# Meta Prometheus Data Center (New Albany)

AI data center campus tracked on DEPLOY: announced-vs-energized capacity, each figure dated and sourced.

- **Canonical ID:** d7c13110-4def-4903-9828-a30b405f3afb
- **Type:** AI data center campus
- **Location:** New Albany, Ohio, United States
- **Lifecycle state:** partially_energized
- **Announced capacity (GW):** 1
- **Energized capacity (GW):** 0.5
- **Announced-to-energized gap (GW):** 0.5

## Capacity ledger (append-only, dated, sourced)

- announced: 1 GW · claimed · as of 2026-05-01 · https://measuredai.substack.com/p/meta-prometheus-google-ohio
- energized: 0.5 GW · reported · as of 2026-05-01 · https://measuredai.substack.com/p/meta-prometheus-google-ohio

## Parties

- Meta Platforms (developer): https://registry.deploy.report/companies/meta-platforms
- Meta Platforms (tenant): https://registry.deploy.report/companies/meta-platforms

## Common questions


**What is Meta Prometheus Data Center (New Albany)?**

Meta Prometheus Data Center (New Albany) is an AI data center campus tracked on the DEPLOY registry, located in New Albany. DEPLOY records its capacity as a dated, sourced ledger: announced gigawatts versus actually energized gigawatts, never a press-release total.

**How much power will Meta Prometheus Data Center (New Albany) use?**

Meta Prometheus Data Center (New Albany) has 1 GW of announced capacity on the DEPLOY registry, of which 0.50 GW is recorded as energized, an announced-to-energized gap of 0.50 GW. Each figure is individually dated and sourced.

**Is Meta Prometheus Data Center (New Albany) operating yet?**

As of the most recent verification on the DEPLOY registry, Meta Prometheus Data Center (New Albany) is partially energized. DEPLOY tracks the lifecycle from announced through energized, so the current state reflects sourced evidence, not the original announcement.

**How verified is the data on Meta Prometheus Data Center (New Albany)?**

A human editor has reviewed this record for the indexed registry. Every capacity figure is an append-only, dated claim resolved to the highest-evidence tier; superseded claims are kept but excluded from the current view.

## Sources

- Meta's Prometheus and Google's Central Ohio Cluster: An AI Data Center Primer: https://measuredai.substack.com/p/meta-prometheus-google-ohio
- Meet Prometheus: World's highest capacity data center slated to open in Ohio in 2026: https://www.nbc4i.com/news/local-news/new-albany/meet-prometheus-worlds-highest-capacity-data-center-slated-to-open-in-ohio-in-2026/
- Meta will use nuclear power for its New Albany A.I. data center: https://www.nbc4i.com/news/local-news/new-albany/meta-will-use-nuclear-power-for-its-new-albany-a-i-data-center/

Canonical: https://registry.deploy.report/datacenters/meta-prometheus-ohio
JSON: https://registry.deploy.report/v1/datacenters/meta-prometheus-ohio