Core Scientific / CoreWeave Muskogee HPC Campus

Core Scientific / CoreWeave Muskogee HPC Campus is an AI data center campus developed by Core Scientific in Oklahoma, Muskogee County. 1.50 GW of capacity has been announced; none is energized yet. The gap is what this page tracks: what is claimed versus what is actually built, each figure dated and sourced.

Under construction · Core Scientific · Private land · SPP · Muskogee, Muskogee County, Oklahoma, United States


Capacity: announced vs energized

Announced-to-energized gap: 1.50 GW. Every figure below is a single dated, sourced claim. Current best per series resolves by evidence tier, then date. See the methodology.

Promised online: 2026. 3 months away. Claimed by Core Scientific / CoreWeave (source).

Core Scientific / CoreWeave Muskogee HPC Campus capacity claims
Source
Announced1.50 GW2025-06-01claimedjournalist report
Under construction0.07 GW2024-11-18verifiedcompany filing
Under construction0.10 GW2024-06-01reportedpress release

Construction evidence

Dated satellite imagery of the site itself, oldest to newest, with the campus milestones that landed in each window. This is what the site looked like from orbit while announcements, permits, and energizations were dated into our ledger, so bare land, grading, and building mass tell their own story alongside the paper trail. Sentinel-2 true color, 10 m resolution, cloud-free scenes; click any frame to expand it.

Delivery paceAnnounced Q2 2025 · not yet energized

2018-06-01Contains modified Copernicus Sentinel data 2018
2020-08-14Contains modified Copernicus Sentinel data 2020
2022-06-25Contains modified Copernicus Sentinel data 2022
2024-06-14Contains modified Copernicus Sentinel data 2024
2025-06-29Contains modified Copernicus Sentinel data 2025

Dated Sentinel-2 imagery, gated to hand-verified site coordinates. Milestones synthesized from the campus's own capacity ledger, financial claims, and lifecycle events; each chip links to its source. How we source and verify it: satellite construction evidence.

Key facts

1.50 GW

Announced

0 GW

Energized

SPP

Grid

5

Facilities tracked

On the data center map

Every tracked data center is on this map, centered on Core Scientific / CoreWeave Muskogee HPC Campus. Pan or zoom out to see how close rivals are building.

Free to use on your site, with a link back to DEPLOY.
The story of Core Scientific / CoreWeave Muskogee HPC Campus
Announced capex
$8.7B
Jobs
150 permanent reported
Grid
SPP · Served by Oklahoma Gas & Electric. Core Scientific announced on 7 May 2026 that it is buying Polaris Technologies for about $421 million in cash, bringing 440 MW of gross power already contracted with OG&E and an on-site substation with it.
Tenant
CoreWeave
Land owner
Port Muskogee
Derived
Cost per MW
$6M/MW
Cost per job
$58M per permanent job

Every figure is one row in the ledger below with its source. Derived rows are pure arithmetic on the rows above (not new claims). Absent lines mean the fact isn't on record yet.

In clusterMuskogee County(11)·Oklahoma(46)

The deal

developer
Core Scientific · Site developer and operator
land owner
Port Muskogee · Industrial park / port authority partner
chip supplier
NVIDIA · GPUs hosted for CoreWeave
tenant
CoreWeave · HPC hosting lessee for Nvidia GPU compute

Power

Power source
grid
Grid operator
SPP
Interconnection
Served by Oklahoma Gas & Electric. Core Scientific announced on 7 May 2026 that it is buying Polaris Technologies for about $421 million in cash, bringing 440 MW of gross power already contracted with OG&E and an on-site substation with it.
Water
Not published. Core Scientific's own page for the site talks about power, connectivity and expansion room, and mentions cooling only as one of the things the facility provides. It names no cooling method, water source or volume.

The SPP grid demand right now: 36.9 GW (EIA-930, 2026-09-27 19:00). Core Scientific / CoreWeave Muskogee HPC Campus's announced 1.50 GW would be 4.1% of the grid's current load.

County water status: Severe drought (D2) in Muskogee County, week of 2026-09-22 (US Drought Monitor). Data centers are large water users for cooling; this is the neutral local water picture.

