Data center campus
Switch Citadel Campus (Tahoe Reno)
Switch Citadel Campus is an AI data center campus developed by Switch, Inc. in Nevada, McCarran (Tahoe Reno Industrial Center). 0.65 GW of capacity has been announced; 0.13 GW is energized. The gap is what this page tracks: what is claimed versus what is actually built, each figure dated and sourced.
Partially energized · Switch, Inc. · Private land · WECC · McCarran (Tahoe Reno Industrial Center), Nevada, United States
Capacity: announced vs energized
Announced-to-energized gap: 0.52 GW. Every figure below is a single dated, sourced claim. Current best per series resolves by evidence tier, then date. See the methodology.
| Source | ||||
|---|---|---|---|---|
| Announced | 0.65 GW | 2019-01-01 | claimed | press release |
| Energized | 0.13 GW | 2019-01-01 | reported | journalist report |
Key facts
Lifecycle
Announced
Energized
Switch, Inc.
Developer
Location
Grid
Land
Announced-to-energized gap
On the data center map
No mappable coordinate is recorded for Switch Citadel Campus (Tahoe Reno) yet. Location: McCarran (Tahoe Reno Industrial Center).
In clusterNevada(65)
The deal
- developer
- Switch, Inc. · Founded/led by Rob Roy
- operator
- Switch, Inc.
- financier
- IFM Investors · Co-owner alongside DigitalBridge
- utility
- NV Energy · Switch litigated utility exit at Nevada PUC
- financier
- DigitalBridge · Took Switch private in 2022
Power
- Power source
- grid
- Grid operator
- WECC
- Interconnection
- Water
- Supplied with reclaimed (treated effluent) water via a 16-mile pipeline from the Truckee Meadows Water Reclamation Facility; Switch states its cooling approach minimizes water dependence.
Why here
Switch Citadel Campus sits on private land in Nevada, McCarran (Tahoe Reno Industrial Center). It connects to the WECC grid, draws on grid power. This siting summary is composed from the record's held fields, not speculation; see methodology.
Regulatory paper trail
The filings and rules on record for this site and its jurisdiction, most recent first. Each is a sourced, dated artifact you can follow to the primary document.
Timeline
- Aug 2026party addedutility: NV Energy
- Sep 2026Current: Partially energized
Sources
- Switch TAHOE RENO Now Open: Largest Data Center Campus in the World
- Switch, Inc. Form 8-K investor presentation (FY2018)
- Switch Launches Its First Enormous Reno Data Center
- Switch Will Support Reno Data Center Campus With Reclaimed Water · Data Center Frontier
385f1c8a-eb14-4741-8526-9cab49bac9cb · Tracked with DEPLOY's verified-vs-claimed methodology. Every term is defined in the glossary. Announced numbers are claims, not built capacity.
Head-to-head
Common questions
What is Switch Citadel Campus (Tahoe Reno)?
How much power will Switch Citadel Campus (Tahoe Reno) use?
Who is building Switch Citadel Campus (Tahoe Reno)?
Is Switch Citadel Campus (Tahoe Reno) operating yet?
How verified is the data on Switch Citadel Campus (Tahoe Reno)?
Deploy Watch
Track Switch Citadel Campus (Tahoe Reno) on Deploy.
We notify you when energized capacity, lifecycle state, or a new dated capacity claim changes against primary-source evidence, not when the developer issues a press release.
Cite this page
DEPLOY. (2026). Switch Citadel Campus (Tahoe Reno): AI data center campus record. Retrieved September 27, 2026, from https://registry.deploy.report/datacenters/switch-citadel-storey-county-nevada
More citation formats (MLA, Chicago, BibTeX) →The verified data on this page is available under a Creative Commons Attribution 4.0 license: reuse the facts freely, with attribution to DEPLOY (deploy.report). The prose, design, and any imagery are not included and keep their own rights.
Machine-readable surfaces
- Markdown mirror: /datacenters/switch-citadel-storey-county-nevada.md
- JSON-LD: embedded in this page’s head
- REST API: /v1/datacenters/switch-citadel-storey-county-nevada
- Data documentation: /data
- Query this programmatically: Deploy MCP