DEPLOY

Data center comparison

Microsoft Fairwater Atlanta / QTS Fayetteville Campus vs QTS Phoenix 3 Campus

Announced-vs-energized capacity, lifecycle, developer, and location for two AI data center campuses, side by side and individually sourced.


Side by side

Microsoft Fairwater Atlanta / QTS Fayetteville CampusQTS Phoenix 3 Campus
Announced capacity1.50 GW0.75 GW
Energized capacity0.34 GWnot recorded
Announced-to-energized gap1.16 GW0.75 GW
Lifecyclepartially energizedpermitted
DeveloperMicrosoftQTS Data Centers
LocationFayetteville, Georgia, United StatesGlendale, Arizona, United States
GridotherWECC
Acreage615 acres375 acres

On the map

Common questions

Which is bigger, Microsoft Fairwater Atlanta / QTS Fayetteville Campus or QTS Phoenix 3 Campus?
By announced capacity, Microsoft Fairwater Atlanta / QTS Fayetteville Campus is larger: 1.50 GW versus 0.75 GW. Announced figures are claims, not built capacity.
Which is further along, Microsoft Fairwater Atlanta / QTS Fayetteville Campus or QTS Phoenix 3 Campus?
Microsoft Fairwater Atlanta / QTS Fayetteville Campus is partially energized; QTS Phoenix 3 Campus is permitted. Energized capacity: 0.34 GW versus not recorded. DEPLOY tracks the announced-to-energized gap, so "further along" means more energized, not more announced.
Where are Microsoft Fairwater Atlanta / QTS Fayetteville Campus and QTS Phoenix 3 Campus?
Microsoft Fairwater Atlanta / QTS Fayetteville Campus is in Fayetteville, Georgia, United States; QTS Phoenix 3 Campus is in Glendale, Arizona, United States. Each record on DEPLOY is sourced and dated.

Compare more on the data center index or the national map. Announced numbers are claims, not built capacity; see the methodology.