Meta Eagle Mountain Data Center Campus

Meta Eagle Mountain Data Center Campus is an AI data center campus developed by Excelsior Energy Capital in Utah, Eagle Mountain. 1.80 GW of capacity has been announced; 0.20 GW is energized. The gap is what this page tracks: what is claimed versus what is actually built, each figure dated and sourced.

Partially energized · Excelsior Energy Capital · greenfield · WECC · Eagle Mountain, Utah, United States


Capacity: announced vs energized

Announced-to-energized gap: 1.60 GW. Every figure below is a single dated, sourced claim. Current best per series resolves by evidence tier, then date. See the methodology.

Meta Eagle Mountain Data Center Campus capacity claims
Source
Announced1.80 GW2025-11-21claimedjournalist report
Energized0.20 GW2025-02-01reportedpress release

Construction evidence

Dated satellite imagery of the site itself, oldest to newest, with the campus milestones that landed in each window. This is what the site looked like from orbit while announcements, permits, and energizations were dated into our ledger, so bare land, grading, and building mass tell their own story alongside the paper trail. Sentinel-2 true color, 10 m resolution, cloud-free scenes; click any frame to expand it.

Delivery paceAnnounced Q4 2025 · live Q1 2025 · -10 mo build

2018-06-12Contains modified Copernicus Sentinel data 2018
2020-07-06Contains modified Copernicus Sentinel data 2020
2022-06-21Contains modified Copernicus Sentinel data 2022
2024-09-06Contains modified Copernicus Sentinel data 2024
2025-05-31Contains modified Copernicus Sentinel data 2025

Dated Sentinel-2 imagery, gated to hand-verified site coordinates. Milestones synthesized from the campus's own capacity ledger, financial claims, and lifecycle events; each chip links to its source. How we source and verify it: satellite construction evidence.

Key facts

1.80 GW

Announced

0.20 GW

Energized

Excelsior Energy Capital

Developer

WECC

Grid

1

Facilities tracked

On the data center map

Every tracked data center is on this map, centered on Meta Eagle Mountain Data Center Campus. Pan or zoom out to see how close rivals are building.

Free to use on your site, with a link back to DEPLOY.
The story of Meta Eagle Mountain Data Center Campus
Announced capex
$1.5B
Jobs
300 permanent reported
Grid
WECC · Grid connected and operating: the campus is served by Rocky Mountain Power and is serving traffic. Meta is bringing more than 800 MW of new solar onto that grid through nine projects across Iron, Tooele and Carbon counties, carrying about $260 million of local investment.
Derived
Cost per MW
$833K/MW
Cost per job
$5M per permanent job

Every figure is one row in the ledger below with its source. Derived rows are pure arithmetic on the rows above (not new claims). Absent lines mean the fact isn't on record yet.

In clusterUtah(67)

The deal

utility
Rocky Mountain Power (PacifiCorp) · Schedule 34 renewable tariff
developer
Excelsior Energy Capital · Owner/developer of the Faraday Solar project supplying the Meta campus via a 20-year renewable PPA (acquired the project from Parasol/Clenera in 2023).

Power

Power source
grid
Grid operator
WECC
Interconnection
Grid connected and operating: the campus is served by Rocky Mountain Power and is serving traffic. Meta is bringing more than 800 MW of new solar onto that grid through nine projects across Iron, Tooele and Carbon counties, carrying about $260 million of local investment.
Water
Meta funds water restoration equal to 200% of the facility's consumption; in-house designs stated ~80% more water-efficient than industry average.

Faraday Solar, 0.69 GW solar, Energized. 685.3 MWdc; 20-year PPA via Rocky Mountain Power Schedule 34.

Spanish Fork (Mapleton) to Mercer 345 kV transmission line, grid, Announced. 45-mile 345 kV line proposed by Rocky Mountain Power (Aug 2025) to add capacity serving Utah County load growth; delivers to the Mercer substation (built 2019 to serve the Meta campus).

County water status: Extreme drought (D3) in Utah County, week of 2026-09-22 (US Drought Monitor). Data centers are large water users for cooling; this is the neutral local water picture.

Why here

Meta Eagle Mountain Data Center Campus sits on greenfield in Utah, Eagle Mountain. It connects to the WECC grid, draws on grid power, interconnection is Grid connected and operating: the campus is served by Rocky Mountain Power and is serving traffic. Meta is bringing more than 800 MW of new solar onto that grid through nine projects across Iron, Tooele and Carbon counties, carrying about $260 million of local investment.. This siting summary is composed from the record's held fields, not speculation; see methodology.

Financial structure

Meta cumulative campus investment
$1.5B. Total capital investment cited at 2022 Phase 3 expansion toward ~4.5M sq ft campus. journalist report

Regulatory paper trail

The filings and rules on record for this site and its jurisdiction, most recent first. Each is a sourced, dated artifact you can follow to the primary document.

NHTSA Recall: Zoox Robotaxi Software Update for Heavy Smoke Visibility (26E044)operational restriction · 2026-07-15 · United States
FCC Proposed Fines Against Drone Companies (July 2026)other · 2026-07-10 · United States
FAA Proposed Rule: Enabling Supersonic Overland Flight (July 2026)operational restriction · 2026-07-02 · United States

Investment, workforce and specs

Capex
$1.5B source
Construction jobs
1,200 source
Permanent jobs
300 source

Facilities at this campus

Timeline

  1. Aug 2026
    party added
    developer: Excelsior Energy Capital
  2. Sep 2026
    Current: Partially energized

Sources

a76e96bd-5e07-444b-ba92-4995dcb78add · Tracked with DEPLOY's verified-vs-claimed methodology. Every term is defined in the glossary. Announced numbers are claims, not built capacity.

Head-to-head

Common questions

What is Meta Eagle Mountain Data Center Campus?
Meta Eagle Mountain Data Center Campus is an AI data center campus tracked on the DEPLOY registry, located in Eagle Mountain. DEPLOY records its capacity as a dated, sourced ledger: announced gigawatts versus actually energized gigawatts, never a press-release total.
How much power will Meta Eagle Mountain Data Center Campus use?
Meta Eagle Mountain Data Center Campus has 1.80 GW of announced capacity on the DEPLOY registry, of which 0.20 GW is recorded as energized, an announced-to-energized gap of 1.60 GW. Each figure is individually dated and sourced.
Who is building Meta Eagle Mountain Data Center Campus?
Excelsior Energy Capital is recorded as a party to Meta Eagle Mountain Data Center Campus on the DEPLOY registry.
Is Meta Eagle Mountain Data Center Campus operating yet?
As of the most recent verification on the DEPLOY registry, Meta Eagle Mountain Data Center Campus is partially energized. DEPLOY tracks the lifecycle from announced through energized, so the current state reflects sourced evidence, not the original announcement.
How verified is the data on Meta Eagle Mountain Data Center Campus?
A human editor has reviewed this record for the indexed registry. Every capacity figure is an append-only, dated claim resolved to the highest-evidence tier; superseded claims are kept but excluded from the current view.

Deploy Watch

Track Meta Eagle Mountain Data Center Campus on Deploy.

We notify you when energized capacity, lifecycle state, or a new dated capacity claim changes against primary-source evidence, not when the developer issues a press release.

Cite this page

DEPLOY. (2026). Meta Eagle Mountain Data Center Campus: AI data center campus record. Retrieved September 27, 2026, from https://registry.deploy.report/datacenters/meta-eagle-mountain-utah