Data center facility
Google Midlothian Data Center (5th building)
Google · Midlothian · 3441 Railport Parkway, Midlothian, TX. Every figure below is individually sourced and dated.
Part of the tracked campus Google Midlothian Campus (Alamo Mission).
- Announced capex
- $880M
Every figure is one row in the ledger below with its source. Derived rows are pure arithmetic on the rows above (not new claims). Absent lines mean the fact isn't on record yet.
In clusterTexas(607)
The deal
Inherited from campus Google Midlothian Campus (Alamo Mission).
Financial structure
Inherited from campus Google Midlothian Campus (Alamo Mission).
- Sharka Building 5 (fifth Midlothian data center)
- $880M. One-story, 288,000 sq ft data center at 3441 Railport Parkway; TDLR project registered Dec 8, 2025 (estimates subject to change) journalist report
Investment, workforce and specs
Inherited from campus Google Midlothian Campus (Alamo Mission).
- Capex
- Fifth data center building (project Sharka), 288,000 sq ft source
Power
Inherited from campus Google Midlothian Campus (Alamo Mission). Live grid demand and drought overlay only render on the campus page.
- Power source
- grid
- Grid operator
- ERCOT
- Interconnection
Facility record
On the data center map
Construction evidence
Dated satellite imagery of the site itself, oldest to newest, with the campus milestones that landed in each window. This is what the site looked like from orbit while announcements, permits, and energizations were dated into our ledger, so bare land, grading, and building mass tell their own story alongside the paper trail. Sentinel-2 true color, 10 m resolution, cloud-free scenes; click any frame to expand it.
Dated Sentinel-2 imagery, gated to hand-verified site coordinates. Milestones inherited from campus Google Midlothian Campus (Alamo Mission). How we source and verify it: satellite construction evidence.
Evidence
Each fact traces to a source. This is what a verified record looks like next to an unsourced directory listing.
Timeline
- Aug 2026First recordedAdded to the DEPLOY registry as a sourced facility record
- Sep 2026Current: planned
Facility-tier record. For campus-scale announced-vs-energized tracking see the data center index. DEPLOY is neutral infrastructure: what is claimed, what is verified, and when.
Common questions
What is Google Midlothian Data Center (5th building)?
Who operates Google Midlothian Data Center (5th building)?
Is Google Midlothian Data Center (5th building) operating?
How verified is the data on Google Midlothian Data Center (5th building)?
Deploy Watch
Track Google Midlothian Data Center (5th building) on Deploy.
We notify you when operating status, capacity, or the operator changes against a sourced record.
Cite this page
DEPLOY. (2026). Google Midlothian Data Center (5th building): data center facility record. Retrieved September 27, 2026, from https://registry.deploy.report/datacenters/facilities/google-midlothian-fifth-building-ellis-tx
More citation formats (MLA, Chicago, BibTeX) →The verified data on this page is available under a Creative Commons Attribution 4.0 license: reuse the facts freely, with attribution to DEPLOY (deploy.report). The prose, design, and any imagery are not included and keep their own rights.
Machine-readable surfaces
- Markdown mirror: /datacenters/facilities/google-midlothian-fifth-building-ellis-tx.md
- JSON-LD: embedded in this page’s head
- REST API: /v1/datacenters/facilities/google-midlothian-fifth-building-ellis-tx
- Data documentation: /data
- Query this programmatically: Deploy MCP