Data center facility
Dallas-Fort Worth (Red Oak)
Compass Datacenters · Red Oak · 441 N Austin Boulevard, Red Oak, TX. Every figure below is individually sourced and dated.
Part of the tracked campus Compass Datacenters Red Oak Campus (DFW III).
- Announced capex
- $300M
- Cooling
- Air-cooled, N+1 redundancy
- Cost per MW
- $833K/MW
Every figure is one row in the ledger below with its source. Derived rows are pure arithmetic on the rows above (not new claims). Absent lines mean the fact isn't on record yet.
In clusterTexas(607)
The deal
Inherited from campus Compass Datacenters Red Oak Campus (DFW III).
- developer
- Compass Datacenters · Entity Compass Datacenters DFW III, LLC
- utility
- Hilco Electric Cooperative · Grid power provider to the Red Oak (DFW III) campus at 300 Houston School Road; TCEQ Federal Operating Permit O4679
Financial structure
Inherited from campus Compass Datacenters Red Oak Campus (DFW III).
- DFW III expansion (up to 3 additional buildings)
- $300M. Combined construction cost of up to three more facilities announced Sept 2024 journalist report
Investment, workforce and specs
Inherited from campus Compass Datacenters Red Oak Campus (DFW III).
- Cooling
- Air-cooled, N+1 redundancy source
Power
Inherited from campus Compass Datacenters Red Oak Campus (DFW III). Live grid demand and drought overlay only render on the campus page.
- Power source
- grid
- Grid operator
- ERCOT
- Interconnection
- Water
- Closed-loop water-cooling system that is not connected to the city utility line and, per city staff, uses less water annually than a Walmart Supercenter.
Facility record
On the data center map
Construction evidence
Dated satellite imagery of the site itself, oldest to newest, with the campus milestones that landed in each window. This is what the site looked like from orbit while announcements, permits, and energizations were dated into our ledger, so bare land, grading, and building mass tell their own story alongside the paper trail. Sentinel-2 true color, 10 m resolution, cloud-free scenes; click any frame to expand it.
Delivery paceAnnounced Q2 2025 · live Q1 2026 · 7 mo build
Dated Sentinel-2 imagery, gated to hand-verified site coordinates. Milestones inherited from campus Compass Datacenters Red Oak Campus (DFW III). How we source and verify it: satellite construction evidence.
Evidence
Each fact traces to a source. This is what a verified record looks like next to an unsourced directory listing.
Timeline
- Aug 2026First recordedAdded to the DEPLOY registry as a sourced facility record
- Sep 2026Current: under construction
Facility-tier record. For campus-scale announced-vs-energized tracking see the data center index. DEPLOY is neutral infrastructure: what is claimed, what is verified, and when.
Common questions
What is Dallas-Fort Worth (Red Oak)?
Who operates Dallas-Fort Worth (Red Oak)?
Is Dallas-Fort Worth (Red Oak) operating?
How verified is the data on Dallas-Fort Worth (Red Oak)?
Deploy Watch
Track Dallas-Fort Worth (Red Oak) on Deploy.
We notify you when operating status, capacity, or the operator changes against a sourced record.
Cite this page
DEPLOY. (2026). Dallas-Fort Worth (Red Oak): data center facility record. Retrieved September 27, 2026, from https://registry.deploy.report/datacenters/facilities/compass-red-oak-red-oak-tx
More citation formats (MLA, Chicago, BibTeX) →The verified data on this page is available under a Creative Commons Attribution 4.0 license: reuse the facts freely, with attribution to DEPLOY (deploy.report). The prose, design, and any imagery are not included and keep their own rights.
Machine-readable surfaces
- Markdown mirror: /datacenters/facilities/compass-red-oak-red-oak-tx.md
- JSON-LD: embedded in this page’s head
- REST API: /v1/datacenters/facilities/compass-red-oak-red-oak-tx
- Data documentation: /data
- Query this programmatically: Deploy MCP