Meta Eagle Mountain Data Center CampusMeta Prometheus Data Center
Announced capacity1.80 GW1 GW
Energized capacity0.20 GW0.50 GW
Announced-to-energized gap1.60 GW0.50 GW
Lifecyclepartially energizedpartially energized
DeveloperMeta PlatformsMeta Platforms
LocationEagle Mountain, Utah, United StatesNew Albany, Ohio, United States
GridWECCPJM
Acreagenot recordednot recorded

On the map

Common questions

Which is bigger, Meta Eagle Mountain Data Center Campus or Meta Prometheus Data Center?
By announced capacity, Meta Eagle Mountain Data Center Campus is larger: 1.80 GW versus 1 GW. Announced figures are claims, not built capacity.
Which is further along, Meta Eagle Mountain Data Center Campus or Meta Prometheus Data Center?
Meta Eagle Mountain Data Center Campus is partially energized; Meta Prometheus Data Center is partially energized. Energized capacity: 0.20 GW versus 0.50 GW. DEPLOY tracks the announced-to-energized gap, so "further along" means more energized, not more announced.
Where are Meta Eagle Mountain Data Center Campus and Meta Prometheus Data Center?
Meta Eagle Mountain Data Center Campus is in Eagle Mountain, Utah, United States; Meta Prometheus Data Center is in New Albany, Ohio, United States. Each record on DEPLOY is sourced and dated.

Compare more on the data center index or the national map. Announced numbers are claims, not built capacity; see the methodology.