DEPLOY

Data center facility

Cologix Johnstown Campus

Cologix · Johnstown · 12017 Duncan Plains Road, Johnstown, OH 43031. Every figure below is individually sourced and dated.


Part of the tracked campus Cologix Johnstown Campus.

The story of Cologix Johnstown Campusinherited from campus Cologix Johnstown Campus
Announced capex
$7B
Land owner
Johnstown Land Company
Derived
Cost per MW
$9M/MW

Every figure is one row in the ledger below with its source. Derived rows are pure arithmetic on the rows above (not new claims). Absent lines mean the fact isn't on record yet.

In clusterOhio(141)

The deal

Inherited from campus Cologix Johnstown Campus.

financier
JobsOhio · state economic-development backing cited
developer
Cologix
land owner
Johnstown Land Company · Affiliate of the New Albany Company; sold the 154 acres (price undisclosed).
utility
AEP Ohio · Local electric utility (PJM footprint) serving Licking County / Johnstown.

Financial structure

Inherited from campus Cologix Johnstown Campus.

Planned campus investment
$7B. Cologix plans to invest more than $7 billion to develop the Johnstown campus. company filing

Power

Inherited from campus Cologix Johnstown Campus. Live grid demand and drought overlay only render on the campus page.

Power source
grid
Grid operator
PJM
Interconnection

Facility record

under construction

Status

hyperscale

Type

Cologix

Operator

Johnstown

Location

800 MW

Critical IT

120,000 sqft

Building

On the data center map

Free to use on your site, with a link back to DEPLOY.

Construction evidence

Dated satellite imagery of the site itself, oldest to newest, with the campus milestones that landed in each window. This is what the site looked like from orbit while announcements, permits, and energizations were dated into our ledger, so bare land, grading, and building mass tell their own story alongside the paper trail. Sentinel-2 true color, 10 m resolution, cloud-free scenes; click any frame to expand it.

Delivery paceAnnounced Q4 2024 · not yet energized

2018-06-14Contains modified Copernicus Sentinel data 2018
2020-06-08Contains modified Copernicus Sentinel data 2020
2022-06-03Contains modified Copernicus Sentinel data 2022
2024-09-05Contains modified Copernicus Sentinel data 2024
2025-08-01Contains modified Copernicus Sentinel data 2025

Dated Sentinel-2 imagery, gated to hand-verified site coordinates. Milestones inherited from campus Cologix Johnstown Campus. How we source and verify it: satellite construction evidence.

Evidence

Each fact traces to a source. This is what a verified record looks like next to an unsourced directory listing.

  • buildingSqft: 120000 (reported) · source · COL7 single building (gross 2M campus figure omitted)
  • critical it mw: 800 (claimed) · source
  • record: Cologix Johnstown Campus (reported) · source
  • status: under_construction (reported) · source
  • streetAddress: 12017 Duncan Plains Road, Johnstown, OH 43031 (reported) · source · COL7, first building of the Johnstown campus

Timeline

  1. Aug 2026
    First recorded
    Added to the DEPLOY registry as a sourced facility record
  2. Sep 2026
    Current: under construction

Facility-tier record. For campus-scale announced-vs-energized tracking see the data center index. DEPLOY is neutral infrastructure: what is claimed, what is verified, and when.

Common questions

What is Cologix Johnstown Campus?
Cologix Johnstown Campus is a data center facility record on the DEPLOY registry, in Johnstown. Every fact on the record is individually sourced and dated.
Who operates Cologix Johnstown Campus?
Cologix operates Cologix Johnstown Campus, per the sourced record on the DEPLOY registry.
Is Cologix Johnstown Campus operating?
Cologix Johnstown Campus is recorded as under construction on the DEPLOY registry, with 800 MW of critical IT capacity. Each figure traces to a source.
How verified is the data on Cologix Johnstown Campus?
A human editor has reviewed this record for the indexed registry. Every rendered fact shows its source: this is what a verified record looks like next to an unsourced directory listing.

Deploy Watch

Track Cologix Johnstown Campus on Deploy.

We notify you when operating status, capacity, or the operator changes against a sourced record.

Cite this page

DEPLOY. (2026). Cologix Johnstown Campus: data center facility record. Retrieved September 27, 2026, from https://registry.deploy.report/datacenters/facilities/cologix-johnstown-campus-oh

More citation formats (MLA, Chicago, BibTeX) →
CC BY 4.0

The verified data on this page is available under a Creative Commons Attribution 4.0 license: reuse the facts freely, with attribution to DEPLOY (deploy.report). The prose, design, and any imagery are not included and keep their own rights.

Machine-readable surfaces