclosure. Georgia Power has told regulators the wider campus approaches 1,500 MW at full build-out.
- GPUs
- 150K >150,000 NVIDIA GB200 GPUs (Fairwater 1)
- Tenant
- OpenAI
- Land owner
- Fayette County Development Authority
- Cost per MW
- $3M/MW
Every figure is one row in the ledger below with its source. Derived rows are pure arithmetic on the rows above (not new claims). Absent lines mean the fact isn't on record yet.
In clusterGeorgia(161)
The deal
- utility
- Georgia Power / Southern Company · Ashley Park 500/230-kV substation
- operator
- Microsoft · Fairwater buildings
- developer
- QTS Data Centers · campus developer, Blackstone-owned
- chip supplier
- NVIDIA · GPU supplier (GB200/GB300 Blackwell).
- financier
- Blackstone · Owner of QTS (Blackstone-backed).
- land owner
- Fayette County Development Authority · Land seller (~$154M, 2022) and incentive grantor.
- tenant
- OpenAI · Named customer/tenant of the site (Microsoft newsroom).
Power
- Power source
- grid
- Grid operator
- other
- Interconnection
- Grid connected, and deliberately grid-only: the Fairwater design strips on-site generation, UPS and dual-corded distribution out of the building entirely and treats the grid itself as the resiliency layer. Serving it took a new Ashley Park 500/230 kV substation with two autotransformers and two new 230 kV lines into the customer substations. Georgia Power treats those costs as trade secrets, so the roughly $158 million figure in circulation is an outside estimate, not a utility disclosure. Georgia Power has told regulators the wider campus approaches 1,500 MW at full build-out.
- Water
- Closed-loop liquid cooling consuming almost zero water; initial fill equivalent to what 20 homes use in a year, no evaporation, ~6-year loop life (Microsoft). Grid-only, no on-site generation and no UPS/gen-sets.
Georgia Power Ashley Park substation + 500 kV line, grid, Under construction. $158M Georgia Power Ashley Park 500/230 kV substation plus 500 kV Ashley Park-Wansley line to serve the campus; grid infrastructure, not on-site generation.
County water status: Moderate drought (D1) in Fayette County, week of 2026-09-22 (US Drought Monitor). Data centers are large water users for cooling; this is the neutral local water picture.
Silicon on site
Every AI chip publicly attributed to Microsoft Fairwater Atlanta / QTS Fayetteville Campus on the DEPLOY registry. Quantity hints are unstructured because underlying disclosures vary by an order of magnitude. Source links per row.
- as of 2025-01-01
Second Fairwater campus targeting Blackwell-generation compute
reported
Why here
Microsoft Fairwater Atlanta / QTS Fayetteville Campus sits on greenfield in Georgia, Fayetteville. It connects to the other grid, draws on grid power, interconnection is Grid connected, and deliberately grid-only: the Fairwater design strips on-site generation, UPS and dual-corded distribution out of the building entirely and treats the grid itself as the resiliency layer. Serving it took a new Ashley Park 500/230 kV substation with two autotransformers and two new 230 kV lines into the customer substations. Georgia Power treats those costs as trade secrets, so the roughly $158 million figure in circulation is an outside estimate, not a utility disclosure. Georgia Power has told regulators the wider campus approaches 1,500 MW at full build-out.. This siting summary is composed from the record's held fields, not speculation; see methodology.
Financial structure
- QTS green bond tied to Fayetteville campus
- $4.6B. ~$4.6B 10-year investment-grade green bond (April 2026). journalist report
- Fayette County Development Authority abatement
- Ramp schedule: facility pays 10% of tax bill in year 1, +10%/yr, reaching 100% at 10 years; no total dollar cap disclosed. journalist report
- Cost of the Ashley Park 500/230 kV substation built to serve the campus
- $158M. Utility-side build: substation, two autotransformers and two new 230 kV lines into the customer substations. Georgia Power treats the cost as a trade secret, so this figure is an outside estimate rather than a utility disclosure. journalist report
- QTS planned campus investment
- up to $1B. Characterized as 'up to $1 billion' / 'billions'. tracker
- QTS campus land purchase
- $154M. QTS bought the ~615-acre campus from the Fayette County Development Authority (Aug 2022). journalist report
Regulatory paper trail
The filings and rules on record for this site and its jurisdiction, most recent first. Each is a sourced, dated artifact you can follow to the primary document.
Investment, workforce and specs
- Cooling
- Closed-loop direct-to-chip liquid cooling source
- Permanent jobs
- Dozens of technicians (no hard number disclosed) source
Estimated compute: the claimed >150,000 NVIDIA GB200 GPUs (Fairwater 1) chips are on the order of 90x the compute used to train a GPT-4-class model. Derived from the chip-count claim, not measured (basis).
Facilities at this campus
- Fayettevillehyperscale
- QTS Fayetteville Data Center Campushyperscale
Timeline
- Aug 2026financial recordedtransmission_build: Cost of the Ashley Park 500/230 kV substation built to serve the campus
- Sep 2026Current: Partially energized
Sources
- Microsoft Fairwater Atlanta: A Grid-Only Gigawatt AI Data Center
- QTS Plans World's Largest Data Center Campus in Fayetteville
- Microsoft launches Atlanta Fairwater data center: two stories, no UPS or gen-sets · Data Center Dynamics
ee24a4c1-dad9-4591-8bc2-dadbd2f88ba7 · Tracked with DEPLOY's verified-vs-claimed methodology. Every term is defined in the glossary. Announced numbers are claims, not built capacity.
Head-to-head
Common questions
What is Microsoft Fairwater Atlanta / QTS Fayetteville Campus?
How much power will Microsoft Fairwater Atlanta / QTS Fayetteville Campus use?
Who is building Microsoft Fairwater Atlanta / QTS Fayetteville Campus?
Is Microsoft Fairwater Atlanta / QTS Fayetteville Campus operating yet?
How verified is the data on Microsoft Fairwater Atlanta / QTS Fayetteville Campus?
Deploy Watch
Track Microsoft Fairwater Atlanta / QTS Fayetteville Campus on Deploy.
We notify you when energized capacity, lifecycle state, or a new dated capacity claim changes against primary-source evidence, not when the developer issues a press release.
Cite this page
DEPLOY. (2026). Microsoft Fairwater Atlanta / QTS Fayetteville Campus: AI data center campus record. Retrieved September 27, 2026, from https://registry.deploy.report/datacenters/microsoft-fairwater-atlanta-fayetteville-georgia
More citation formats (MLA, Chicago, BibTeX) →The verified data on this page is available under a Creative Commons Attribution 4.0 license: reuse the facts freely, with attribution to DEPLOY (deploy.report). The prose, design, and any imagery are not included and keep their own rights.
Machine-readable surfaces
- Markdown mirror: /datacenters/microsoft-fairwater-atlanta-fayetteville-georgia.md
- JSON-LD: embedded in this page’s head
- REST API: /v1/datacenters/microsoft-fairwater-atlanta-fayetteville-georgia
- Data documentation: /data
- Query this programmatically: Deploy MCP