Data center comparison
PowerHouse 95 (Spotsylvania) Campus vs Prince William Digital Gateway
Announced-vs-energized capacity, lifecycle, developer, and location for two AI data center campuses, side by side and individually sourced.
Side by side
| PowerHouse 95 (Spotsylvania) Campus | Prince William Digital Gateway | |
|---|---|---|
| Announced capacity | 0.80 GW | 1.70 GW |
| Energized capacity | not recorded | not recorded |
| Announced-to-energized gap | 0.80 GW | 1.70 GW |
| Lifecycle | under construction | cancelled |
| Developer | PowerHouse Data Centers | Compass Datacenters |
| Location | Spotsylvania County, Virginia, United States | Gainesville, Virginia, United States |
| Grid | PJM | PJM |
| Acreage | 145 acres | 2,100 acres |
On the map
Common questions
Which is bigger, PowerHouse 95 (Spotsylvania) Campus or Prince William Digital Gateway?
By announced capacity, Prince William Digital Gateway is larger: 1.70 GW versus 0.80 GW. Announced figures are claims, not built capacity.
Which is further along, PowerHouse 95 (Spotsylvania) Campus or Prince William Digital Gateway?
PowerHouse 95 (Spotsylvania) Campus is under construction; Prince William Digital Gateway is cancelled. Energized capacity: not recorded versus not recorded. DEPLOY tracks the announced-to-energized gap, so "further along" means more energized, not more announced.
Where are PowerHouse 95 (Spotsylvania) Campus and Prince William Digital Gateway?
PowerHouse 95 (Spotsylvania) Campus is in Spotsylvania County, Virginia, United States; Prince William Digital Gateway is in Gainesville, Virginia, United States. Each record on DEPLOY is sourced and dated.
Compare more on the data center index or the national map. Announced numbers are claims, not built capacity; see the methodology.