Meta Prometheus Data CenterMeta Social Circle / Stanton Springs Data Center
Announced capacity1 GW0.25 GW
Energized capacity0.50 GWnot recorded
Announced-to-energized gap0.50 GW0.25 GW
Lifecyclepartially energizedpartially energized
DeveloperMeta PlatformsMeta Platforms
LocationNew Albany, Ohio, United StatesSocial Circle, Georgia, United States
GridPJMother
Acreagenot recorded628 acres

On the map

Common questions

Which is bigger, Meta Prometheus Data Center or Meta Social Circle / Stanton Springs Data Center?
By announced capacity, Meta Prometheus Data Center is larger: 1 GW versus 0.25 GW. Announced figures are claims, not built capacity.
Which is further along, Meta Prometheus Data Center or Meta Social Circle / Stanton Springs Data Center?
Meta Prometheus Data Center is partially energized; Meta Social Circle / Stanton Springs Data Center is partially energized. Energized capacity: 0.50 GW versus not recorded. DEPLOY tracks the announced-to-energized gap, so "further along" means more energized, not more announced.
Where are Meta Prometheus Data Center and Meta Social Circle / Stanton Springs Data Center?
Meta Prometheus Data Center is in New Albany, Ohio, United States; Meta Social Circle / Stanton Springs Data Center is in Social Circle, Georgia, United States. Each record on DEPLOY is sourced and dated.