Data center comparison
Meta Prometheus Data Center vs Meta Social Circle / Stanton Springs Data Center
Announced-vs-energized capacity, lifecycle, developer, and location for two AI data center campuses, side by side and individually sourced.
Side by side
| Meta Prometheus Data Center | Meta Social Circle / Stanton Springs Data Center | |
|---|---|---|
| Announced capacity | 1 GW | 0.25 GW |
| Energized capacity | 0.50 GW | not recorded |
| Announced-to-energized gap | 0.50 GW | 0.25 GW |
| Lifecycle | partially energized | partially energized |
| Developer | Meta Platforms | Meta Platforms |
| Location | New Albany, Ohio, United States | Social Circle, Georgia, United States |
| Grid | PJM | other |
| Acreage | not recorded | 628 acres |
On the map
Common questions
Which is bigger, Meta Prometheus Data Center or Meta Social Circle / Stanton Springs Data Center?
By announced capacity, Meta Prometheus Data Center is larger: 1 GW versus 0.25 GW. Announced figures are claims, not built capacity.
Which is further along, Meta Prometheus Data Center or Meta Social Circle / Stanton Springs Data Center?
Meta Prometheus Data Center is partially energized; Meta Social Circle / Stanton Springs Data Center is partially energized. Energized capacity: 0.50 GW versus not recorded. DEPLOY tracks the announced-to-energized gap, so "further along" means more energized, not more announced.
Where are Meta Prometheus Data Center and Meta Social Circle / Stanton Springs Data Center?
Meta Prometheus Data Center is in New Albany, Ohio, United States; Meta Social Circle / Stanton Springs Data Center is in Social Circle, Georgia, United States. Each record on DEPLOY is sourced and dated.
Compare more on the data center index or the national map. Announced numbers are claims, not built capacity; see the methodology.