Data center campus
Microsoft Fairwater Data Center (Mount Pleasant)
Microsoft Fairwater Data Center is an AI data center campus developed by Microsoft in Wisconsin, Mount Pleasant. 0.45 GW of capacity has been announced; 0.37 GW is energized. The gap is what this page tracks: what is claimed versus what is actually built, each figure dated and sourced.
Partially energized · Microsoft · Former industrial site · MISO · Mount Pleasant, Wisconsin, United States
Capacity: announced vs energized
Announced-to-energized gap: 0.08 GW. Every figure below is a single dated, sourced claim. Current best per series resolves by evidence tier, then date. See the methodology.
Promised online: Q1 2026. Energized capacity is now on record. Claimed by Microsoft (source).
| Source | ||||
|---|---|---|---|---|
| Announced | 0.45 GW | 2025-01-01 | reported | utility filing |
| Energized | 0.37 GW | 2026-04-16 | reported | journalist report |
| Under construction | 2.26 GW | 2028-05-13 | claimed | journalist report |
Construction evidence
Dated satellite imagery of the site itself, oldest to newest, with the campus milestones that landed in each window. This is what the site looked like from orbit while announcements, permits, and energizations were dated into our ledger, so bare land, grading, and building mass tell their own story alongside the paper trail. Sentinel-2 true color, 10 m resolution, cloud-free scenes; click any frame to expand it.
Delivery paceAnnounced Q1 2025 · live Q2 2026 · 1 yr 4 mo build
Dated Sentinel-2 imagery, gated to hand-verified site coordinates. Milestones synthesized from the campus's own capacity ledger, financial claims, and lifecycle events; each chip links to its source. How we source and verify it: satellite construction evidence.
Per-building manifest tied to the site polygons and imagery. When we know a building's outline we render it; when we know only its year and capacity we still surface those as first-class rows so the campus total is auditable, not a headline claim. Sorted largest-first; 3 on record.
Manifest totals: 699,916 sqft. Rolled from the per-building rows above.
Key facts
Lifecycle
Announced
Energized
Developer
Location
Grid
Facilities tracked
On the data center map
Every tracked data center is on this map, centered on Microsoft Fairwater Data Center. Pan or zoom out to see how close rivals are building.
- Announced capex
- $3.3B
- Tenant
- Microsoft / OpenAI
- Cost per MW
- $7M/MW
Every figure is one row in the ledger below with its source. Derived rows are pure arithmetic on the rows above (not new claims). Absent lines mean the fact isn't on record yet.
In clusterWisconsin(43)
The deal
- tenant
- Microsoft / OpenAI · Self-tenant AI supercompute (Azure).
- chip supplier
- NVIDIA · GB200/B200-class GPUs (Epoch cites B200).
- utility
- We Energies · Regulated monopoly; sole grid power supplier, building new gas generation.
- grid operator
- MISO · We Energies operates within MISO.
- developer
- Microsoft · Owner-operator; Fairwater flagship AI datacenter on former Foxconn land.
Power
- Power source
- grid
- Grid operator
- MISO
- Interconnection
- Water
- Closed-loop liquid cooling filled once at construction with no ongoing water draw and no evaporation across about 90% of capacity; the remaining ~10% uses outdoor-air cooling and taps water only during peak summer heat. Microsoft compares annual water use to a single restaurant.
We Energies Oak Creek gas plant (5 simple-cycle turbines), 1.10 GW gas, Permitted. 1,100 MW proposed at the Oak Creek coal site; first turbine delivery May 2026, operations winter 2027-summer 2028.
We Energies Paris gas plant (Kenosha County), 0.13 GW gas, Permitted. 128 MW gas plant near Paris, WI; part of ~$2.77B of PSC-approved generation/transmission justified on Microsoft load.
The MISO grid demand right now: 74.6 GW (EIA-930, 2026-09-27 18:00). Microsoft Fairwater Data Center's announced 0.45 GW would be 0.6% of the grid's current load.
County water status: No drought in Racine County, week of 2026-09-22 (US Drought Monitor). Data centers are large water users for cooling; this is the neutral local water picture.
Silicon on site
Every AI chip publicly attributed to Microsoft Fairwater Data Center (Mount Pleasant) on the DEPLOY registry. Quantity hints are unstructured because underlying disclosures vary by an order of magnitude. Source links per row.
- as of 2025-01-01
Blackwell-generation AI datacenter (Fairwater flagship); Microsoft's next-generation closed-loop cooled AI DC design
reported
Why here
Microsoft Fairwater Data Center sits on former industrial site in Wisconsin, Mount Pleasant. It connects to the MISO grid, draws on grid power. This siting summary is composed from the record's held fields, not speculation; see methodology.
Financial structure
- Microsoft Mount Pleasant campus investment (announced)
- $3.3B. Initial announced investment; Epoch estimates ~$14B deployed to date and ~$85B at full buildout. press release
Regulatory paper trail
The filings and rules on record for this site and its jurisdiction, most recent first. Each is a sourced, dated artifact you can follow to the primary document.
Facilities at this campus
Timeline
- Aug 2026party addedgrid_operator: MISO
- Sep 2026Current: Partially energized
Sources
- Microsoft completes construction on first datacenter facility in Mount Pleasant, Wisconsin · Microsoft Source
- Microsoft Fairwater Wisconsin | AI Data Centers · Epoch AI
- Wisconsin gas plant proposals test state review process · Utility Dive
- Inside the world's most powerful AI datacenter · Microsoft
824d3b90-2903-4335-9716-8f73fb969f7a · Tracked with DEPLOY's verified-vs-claimed methodology. Every term is defined in the glossary. Announced numbers are claims, not built capacity.
Head-to-head
Common questions
What is Microsoft Fairwater Data Center (Mount Pleasant)?
How much power will Microsoft Fairwater Data Center (Mount Pleasant) use?
Who is building Microsoft Fairwater Data Center (Mount Pleasant)?
Is Microsoft Fairwater Data Center (Mount Pleasant) operating yet?
How verified is the data on Microsoft Fairwater Data Center (Mount Pleasant)?
Deploy Watch
Track Microsoft Fairwater Data Center (Mount Pleasant) on Deploy.
We notify you when energized capacity, lifecycle state, or a new dated capacity claim changes against primary-source evidence, not when the developer issues a press release.
Cite this page
DEPLOY. (2026). Microsoft Fairwater Data Center (Mount Pleasant): AI data center campus record. Retrieved September 27, 2026, from https://registry.deploy.report/datacenters/microsoft-fairwater-wisconsin
More citation formats (MLA, Chicago, BibTeX) →The verified data on this page is available under a Creative Commons Attribution 4.0 license: reuse the facts freely, with attribution to DEPLOY (deploy.report). The prose, design, and any imagery are not included and keep their own rights.
Machine-readable surfaces
- Markdown mirror: /datacenters/microsoft-fairwater-wisconsin.md
- JSON-LD: embedded in this page’s head
- REST API: /v1/datacenters/microsoft-fairwater-wisconsin
- Data documentation: /data
- Query this programmatically: Deploy MCP