# Microsoft Fairwater Atlanta / QTS Fayetteville Campus

AI data center campus tracked on DEPLOY: announced-vs-energized capacity, each figure dated and sourced.

- **Canonical ID:** ee24a4c1-dad9-4591-8bc2-dadbd2f88ba7
- **Type:** AI data center campus
- **Location:** Fayetteville, Georgia, United States
- **Lifecycle state:** partially_energized
- **Announced capacity (GW):** 1.5
- **Energized capacity (GW):** 0.34
- **Announced-to-energized gap (GW):** 1.16

## Capacity ledger (append-only, dated, sourced)

- announced: 1.5 GW · reported · as of 2025-01-01 · https://measuredai.substack.com/p/microsoft-fairwater-atlanta-data-center
- energized: 0.34 GW · reported · as of 2025-10-01 · https://measuredai.substack.com/p/microsoft-fairwater-atlanta-data-center

## Parties

- Microsoft (operator): https://registry.deploy.report/companies/microsoft
- QTS Data Centers (developer): https://registry.deploy.report/companies/qts-data-centers
- NVIDIA (chip_supplier): https://registry.deploy.report/companies/nvidia
- OpenAI (tenant): https://registry.deploy.report/companies/openai

## Common questions


**What is Microsoft Fairwater Atlanta / QTS Fayetteville Campus?**

Microsoft Fairwater Atlanta / QTS Fayetteville Campus is an AI data center campus tracked on the DEPLOY registry, located in Fayetteville. DEPLOY records its capacity as a dated, sourced ledger: announced gigawatts versus actually energized gigawatts, never a press-release total.

**How much power will Microsoft Fairwater Atlanta / QTS Fayetteville Campus use?**

Microsoft Fairwater Atlanta / QTS Fayetteville Campus has 1.50 GW of announced capacity on the DEPLOY registry, of which 0.34 GW is recorded as energized, an announced-to-energized gap of 1.16 GW. Each figure is individually dated and sourced.

**Is Microsoft Fairwater Atlanta / QTS Fayetteville Campus operating yet?**

As of the most recent verification on the DEPLOY registry, Microsoft Fairwater Atlanta / QTS Fayetteville Campus is partially energized. DEPLOY tracks the lifecycle from announced through energized, so the current state reflects sourced evidence, not the original announcement.

**How verified is the data on Microsoft Fairwater Atlanta / QTS Fayetteville Campus?**

A human editor has reviewed this record for the indexed registry. Every capacity figure is an append-only, dated claim resolved to the highest-evidence tier; superseded claims are kept but excluded from the current view.

## Sources

- Microsoft Fairwater Atlanta: A Grid-Only Gigawatt AI Data Center: https://measuredai.substack.com/p/microsoft-fairwater-atlanta-data-center
- QTS Plans World's Largest Data Center Campus in Fayetteville: https://www.asbn.com/articles/qts-plans-worlds-largest-data-center-campus-in-fayetteville/
- Microsoft launches Atlanta Fairwater data center: two stories, no UPS or gen-sets: https://www.datacenterdynamics.com/en/news/microsoft-launches-atlanta-fairwater-data-center-two-stories-no-ups-or-gen-sets/

Canonical: https://registry.deploy.report/datacenters/microsoft-fairwater-atlanta-fayetteville-georgia
JSON: https://registry.deploy.report/v1/datacenters/microsoft-fairwater-atlanta-fayetteville-georgia