DEPLOY

Data center comparison

Cologix Johnstown Campus vs PORTS-Pike Technology Campus

Announced-vs-energized capacity, lifecycle, developer, and location for two AI data center campuses, side by side and individually sourced.


Side by side

Cologix Johnstown CampusPORTS-Pike Technology Campus
Announced capacity0.80 GW10 GW
Energized capacitynot recorded0 GW
Announced-to-energized gap0.80 GW10 GW
Lifecycleannouncedannounced
DeveloperCologixSB Energy
LocationJohnstown, Ohio, United StatesPiketon, Ohio, United States
GridPJMPJM
Acreage154 acresnot recorded

On the map

Common questions

Which is bigger, Cologix Johnstown Campus or PORTS-Pike Technology Campus?
By announced capacity, PORTS-Pike Technology Campus is larger: 10 GW versus 0.80 GW. Announced figures are claims, not built capacity.
Which is further along, Cologix Johnstown Campus or PORTS-Pike Technology Campus?
Cologix Johnstown Campus is announced; PORTS-Pike Technology Campus is announced. Energized capacity: not recorded versus 0 GW. DEPLOY tracks the announced-to-energized gap, so "further along" means more energized, not more announced.
Where are Cologix Johnstown Campus and PORTS-Pike Technology Campus?
Cologix Johnstown Campus is in Johnstown, Ohio, United States; PORTS-Pike Technology Campus is in Piketon, Ohio, United States. Each record on DEPLOY is sourced and dated.

Compare more on the data center index or the national map. Announced numbers are claims, not built capacity; see the methodology.