Data center campus
Vermaland La Osa Data Center Park (Pinal County)
Vermaland La Osa Data Center Park is an AI data center campus developed by Vermaland, LLC in Arizona, Eloy. 1 GW of capacity has been announced; none is energized yet. The gap is what this page tracks: what is claimed versus what is actually built, each figure dated and sourced.
Rumored · Vermaland, LLC · greenfield · WECC · Eloy, Arizona, United States
Capacity: announced vs energized
Announced-to-energized gap: 1 GW. Every figure below is a single dated, sourced claim. Current best per series resolves by evidence tier, then date. See the methodology.
| Source | ||||
|---|---|---|---|---|
| Announced | 1 GW | 2026-05-01 | reported | journalist report |
| Announced | 3 GW | 2025-09-01 | claimed | county docket |
Key facts
Lifecycle
Announced
Energized
Vermaland, LLC
Developer
Location
Grid
Land
Announced-to-energized gap
On the data center map
Every tracked data center is on this map, centered on Vermaland La Osa Data Center Park. Pan or zoom out to see how close rivals are building.
- Announced capex
- $33B
- Grid
- WECC · A mix, with gas first and solar to follow: a gas-fired plant on 480 acres of the site provides initial power while the solar component is developed, alongside two large solar projects nearby and an application to the Arizona State Land Department for solar on state land. Of 3,374 acres, about 1,910 are for data centers and employment and 983 stay open space, against a ceiling of about 3 GW.
- Cost per MW
- $33M/MW
Every figure is one row in the ledger below with its source. Derived rows are pure arithmetic on the rows above (not new claims). Absent lines mean the fact isn't on record yet.
In clusterArizona(149)
The deal
- developer
- Vermaland, LLC · CEO Kuldip Verma; EPS Group Inc. civil engineer/planner.
Power
- Power source
- behind the meter gas
- Grid operator
- WECC
- Interconnection
- A mix, with gas first and solar to follow: a gas-fired plant on 480 acres of the site provides initial power while the solar component is developed, alongside two large solar projects nearby and an application to the Arizona State Land Department for solar on state land. Of 3,374 acres, about 1,910 are for data centers and employment and 983 stay open space, against a ceiling of about 3 GW.
- Water
- Site located along the Green Canal south of Eloy, Pinal County.
On-site gas-fired generation (~480 acres), gas, Announced. Behind-the-meter gas plant proposed as initial power; specific MW not stated.
La Osa on-site gas generation, gas, Announced. Originally two on-site natural-gas facilities plus utility-scale BESS; revised to a single gas-fired plant after the 80% scale-back. Pinal County land-use panel gave first recommendation to advance the rezone.
County water status: Severe drought (D2) in Pinal County, week of 2026-09-22 (US Drought Monitor). Data centers are large water users for cooling; this is the neutral local water picture.
Why here
Vermaland La Osa Data Center Park sits on greenfield in Arizona, Eloy. It connects to the WECC grid, draws on behind the meter gas power, interconnection is A mix, with gas first and solar to follow: a gas-fired plant on 480 acres of the site provides initial power while the solar component is developed, alongside two large solar projects nearby and an application to the Arizona State Land Department for solar on state land. Of 3,374 acres, about 1,910 are for data centers and employment and 983 stay open space, against a ceiling of about 3 GW.. This siting summary is composed from the record's held fields, not speculation; see methodology.
Financial structure
- Proposed total investment (~$33B)
- $33B. Developer figure for the original full-scale La Osa proposal. tracker
Regulatory paper trail
The filings and rules on record for this site and its jurisdiction, most recent first. Each is a sourced, dated artifact you can follow to the primary document.
Timeline
- Aug 2026financial recordedcapex: Proposed total investment (~$33B)
- Sep 2026Current: Rumored
Sources
- State's Largest Data Center Project Part of Vermaland Pinal Plan
- Pinal County officials seek more guidance on large-scale data centers ahead of La Osa decision
7181d3aa-298b-4b24-8284-dac3c43239b6 · Tracked with DEPLOY's verified-vs-claimed methodology. Every term is defined in the glossary. Announced numbers are claims, not built capacity.
Head-to-head
Common questions
What is Vermaland La Osa Data Center Park (Pinal County)?
How much power will Vermaland La Osa Data Center Park (Pinal County) use?
Who is building Vermaland La Osa Data Center Park (Pinal County)?
Is Vermaland La Osa Data Center Park (Pinal County) operating yet?
How verified is the data on Vermaland La Osa Data Center Park (Pinal County)?
Deploy Watch
Track Vermaland La Osa Data Center Park (Pinal County) on Deploy.
We notify you when energized capacity, lifecycle state, or a new dated capacity claim changes against primary-source evidence, not when the developer issues a press release.
Cite this page
DEPLOY. (2026). Vermaland La Osa Data Center Park (Pinal County): AI data center campus record. Retrieved September 27, 2026, from https://registry.deploy.report/datacenters/vermaland-la-osa-pinal
More citation formats (MLA, Chicago, BibTeX) →The verified data on this page is available under a Creative Commons Attribution 4.0 license: reuse the facts freely, with attribution to DEPLOY (deploy.report). The prose, design, and any imagery are not included and keep their own rights.
Machine-readable surfaces
- Markdown mirror: /datacenters/vermaland-la-osa-pinal.md
- JSON-LD: embedded in this page’s head
- REST API: /v1/datacenters/vermaland-la-osa-pinal
- Data documentation: /data
- Query this programmatically: Deploy MCP