xAI Colossus is an AI data center campus developed by xAI in Tennessee, Memphis. 2 GW of capacity has been announced; 1 GW is energized. The gap is what this page tracks: what is claimed versus what is actually built, each figure dated and sourced.
Partially energized · xAI · Former industrial site · Memphis, Tennessee, United States
Capacity: announced vs energized
Announced-to-energized gap: 1 GW. Every figure below is a single dated, sourced claim. Current best per series resolves by evidence tier, then date. See the methodology.
Promised online: Q4 2025. Energized capacity is now on record. Claimed by Elon Musk / xAI (source).
| Source | ||||
|---|---|---|---|---|
| Announced | 2 GW | 2026-01-15 | claimed | press release |
| Energized | 1 GW | 2026-06-30 | reported | journalist report |
Construction evidence
Dated satellite imagery of the site itself, oldest to newest, with the campus milestones that landed in each window. This is what the site looked like from orbit while announcements, permits, and energizations were dated into our ledger, so bare land, grading, and building mass tell their own story alongside the paper trail. Sentinel-2 true color, 10 m resolution, cloud-free scenes; click any frame to expand it.
Delivery paceAnnounced Q1 2026 · live Q2 2026 · 6 mo build
Dated Sentinel-2 imagery, gated to hand-verified site coordinates. Milestones synthesized from the campus's own capacity ledger, financial claims, and lifecycle events; each chip links to its source. How we source and verify it: satellite construction evidence.
Per-building manifest tied to the site polygons and imagery. When we know a building's outline we render it; when we know only its year and capacity we still surface those as first-class rows so the campus total is auditable, not a headline claim. Sorted largest-first; 4 on record.
Manifest totals: 1,422,623 sqft. Rolled from the per-building rows above.
Key facts
Lifecycle
Announced
Energized
Developer
Location
Facilities tracked
Reported facts
Structured facts sourced from citations already on this record. Each fact traces to a source in the References section below.
- Operator
- xAI
- Primary workload
- Grok foundation-model training and inference
- GPU count (reported)
- ~200,000 Nvidia GPUs on-site (Hopper / Blackwell mix)
- Announced capacity
- 2 GW target (combined Memphis-area complex)
- Cooling
- Treated wastewater, roughly 3 million gallons/day from the purpose-built Colossus Water Recycling Plant
- On-site power
- Methane gas turbines (Solaris fleet, ~1.1 GW under construction)
- Reported buildout cost
- ~$18B (Introl / SemiAnalysis)
- First-cluster energization
- September 2024 (100k GPUs live in 122 days)
- Chip supplier
- Nvidia
- GPU mix (Musk-stated Sep 2026)
- Musk-stated (company-stated): Colossus 1 = 150k NVIDIA H100 + 50k H200 + 30k GB200 (230k GPUs on this accounting). Cap: founder X; supersedes coarser prior ~200k mix reporting for this snapshot
- GPUs 220k+ (Mid-South company-stated Sep 2026)
- Company-stated (company-stated; browser-confirmed Sep 25 2026): Colossus I page figure lists GPUs: 220k+. Cap: SpaceX Mid-South page figure; distinct from the Musk-stated mix fact on this record (150k H100 + 50k H200 + 30k GB200 = 230k on that accounting)
On the data center map
Every tracked data center is on this map, centered on xAI Colossus. Pan or zoom out to see how close rivals are building.
- Announced capex
- $18B
- Grid
- Grid connected in stages: the TVA board approved 150 MW on 7 November 2024, requested through Memphis Light, Gas and Water, which was upgrading the site to 50 MW in the meantime. xAI committed $24 million to build a new substation for the additional load, recovered by MLGW through monthly rebates before it takes ownership. Fourteen mobile Voltagrid generators of 2.5 MW each, about 35 MW in total, covered the gap.
- GPUs
- 200K 200,000 H100/H200
- Cost per MW
- $9M/MW
Every figure is one row in the ledger below with its source. Derived rows are pure arithmetic on the rows above (not new claims). Absent lines mean the fact isn't on record yet.
In clusterTennessee(54)
The deal
Power
- Power source
- behind the meter gas
- Interconnection
- Grid connected in stages: the TVA board approved 150 MW on 7 November 2024, requested through Memphis Light, Gas and Water, which was upgrading the site to 50 MW in the meantime. xAI committed $24 million to build a new substation for the additional load, recovered by MLGW through monthly rebates before it takes ownership. Fourteen mobile Voltagrid generators of 2.5 MW each, about 35 MW in total, covered the gap.
