Data center campus
Meta Social Circle / Stanton Springs Data Center
Meta Social Circle / Stanton Springs Data Center is an AI data center campus developed by Meta Platforms in Georgia, Social Circle. 0.25 GW of capacity has been announced; none is energized yet. The gap is what this page tracks: what is claimed versus what is actually built, each figure dated and sourced.
Partially energized · Meta Platforms · Private land · other · Social Circle, Georgia, United States
Capacity: announced vs energized
Announced-to-energized gap: 0.25 GW. Every figure below is a single dated, sourced claim. Current best per series resolves by evidence tier, then date. See the methodology.
| Source | ||||
|---|---|---|---|---|
| Announced | 0.25 GW | 2023-06-01 | claimed | tracker |
Construction evidence
Dated satellite imagery of the site itself, oldest to newest, with the campus milestones that landed in each window. This is what the site looked like from orbit while announcements, permits, and energizations were dated into our ledger, so bare land, grading, and building mass tell their own story alongside the paper trail. Sentinel-2 true color, 10 m resolution, cloud-free scenes; click any frame to expand it.
Delivery paceAnnounced Q2 2023 · not yet energized
Dated Sentinel-2 imagery, gated to hand-verified site coordinates. Milestones synthesized from the campus's own capacity ledger, financial claims, and lifecycle events; each chip links to its source. How we source and verify it: satellite construction evidence.
Per-building manifest tied to the site polygons and imagery. When we know a building's outline we render it; when we know only its year and capacity we still surface those as first-class rows so the campus total is auditable, not a headline claim. Sorted largest-first; 5 on record.
Manifest totals: 2,347,836 sqft. Rolled from the per-building rows above.
Key facts
Lifecycle
Announced
Energized
Developer
Location
Grid
Land
Facilities tracked
On the data center map
Every tracked data center is on this map, centered on Meta Social Circle / Stanton Springs Data Center. Pan or zoom out to see how close rivals are building.
- Announced capex
- $1.5B
- Jobs
- 400 permanent reported
- Cost per MW
- $6M/MW
- Cost per job
- $4M per permanent job
Every figure is one row in the ledger below with its source. Derived rows are pure arithmetic on the rows above (not new claims). Absent lines mean the fact isn't on record yet.
In clusterGeorgia(161)
The deal
- utility
- Walton EMC / Southern Company · renewable interconnection partnership
- operator
- Meta Platforms · Morning Hornet, LLC
Power
- Power source
- grid
- Grid operator
- other
- Interconnection
- Water
- Served within Southern Company / Walton EMC territory (Southern Company is the balancing authority; not an RTO/ISO).
County water status: Moderate drought (D1) in Newton County, week of 2026-09-22 (US Drought Monitor). Data centers are large water users for cooling; this is the neutral local water picture.
Why here
Meta Social Circle / Stanton Springs Data Center sits on private land in Georgia, Social Circle. It connects to the other grid, draws on grid power. This siting summary is composed from the record's held fields, not speculation; see methodology.
Regulatory paper trail
The filings and rules on record for this site and its jurisdiction, most recent first. Each is a sourced, dated artifact you can follow to the primary document.
Investment, workforce and specs
Facilities at this campus
- Meta Social Circle Campushyperscale
Timeline
- Aug 2026capacity changedannounced: unknown to 0.25
- Sep 2026Current: Partially energized
Sources
- Meta data center — Walton County (interconnection tracker)
- Social Circle officials clear way for second data center
1302fd35-e06f-4ee2-9fa8-0fc870ca71a7 · Tracked with DEPLOY's verified-vs-claimed methodology. Every term is defined in the glossary. Announced numbers are claims, not built capacity.
Head-to-head
Common questions
What is Meta Social Circle / Stanton Springs Data Center?
How much power will Meta Social Circle / Stanton Springs Data Center use?
Who is building Meta Social Circle / Stanton Springs Data Center?
Is Meta Social Circle / Stanton Springs Data Center operating yet?
How verified is the data on Meta Social Circle / Stanton Springs Data Center?
Deploy Watch
Track Meta Social Circle / Stanton Springs Data Center on Deploy.
We notify you when energized capacity, lifecycle state, or a new dated capacity claim changes against primary-source evidence, not when the developer issues a press release.
Cite this page
DEPLOY. (2026). Meta Social Circle / Stanton Springs Data Center: AI data center campus record. Retrieved September 27, 2026, from https://registry.deploy.report/datacenters/meta-social-circle-newton-georgia
More citation formats (MLA, Chicago, BibTeX) →The verified data on this page is available under a Creative Commons Attribution 4.0 license: reuse the facts freely, with attribution to DEPLOY (deploy.report). The prose, design, and any imagery are not included and keep their own rights.
Machine-readable surfaces
- Markdown mirror: /datacenters/meta-social-circle-newton-georgia.md
- JSON-LD: embedded in this page’s head
- REST API: /v1/datacenters/meta-social-circle-newton-georgia
- Data documentation: /data
- Query this programmatically: Deploy MCP