Stargate Saline TownshipStargate Doña Ana County / Project Jupiter
Announced capacity1 GW2.20 GW
Energized capacity0 GW0 GW
Announced-to-energized gap1 GW2.20 GW
Lifecycleunder constructionunder construction
DeveloperRelated DigitalSTACK Infrastructure
LocationSaline Township, Michigan, United StatesSanta Teresa, New Mexico, United States
GridMISOWECC
Acreagenot recorded1,400 acres

On the map

Common questions

Which is bigger, Stargate Saline Township or Stargate Doña Ana County / Project Jupiter?
By announced capacity, Stargate Doña Ana County / Project Jupiter is larger: 2.20 GW versus 1 GW. Announced figures are claims, not built capacity.
Which is further along, Stargate Saline Township or Stargate Doña Ana County / Project Jupiter?
Stargate Saline Township is under construction; Stargate Doña Ana County / Project Jupiter is under construction. Energized capacity: 0 GW versus 0 GW. DEPLOY tracks the announced-to-energized gap, so "further along" means more energized, not more announced.
Where are Stargate Saline Township and Stargate Doña Ana County / Project Jupiter?
Stargate Saline Township is in Saline Township, Michigan, United States; Stargate Doña Ana County / Project Jupiter is in Santa Teresa, New Mexico, United States. Each record on DEPLOY is sourced and dated.