Why here

Core Scientific / CoreWeave Muskogee HPC Campus sits on private land in Oklahoma, Muskogee County. It connects to the SPP grid, draws on grid power, interconnection is Served by Oklahoma Gas & Electric. Core Scientific announced on 7 May 2026 that it is buying Polaris Technologies for about $421 million in cash, bringing 440 MW of gross power already contracted with OG&E and an on-site substation with it.. This siting summary is composed from the record's held fields, not speculation; see methodology.

Financial structure

CoreWeave HPC hosting contracts with Core Scientific (portfolio, not Muskogee alone)
$8.7B. ~$8.7B potential value over 12-year contracts across six sites; ~590 MW total contracted journalist report
Total capital investment
$4B. Core Scientific IR: 'more than $4 billion in capital investment' company filing

Regulatory paper trail

The filings and rules on record for this site and its jurisdiction, most recent first. Each is a sourced, dated artifact you can follow to the primary document.

NHTSA Recall: Zoox Robotaxi Software Update for Heavy Smoke Visibility (26E044)operational restriction · 2026-07-15 · United States
FCC Proposed Fines Against Drone Companies (July 2026)other · 2026-07-10 · United States
FAA Proposed Rule: Enabling Supersonic Overland Flight (July 2026)operational restriction · 2026-07-02 · United States

Investment, workforce and specs

Capex
CoreWeave 500 MW hosting contract valued at $8.7B over 12-year terms (each with two 5-year options); Muskogee is one facility within it source
Permanent jobs
150 jobs, average salaries exceeding $65,000 source

Facilities at this campus

Timeline

  1. Aug 2026
    party linked
    tenant: linked externalName "CoreWeave" to company coreweave
  2. Sep 2026
    Current: Under construction

Sources

6db978fa-8c95-4c64-96a1-0a4271e38943 · Tracked with DEPLOY's verified-vs-claimed methodology. Every term is defined in the glossary. Announced numbers are claims, not built capacity.

Head-to-head

Common questions

What is Core Scientific / CoreWeave Muskogee HPC Campus?
Core Scientific / CoreWeave Muskogee HPC Campus is an AI data center campus tracked on the DEPLOY registry, located in Muskogee. DEPLOY records its capacity as a dated, sourced ledger: announced gigawatts versus actually energized gigawatts, never a press-release total.
How much power will Core Scientific / CoreWeave Muskogee HPC Campus use?
Core Scientific / CoreWeave Muskogee HPC Campus has 1.50 GW of announced capacity on the DEPLOY registry; no energized capacity is yet recorded. Each figure is individually dated and sourced.
Who is building Core Scientific / CoreWeave Muskogee HPC Campus?
Core Scientific is recorded as a party to Core Scientific / CoreWeave Muskogee HPC Campus on the DEPLOY registry. The full party list, with each role, is on the record.
Is Core Scientific / CoreWeave Muskogee HPC Campus operating yet?
As of the most recent verification on the DEPLOY registry, Core Scientific / CoreWeave Muskogee HPC Campus is under construction. DEPLOY tracks the lifecycle from announced through energized, so the current state reflects sourced evidence, not the original announcement.
How verified is the data on Core Scientific / CoreWeave Muskogee HPC Campus?
A human editor has reviewed this record for the indexed registry. Every capacity figure is an append-only, dated claim resolved to the highest-evidence tier; superseded claims are kept but excluded from the current view.

Deploy Watch

Track Core Scientific / CoreWeave Muskogee HPC Campus on Deploy.

We notify you when energized capacity, lifecycle state, or a new dated capacity claim changes against primary-source evidence, not when the developer issues a press release.

Cite this page

DEPLOY. (2026). Core Scientific / CoreWeave Muskogee HPC Campus: AI data center campus record. Retrieved September 27, 2026, from https://registry.deploy.report/datacenters/coreweave-core-scientific-muskogee-oklahoma

More citation formats (MLA, Chicago, BibTeX) →
CC BY 4.0

The verified data on this page is available under a Creative Commons Attribution 4.0 license: reuse the facts freely, with attribution to DEPLOY (deploy.report). The prose, design, and any imagery are not included and keep their own rights.

Machine-readable surfaces