- Water
- Cooled with treated wastewater (about 3 million gallons/day) piped from the purpose-built Colossus Water Recycling Plant, avoiding an equivalent draw on Memphis drinking water; on-site power is from methane gas turbines.
Solaris on-site gas turbines, 1.10 GW gas, Under construction. About 400 MW currently serving xAI; Solaris expects over 1.1 GW operating for xAI by Q2 2027.
County water status: Severe drought (D2) in Shelby County, week of 2026-09-22 (US Drought Monitor). Data centers are large water users for cooling; this is the neutral local water picture.
Silicon on site
Every AI chip publicly attributed to xAI Colossus (Memphis) on the DEPLOY registry. Quantity hints are unstructured because underlying disclosures vary by an order of magnitude. Source links per row.
- as of 2026-01-15
Second-wave upgrade GPUs added late 2024
reported - as of 2024-09-01
~100,000 GPUs live in first cluster (Sep 2024); scaled toward 200,000 across the complex
reported
Why here
xAI Colossus sits on former industrial site in Tennessee, Memphis. It draws on behind the meter gas power, interconnection is Grid connected in stages: the TVA board approved 150 MW on 7 November 2024, requested through Memphis Light, Gas and Water, which was upgrading the site to 50 MW in the meantime. xAI committed $24 million to build a new substation for the additional load, recovered by MLGW through monthly rebates before it takes ownership. Fourteen mobile Voltagrid generators of 2.5 MW each, about 35 MW in total, covered the gap.. This siting summary is composed from the record's held fields, not speculation; see methodology.
Financial structure
- Reported buildout cost
- $18B journalist report
Regulatory paper trail
The filings and rules on record for this site and its jurisdiction, most recent first. Each is a sourced, dated artifact you can follow to the primary document.
Investment, workforce and specs
Estimated compute: the claimed 200,000 H100/H200 chips are on the order of 20x the compute used to train a GPT-4-class model. Derived from the chip-count claim, not measured (basis).
AI models here
Reported model-to-campus links, first-party sourced. Companies rarely disclose where a model trains, so this is sparse by nature.
Facilities at this campus
Timeline
- Aug 2026party addedutility: Solaris Energy Infrastructure
- Sep 2026Current: Partially energized
Sources
- xAI Colossus Hits 2 GW: 555,000 GPUs, $18B · Introl
- xAI's Colossus 2: First Gigawatt Datacenter · SemiAnalysis
- Wastewater Will Cool This Memphis Data Center · Governing
- Fury from campaigners as Elon Musk's xAI gets 150MW for Colossus supercomputer in Memphis · Data Center Dynamics
- Fury from campaigners as Elon Musk's xAI gets 150MW for Colossus supercomputer in Memphis · SDxCentral
- Elon Musk: Colossus 1/2 GPU inventory and Q4 GB300 ramp · X (@elonmusk)
- Sawyer Merritt: amplifying Musk Colossus inventory post · X (@SawyerMerritt)
- Memphis Local Impact Report (SpaceX Mid-South) · SpaceX (official PDF)
- Southaven Local Impact Report (SpaceX Mid-South) · SpaceX (official PDF)
c174e6dd-1a31-4984-be75-5ca3adf7aafa · Tracked with DEPLOY's verified-vs-claimed methodology. Every term is defined in the glossary. Announced numbers are claims, not built capacity.
Head-to-head
Common questions
What is xAI Colossus (Memphis)?
How much power will xAI Colossus (Memphis) use?
Who is building xAI Colossus (Memphis)?
Is xAI Colossus (Memphis) operating yet?
How verified is the data on xAI Colossus (Memphis)?
Deploy Watch
Track xAI Colossus (Memphis) on Deploy.
We notify you when energized capacity, lifecycle state, or a new dated capacity claim changes against primary-source evidence, not when the developer issues a press release.
Cite this page
DEPLOY. (2026). xAI Colossus (Memphis): AI data center campus record. Retrieved September 27, 2026, from https://registry.deploy.report/datacenters/xai-colossus-memphis
More citation formats (MLA, Chicago, BibTeX) →The verified data on this page is available under a Creative Commons Attribution 4.0 license: reuse the facts freely, with attribution to DEPLOY (deploy.report). The prose, design, and any imagery are not included and keep their own rights.
Machine-readable surfaces
- Markdown mirror: /datacenters/xai-colossus-memphis.md
- JSON-LD: embedded in this page’s head
- REST API: /v1/datacenters/xai-colossus-memphis
- Data documentation: /data
- Query this programmatically: Deploy MCP