Data center campus
Microsoft Goodyear Data Center Campus (PHX70)
Microsoft Goodyear Data Center Campus is an AI data center campus developed by Microsoft Azure in Arizona, Goodyear. 0.26 GW of capacity has been announced; none is energized yet. The gap is what this page tracks: what is claimed versus what is actually built, each figure dated and sourced.
Partially energized · Microsoft Azure · Private land · WECC · Goodyear, Arizona, United States
Capacity: announced vs energized
Announced-to-energized gap: 0.26 GW. Every figure below is a single dated, sourced claim. Current best per series resolves by evidence tier, then date. See the methodology.
Promised online: 2027. 15 months away. Claimed by Blackridge Research project tracker (source).
| Source | ||||
|---|---|---|---|---|
| Announced | 0.26 GW | 2025-06-01 | claimed | tracker |
Key facts
Lifecycle
Announced
Energized
Microsoft Azure
Developer
Location
Grid
Land
Announced-to-energized gap
On the data center map
Every tracked data center is on this map, centered on Microsoft Goodyear Data Center Campus. Pan or zoom out to see how close rivals are building.
In clusterArizona(149)
The deal
- operator
- Microsoft Azure
- utility
- Arizona Public Service (APS)
Power
- Power source
- grid
- Grid operator
- WECC
- Interconnection
- Water
- Microsoft committed ~$36M toward a ~$90M expansion of Goodyear wastewater treatment; targets ~42M gallons/yr water savings (tracker-reported). Sources conflict on total campus acreage (147-acre documented land parcel vs ~300-acre marketed campus).
County water status: Extreme drought (D3) in Maricopa County, week of 2026-09-22 (US Drought Monitor). Data centers are large water users for cooling; this is the neutral local water picture.
Why here
Microsoft Goodyear Data Center Campus sits on private land in Arizona, Goodyear. It connects to the WECC grid, draws on grid power. This siting summary is composed from the record's held fields, not speculation; see methodology.
Regulatory paper trail
The filings and rules on record for this site and its jurisdiction, most recent first. Each is a sourced, dated artifact you can follow to the primary document.
Timeline
- Aug 2026capacity changedannounced: unknown to 0.263
- Sep 2026Current: Partially energized
Sources
- Microsoft Azure P0013042 air permit filing (Goodyear)
- Microsoft Builds World-Class Datacenter Campus in Goodyear
a1629c36-66b6-4b2a-b032-15c4882e56f5 · Tracked with DEPLOY's verified-vs-claimed methodology. Every term is defined in the glossary. Announced numbers are claims, not built capacity.
Head-to-head
Common questions
What is Microsoft Goodyear Data Center Campus (PHX70)?
How much power will Microsoft Goodyear Data Center Campus (PHX70) use?
Who is building Microsoft Goodyear Data Center Campus (PHX70)?
Is Microsoft Goodyear Data Center Campus (PHX70) operating yet?
How verified is the data on Microsoft Goodyear Data Center Campus (PHX70)?
Deploy Watch
Track Microsoft Goodyear Data Center Campus (PHX70) on Deploy.
We notify you when energized capacity, lifecycle state, or a new dated capacity claim changes against primary-source evidence, not when the developer issues a press release.
Cite this page
DEPLOY. (2026). Microsoft Goodyear Data Center Campus (PHX70): AI data center campus record. Retrieved September 27, 2026, from https://registry.deploy.report/datacenters/microsoft-goodyear-phx70
More citation formats (MLA, Chicago, BibTeX) →The verified data on this page is available under a Creative Commons Attribution 4.0 license: reuse the facts freely, with attribution to DEPLOY (deploy.report). The prose, design, and any imagery are not included and keep their own rights.
Machine-readable surfaces
- Markdown mirror: /datacenters/microsoft-goodyear-phx70.md
- JSON-LD: embedded in this page’s head
- REST API: /v1/datacenters/microsoft-goodyear-phx70
- Data documentation: /data
- Query this programmatically: Deploy MCP