Data center campus
Microsoft Cheyenne Data Center Campus
Microsoft Cheyenne Data Center Campus is a tracked AI data center campus in Wyoming, Cheyenne. Microsoft has operated data centers in Cheyenne since 2012 and on 2026-04-14 announced intent to buy ~3,200 acres south of the city (200-acre Bison Business Park parcel plus adjacent 3,000 acres) to roughly triple its fo
Energized · Microsoft · greenfield · WECC · Cheyenne, Wyoming, United States
Capacity: announced vs energized
| Source |
|---|
Construction evidence
Dated satellite imagery of the site itself, oldest to newest, with the campus milestones that landed in each window. This is what the site looked like from orbit while announcements, permits, and energizations were dated into our ledger, so bare land, grading, and building mass tell their own story alongside the paper trail. Sentinel-2 true color, 10 m resolution, cloud-free scenes; click any frame to expand it.
Dated Sentinel-2 imagery, gated to hand-verified site coordinates. Milestones synthesized from the campus's own capacity ledger, financial claims, and lifecycle events; each chip links to its source. How we source and verify it: satellite construction evidence.
Key facts
Lifecycle
Energized
Developer
Location
Grid
Land
Facilities tracked
On the data center map
Every tracked data center is on this map, centered on Microsoft Cheyenne Data Center Campus. Pan or zoom out to see how close rivals are building.
- Announced capex
- $68M
- Jobs
- 320 permanent reported
- Cost per job
- $213K per permanent job
Every figure is one row in the ledger below with its source. Derived rows are pure arithmetic on the rows above (not new claims). Absent lines mean the fact isn't on record yet.
In clusterWyoming(26)
The deal
- utility
- Black Hills Energy · Large Power Contract Service (LPCS) tariff; Microsoft covers infrastructure upgrade costs
- operator
- Microsoft
Power
- Power source
- grid
- Grid operator
- WECC
- Interconnection
- Water
- Direct evaporative cooling uses water less than 10% of the year; Microsoft commits to replenish an estimated 566M gallons of water. Served by Black Hills Energy under Large Power Contract Service (LPCS) tariff.
Silicon on site
Every AI chip publicly attributed to Microsoft Cheyenne Data Center Campus on the DEPLOY registry. Quantity hints are unstructured because underlying disclosures vary by an order of magnitude. Source links per row.
- as of 2025-01-01
Blackwell-generation training capacity at Cheyenne
inferredSite published as Fairwater-class; specific chip inferred from Microsoft's Blackwell-first stance for new build
Why here
Microsoft Cheyenne Data Center Campus sits on greenfield in Wyoming, Cheyenne. It connects to the WECC grid, draws on grid power. This siting summary is composed from the record's held fields, not speculation; see methodology.
Financial structure
- Off-site infrastructure improvements
- $68M. Completed and future off-site infrastructure improvements associated with Cheyenne datacenter operations. press release
Regulatory paper trail
The filings and rules on record for this site and its jurisdiction, most recent first. Each is a sourced, dated artifact you can follow to the primary document.
Investment, workforce and specs
Facilities at this campus
- Microsoft Bison Business Park Data Centerhyperscale
- Microsoft Cheyenne Business Parkway 2 (CBP2)hyperscale
- Microsoft Cheyenne Business Parkway Data Centerhyperscale
- Microsoft Cheyenne Datacenter Expansion (Southeast Cheyenne)hyperscale
- Microsoft Cheyenne Expansion (Wapiti Trail, 3,200 acres)hyperscale
- Microsoft Cheyenne Highlands (Southeast) Expansionhyperscale
- Microsoft HR Ranch Road Campushyperscale
- Microsoft North Range Business Park Data Centerhyperscale
Timeline
- Aug 2026financial recordedcapex: Off-site infrastructure improvements
- Sep 2026Current: Energized
Sources
- Microsoft announces intent to expand datacenter operations in Cheyenne
- Microsoft plans massive 3,200-acre expansion of Cheyenne data centers
9bf4a473-a657-4b97-8a64-fc31b399d260 · Tracked with DEPLOY's verified-vs-claimed methodology. Every term is defined in the glossary. Announced numbers are claims, not built capacity.
Head-to-head
Common questions
What is Microsoft Cheyenne Data Center Campus?
Who is building Microsoft Cheyenne Data Center Campus?
Is Microsoft Cheyenne Data Center Campus operating yet?
How verified is the data on Microsoft Cheyenne Data Center Campus?
Deploy Watch
Track Microsoft Cheyenne Data Center Campus on Deploy.
We notify you when energized capacity, lifecycle state, or a new dated capacity claim changes against primary-source evidence, not when the developer issues a press release.
Cite this page
DEPLOY. (2026). Microsoft Cheyenne Data Center Campus: AI data center campus record. Retrieved September 27, 2026, from https://registry.deploy.report/datacenters/microsoft-cheyenne-wyoming
More citation formats (MLA, Chicago, BibTeX) →The verified data on this page is available under a Creative Commons Attribution 4.0 license: reuse the facts freely, with attribution to DEPLOY (deploy.report). The prose, design, and any imagery are not included and keep their own rights.
Machine-readable surfaces
- Markdown mirror: /datacenters/microsoft-cheyenne-wyoming.md
- JSON-LD: embedded in this page’s head
- REST API: /v1/datacenters/microsoft-cheyenne-wyoming
- Data documentation: /data
- Query this programmatically: Deploy MCP