Stargate Doña Ana County / Project Jupiter (New Mexico)

Stargate Doña Ana County / Project Jupiter is an AI data center campus developed by Oracle in New Mexico, Santa Teresa. 2.20 GW of capacity has been announced; none is energized yet. The gap is what this page tracks: what is claimed versus what is actually built, each figure dated and sourced.

Under construction · Oracle · Private land · WECC · Santa Teresa, New Mexico, United States


Capacity: announced vs energized

Announced-to-energized gap: 2.20 GW. Every figure below is a single dated, sourced claim. Current best per series resolves by evidence tier, then date. See the methodology.

Promised online: Q4 2026. 2 months away. Claimed by STACK Infrastructure / BorderPlex Digital Assets (source).

Stargate Doña Ana County / Project Jupiter (New Mexico) capacity claims
Source
Announced2.20 GW2026-04-17claimedjournalist report
Energized0 GW2026-07-01reportedjournalist report

Key facts

2.20 GW

Announced

0 GW

Energized

Oracle

Developer

WECC

Grid

1

Facilities tracked

Reported facts

Structured facts sourced from citations already on this record. Each fact traces to a source in the References section below.

Also known as
Project Jupiter
Location
Doña Ana County, New Mexico (Santa Teresa area)
Lifecycle (reported)
Under construction; foundation work seen in satellite imagery
Planned capacity (reported)
About 2.2 GW; part of about 5.5 GW across three Oracle-led sites
Cooling
Closed-loop; about 20,000 gal/day domestic water proposed
On-site power
Two natural-gas microgrids; net-zero target by 2045
First GW target
H2 2026; initial operations Q4 2026
Incentive
Industrial revenue bond approved
Utility
El Paso Electric
Force majeure (reported, Sep 2026)
Oracle sent a force majeure notice on payment timing; Oracle says schedule unchanged.
Delay (reported, Sep 2026)
About one-year delay reported; Blue Owl holds about $3B of equity
Open issues (reported, Oct 2026)
Gas supply, air permit and land access unresolved; pipeline in service Feb 1 2027.
Renewable energy RFP (company-stated, Sep 2026)
Oracle seeks proposals for 2 GW of new New Mexico solar, wind and geothermal deliverable 2027 to 2031, toward 100% carbon-free energy matching for the campus by 2031.

On the data center map

Every tracked data center is on this map, centered on Stargate Doña Ana County / Project Jupiter. Pan or zoom out to see how close rivals are building.

Approximate pin. We hold a city-level coordinate for this campus, not a verified site coordinate, so the marker shows the city rather than the parcel. The satellite strip and building outlines stay off until the site coordinate is sourced.

Free to use on your site, with a link back to DEPLOY.
The story of Stargate Doña Ana County / Project Jupiter (New Mexico)
Jobs
750 permanent reported
Water
20K gal/day (77 households)
Cooling
Closed-loop cooling system
Tenant
OpenAI

Every figure is one row in the ledger below with its source. Derived rows are pure arithmetic on the rows above (not new claims). Absent lines mean the fact isn't on record yet.

In clusterNew Mexico(29)

The deal

developer
STACK Infrastructure · Developer/builder of Project Jupiter (four buildings).
tenant
OpenAI · Anchor tenant / Stargate program lead.
developer
Oracle · Oracle-led site under the Stargate expansion; contracts compute to OpenAI.
chip supplier
NVIDIA · GPU supplier across the Stargate program.
developer
BorderPlex Digital Assets · Austin-based co-developer of Project Jupiter alongside STACK Infrastructure.
utility
El Paso Electric · Regional utility serving the Santa Teresa / Doña Ana County area (WECC).

Power

Power source
behind the meter gas
Grid operator
WECC
Interconnection
Water
Closed-loop cooling; proposed domestic water use ~20,000 gallons/day; on-site microgrid targeting net-zero emissions by 2045.

Project Jupiter on-site natural gas microgrids, gas, Under construction. Two natural gas microgrids to power the campus behind the meter; individual capacity not disclosed (0.0 = unknown, not zero).

On-site natural gas turbine microgrid, gas, Announced. Natural gas turbine system with microgrid designed to meet net-zero emission targets by 2045.

County water status: No drought in Dona Ana County, week of 2026-11-03 (US Drought Monitor). Data centers are large water users for cooling; this is the neutral local water picture.

