| Meta Beaver Dam Data Center | Meta Eagle Mountain Data Center Campus | |
|---|---|---|
| Announced capacity | 0.22 GW | 1.80 GW |
| Energized capacity | not recorded | 0.20 GW |
| Announced-to-energized gap | 0.22 GW | 1.60 GW |
| Lifecycle | under construction | partially energized |
| Developer | Meta Platforms | Meta Platforms |
| Location | Beaver Dam, Wisconsin, United States | Eagle Mountain, Utah, United States |
| Grid | MISO | WECC |
| Acreage | not recorded | not recorded |
On the map
Common questions
Which is bigger, Meta Beaver Dam Data Center or Meta Eagle Mountain Data Center Campus?
By announced capacity, Meta Eagle Mountain Data Center Campus is larger: 1.80 GW versus 0.22 GW. Announced figures are claims, not built capacity.
Which is further along, Meta Beaver Dam Data Center or Meta Eagle Mountain Data Center Campus?
Meta Beaver Dam Data Center is under construction; Meta Eagle Mountain Data Center Campus is partially energized. Energized capacity: not recorded versus 0.20 GW. DEPLOY tracks the announced-to-energized gap, so "further along" means more energized, not more announced.
Where are Meta Beaver Dam Data Center and Meta Eagle Mountain Data Center Campus?
Meta Beaver Dam Data Center is in Beaver Dam, Wisconsin, United States; Meta Eagle Mountain Data Center Campus is in Eagle Mountain, Utah, United States. Each record on DEPLOY is sourced and dated.