Data center facility
Fayetteville
QTS Data Centers · Fayetteville · 1435 Hwy 54 W, Fayetteville, GA 30214. Every figure below is individually sourced and dated.
Part of the tracked campus Microsoft Fairwater Atlanta / QTS Fayetteville Campus.
- Announced capex
- $4.6B
- Cooling
- Closed-loop direct-to-chip liquid cooling
- Grid
- other · Grid connected, and deliberately grid-only: the Fairwater design strips on-site generation, UPS and dual-corded distribution out of the building entirely and treats the grid itself as the resiliency layer. Serving it took a new Ashley Park 500/230 kV substation with two autotransformers and two new 230 kV lines into the customer substations. Georgia Power treats those costs as trade secrets, so the roughly $158 million figure in circulation is an outside estimate, not a utility disclosure. Georgia Power has told regulators the wider campus approaches 1,500 MW at full build-out.
- GPUs
- 150K >150,000 NVIDIA GB200 GPUs (Fairwater 1)
- Tenant
- OpenAI
- Land owner
- Fayette County Development Authority
- Cost per MW
- $3M/MW
Every figure is one row in the ledger below with its source. Derived rows are pure arithmetic on the rows above (not new claims). Absent lines mean the fact isn't on record yet.
In clusterGeorgia(161)
The deal
Inherited from campus Microsoft Fairwater Atlanta / QTS Fayetteville Campus.
- utility
- Georgia Power / Southern Company · Ashley Park 500/230-kV substation
- operator
- Microsoft · Fairwater buildings
- developer
- QTS Data Centers · campus developer, Blackstone-owned
- chip supplier
- NVIDIA · GPU supplier (GB200/GB300 Blackwell).
- financier
- Blackstone · Owner of QTS (Blackstone-backed).
- land owner
- Fayette County Development Authority · Land seller (~$154M, 2022) and incentive grantor.
- tenant
- OpenAI · Named customer/tenant of the site (Microsoft newsroom).
Financial structure
Inherited from campus Microsoft Fairwater Atlanta / QTS Fayetteville Campus.
- QTS green bond tied to Fayetteville campus
- $4.6B. ~$4.6B 10-year investment-grade green bond (April 2026). journalist report
- Fayette County Development Authority abatement
- Ramp schedule: facility pays 10% of tax bill in year 1, +10%/yr, reaching 100% at 10 years; no total dollar cap disclosed. journalist report
- Cost of the Ashley Park 500/230 kV substation built to serve the campus
- $158M. Utility-side build: substation, two autotransformers and two new 230 kV lines into the customer substations. Georgia Power treats the cost as a trade secret, so this figure is an outside estimate rather than a utility disclosure. journalist report
- QTS planned campus investment
- up to $1B. Characterized as 'up to $1 billion' / 'billions'. tracker
- QTS campus land purchase
- $154M. QTS bought the ~615-acre campus from the Fayette County Development Authority (Aug 2022). journalist report
Investment, workforce and specs
Inherited from campus Microsoft Fairwater Atlanta / QTS Fayetteville Campus.
Power
Inherited from campus Microsoft Fairwater Atlanta / QTS Fayetteville Campus. Live grid demand and drought overlay only render on the campus page.
- Power source
- grid
- Grid operator
- other
- Interconnection
- Grid connected, and deliberately grid-only: the Fairwater design strips on-site generation, UPS and dual-corded distribution out of the building entirely and treats the grid itself as the resiliency layer. Serving it took a new Ashley Park 500/230 kV substation with two autotransformers and two new 230 kV lines into the customer substations. Georgia Power treats those costs as trade secrets, so the roughly $158 million figure in circulation is an outside estimate, not a utility disclosure. Georgia Power has told regulators the wider campus approaches 1,500 MW at full build-out.
- Water
- Closed-loop liquid cooling consuming almost zero water; initial fill equivalent to what 20 homes use in a year, no evaporation, ~6-year loop life (Microsoft). Grid-only, no on-site generation and no UPS/gen-sets.
Georgia Power Ashley Park substation + 500 kV line, grid, Under construction. $158M Georgia Power Ashley Park 500/230 kV substation plus 500 kV Ashley Park-Wansley line to serve the campus; grid infrastructure, not on-site generation.
Facility record
On the data center map
Construction evidence
Dated satellite imagery of the site itself, oldest to newest, with the campus milestones that landed in each window. This is what the site looked like from orbit while announcements, permits, and energizations were dated into our ledger, so bare land, grading, and building mass tell their own story alongside the paper trail. Sentinel-2 true color, 10 m resolution, cloud-free scenes; click any frame to expand it.
Delivery paceAnnounced Q1 2025 · live Q4 2025 · 9 mo build
Dated Sentinel-2 imagery, gated to hand-verified site coordinates. Milestones inherited from campus Microsoft Fairwater Atlanta / QTS Fayetteville Campus. How we source and verify it: satellite construction evidence.
Evidence
Each fact traces to a source. This is what a verified record looks like next to an unsourced directory listing.
Timeline
- Aug 2026First recordedAdded to the DEPLOY registry as a sourced facility record
- Sep 2026Current: operating
Facility-tier record. For campus-scale announced-vs-energized tracking see the data center index. DEPLOY is neutral infrastructure: what is claimed, what is verified, and when.
Common questions
What is Fayetteville?
Who operates Fayetteville?
Is Fayetteville operating?
How verified is the data on Fayetteville?
Deploy Watch
Track Fayetteville on Deploy.
We notify you when operating status, capacity, or the operator changes against a sourced record.
Cite this page
DEPLOY. (2026). Fayetteville: data center facility record. Retrieved September 27, 2026, from https://registry.deploy.report/datacenters/facilities/qts-fayetteville-fayetteville-ga
More citation formats (MLA, Chicago, BibTeX) →The verified data on this page is available under a Creative Commons Attribution 4.0 license: reuse the facts freely, with attribution to DEPLOY (deploy.report). The prose, design, and any imagery are not included and keep their own rights.
Machine-readable surfaces
- Markdown mirror: /datacenters/facilities/qts-fayetteville-fayetteville-ga.md
- JSON-LD: embedded in this page’s head
- REST API: /v1/datacenters/facilities/qts-fayetteville-fayetteville-ga
- Data documentation: /data
- Query this programmatically: Deploy MCP