Silicon on site

Every AI chip publicly attributed to Stargate Doña Ana County / Project Jupiter (New Mexico) on the DEPLOY registry. Quantity hints are unstructured because underlying disclosures vary by an order of magnitude. Source links per row.

  1. Planned Blackwell capacity (Nvidia default for new Stargate builds; specific SKU pending disclosure)

    inferredInferred from Stargate program's consistent Blackwell posture per OpenAI + Nvidia partnership; upgrade when G42/OpenAI confirms

    OpenAI

Why here

Stargate Doña Ana County / Project Jupiter sits on private land in New Mexico, Santa Teresa. It connects to the WECC grid, draws on behind the meter gas power. This siting summary is composed from the record's held fields, not speculation; see methodology.

Financial structure

Industrial revenue bond approved
up to $165B. Up to $165 billion industrial revenue bond approved by Doña Ana County commissioners to finance the campus. journalist report

Regulatory paper trail

The filings and rules on record for this site and its jurisdiction, most recent first. Each is a sourced, dated artifact you can follow to the primary document.

NHTSA Recall: Zoox Robotaxi Software Update for Heavy Smoke Visibility (26E044)operational restriction · 2026-07-15 · United States
FCC Proposed Fines Against Drone Companies (July 2026)other · 2026-07-10 · United States

Investment, workforce and specs

Cooling
Closed-loop cooling system source
Construction jobs
~2,500 construction jobs over a decade source
Permanent jobs
~750 permanent positions (salaries ~$75k-$100k) source
Water (gal/day)
~20,000 gallons/day proposed domestic water use source

Facilities at this campus

Timeline

  1. Aug 2026
    party added
    utility: El Paso Electric
  2. Nov 2026
    Current: Under construction

Sources

4c5d91e2-9598-4b3c-9128-702828bf4251 · Tracked with DEPLOY's verified-vs-claimed methodology. Every term is defined in the glossary. Announced numbers are claims, not built capacity.

Head-to-head

Common questions

What is Stargate Doña Ana County / Project Jupiter (New Mexico)?
Stargate Doña Ana County / Project Jupiter (New Mexico) is an AI data center campus tracked on the DEPLOY registry, located in Santa Teresa. DEPLOY records its capacity as a dated, sourced ledger: announced gigawatts versus actually energized gigawatts, never a press-release total.
How much power will Stargate Doña Ana County / Project Jupiter (New Mexico) use?
Stargate Doña Ana County / Project Jupiter (New Mexico) has 2.20 GW of announced capacity on the DEPLOY registry, of which 0 GW is recorded as energized, an announced-to-energized gap of 2.20 GW. Each figure is individually dated and sourced.
Who is building Stargate Doña Ana County / Project Jupiter (New Mexico)?
Oracle is recorded as a party to Stargate Doña Ana County / Project Jupiter (New Mexico) on the DEPLOY registry. The full party list, with each role, is on the record.
Is Stargate Doña Ana County / Project Jupiter (New Mexico) operating yet?
As of the most recent verification on the DEPLOY registry, Stargate Doña Ana County / Project Jupiter (New Mexico) is under construction. DEPLOY tracks the lifecycle from announced through energized, so the current state reflects sourced evidence, not the original announcement.
How verified is the data on Stargate Doña Ana County / Project Jupiter (New Mexico)?
This record has been checked against its cited sources by automated agents for the indexed registry; it has not been individually reviewed by a person. Every capacity figure is an append-only, dated claim resolved to the highest-evidence tier; superseded claims are kept but excluded from the current view.

Deploy Watch

Track Stargate Doña Ana County / Project Jupiter (New Mexico) on Deploy.

We notify you when energized capacity, lifecycle state, or a new dated capacity claim changes against primary-source evidence, not when the developer issues a press release.

Cite this page

DEPLOY. (2026). Stargate Doña Ana County / Project Jupiter (New Mexico): AI data center campus record. Retrieved November 11, 2026, from https://registry.deploy.report/datacenters/stargate-dona-ana-county-new-mexico

More citation formats (MLA, Chicago, BibTeX) →
CC BY 4.0

The verified data on this page is available under a Creative Commons Attribution 4.0 license: reuse the facts freely, with attribution to DEPLOY (deploy.report). The prose, design, and any imagery are not included and keep their own rights.

Machine-readable surfaces