Stargate Doña Ana County / Project Jupiter vs Stargate Norway

Announced-vs-energized capacity, lifecycle, developer, and location for two AI data center campuses, side by side and individually sourced.


Side by side

Stargate Doña Ana County / Project JupiterStargate Norway
Announced capacity2.20 GW0.23 GW
Energized capacity0 GW0 GW
Announced-to-energized gap2.20 GW0.23 GW
Lifecycleunder constructionunder construction
DeveloperSTACK InfrastructureNscale
LocationSanta Teresa, New Mexico, United StatesNarvik, Nordland, Norway
GridWECCother
Acreage1,400 acresnot recorded

On the map

Common questions

Which is bigger, Stargate Doña Ana County / Project Jupiter or Stargate Norway?
By announced capacity, Stargate Doña Ana County / Project Jupiter is larger: 2.20 GW versus 0.23 GW. Announced figures are claims, not built capacity.
Which is further along, Stargate Doña Ana County / Project Jupiter or Stargate Norway?
Stargate Doña Ana County / Project Jupiter is under construction; Stargate Norway is under construction. Energized capacity: 0 GW versus 0 GW. DEPLOY tracks the announced-to-energized gap, so "further along" means more energized, not more announced.
Where are Stargate Doña Ana County / Project Jupiter and Stargate Norway?
Stargate Doña Ana County / Project Jupiter is in Santa Teresa, New Mexico, United States; Stargate Norway is in Narvik, Nordland, Norway. Each record on DEPLOY is sourced and dated.

Compare more on the data center index or the national map. Announced numbers are claims, not built capacity; see the methodology.