{"id":"c174e6dd-1a31-4984-be75-5ca3adf7aafa","slug":"xai-colossus-memphis","name":"xAI Colossus (Memphis)","aliases":["Colossus","Colossus 1","Colossus 2","xAI Memphis supercluster"],"locationId":"1ffe2451-a057-475c-a4a9-f6ef8b9015a9","lat":35.0601,"lng":-90.1522,"locationPrecision":"exact","landStatus":"former_industrial","lifecycleState":"partially_energized","powerSourceMix":"behind_the_meter_gas","interconnectionQueueStatus":"Grid connected in stages: the TVA board approved 150 MW on 7 November 2024, requested through Memphis Light, Gas and Water, which was upgrading the site to 50 MW in the meantime. xAI committed $24 million to build a new substation for the additional load, recovered by MLGW through monthly rebates before it takes ownership. Fourteen mobile Voltagrid generators of 2.5 MW each, about 35 MW in total, covered the gap.","interconnectionQueueId":null,"expectedEnergizationDate":null,"dedicatedSubstation":null,"gridOperator":null,"waterSourceNotes":"Cooled with treated wastewater (about 3 million gallons/day) piped from the purpose-built Colossus Water Recycling Plant, avoiding an equivalent draw on Memphis drinking water; on-site power is from methane gas turbines.","servingUtility":null,"acreage":null,"totalBuildingSqft":null,"streetAddress":null,"notes":"xAI's Colossus AI training campus in the Whitehaven area of Memphis, Tennessee (Colossus 1 at 3231 Riverport Rd; Colossus 2 at 5420 Tulane Rd), with associated on-site gas generation. Elon Musk announced a 2 GW total-capacity target in January 2026 (555,000 Nvidia GPUs, ~$18B). As of mid-2026 the combined sites provided on the order of 1 GW of operating AI-compute capacity, powered largely behind the meter by on-site gas turbines supplied by Solaris Energy Infrastructure (about 400 MW serving xAI, with Solaris expecting over 1.1 GW operating for xAI by Q2 2027).","keyFacts":[{"label":"Operator","value":"xAI"},{"label":"Primary workload","value":"Grok foundation-model training and inference"},{"label":"GPU count (reported)","value":"~200,000 Nvidia GPUs on-site (Hopper / Blackwell mix)"},{"label":"Announced capacity","value":"2 GW target (combined Memphis-area complex)"},{"label":"Cooling","value":"Treated wastewater, roughly 3 million gallons/day from the purpose-built Colossus Water Recycling Plant"},{"label":"On-site power","value":"Methane gas turbines (Solaris fleet, ~1.1 GW under construction)"},{"label":"Reported buildout cost","value":"~$18B (Introl / SemiAnalysis)"},{"label":"First-cluster energization","value":"September 2024 (100k GPUs live in 122 days)"},{"label":"Chip supplier","value":"Nvidia"},{"label":"GPU mix (Musk-stated Sep 2026)","value":"Musk-stated ([company-stated](https://x.com/elonmusk/status/2103329761690865846)): Colossus 1 = 150k NVIDIA H100 + 50k H200 + 30k GB200 (230k GPUs on this accounting). Cap: founder X; supersedes coarser prior ~200k mix reporting for this snapshot"},{"label":"GPUs 220k+ (Mid-South company-stated Sep 2026)","value":"Company-stated ([company-stated](https://www.spacex.com/Mid-South); browser-confirmed Sep 25 2026): Colossus I page figure lists GPUs: 220k+. Cap: SpaceX Mid-South page figure; distinct from the Musk-stated mix fact on this record (150k H100 + 50k H200 + 30k GB200 = 230k on that accounting)"}],"reviewStatus":"reviewed","sources":[{"url":"https://introl.com/blog/xai-colossus-2-gigawatt-expansion-555k-gpus-january-2026","title":"xAI Colossus Hits 2 GW: 555,000 GPUs, $18B","sourceName":"Introl"},{"url":"https://newsletter.semianalysis.com/p/xais-colossus-2-first-gigawatt-datacenter","title":"xAI's Colossus 2: First Gigawatt Datacenter","sourceName":"SemiAnalysis"},{"url":"https://www.governing.com/resilience/wastewater-will-cool-this-memphis-data-center","title":"Wastewater Will Cool This Memphis Data Center","sourceName":"Governing"},{"url":"https://www.datacenterdynamics.com/en/news/xai-colossus-memphis-power-tva/","title":"Fury from campaigners as Elon Musk's xAI gets 150MW for Colossus supercomputer in Memphis","sourceName":"Data Center Dynamics"},{"url":"https://www.sdxcentral.com/news/xai-colossus-memphis-power-tva/","title":"Fury from campaigners as Elon Musk's xAI gets 150MW for Colossus supercomputer in Memphis","sourceName":"SDxCentral"},{"url":"https://x.com/elonmusk/status/2103329761690865846","title":"Elon Musk: Colossus 1/2 GPU inventory and Q4 GB300 ramp","sourceName":"X (@elonmusk)","publishedAt":"2026-09-24"},{"url":"https://x.com/SawyerMerritt/status/2103332409789776197","title":"Sawyer Merritt: amplifying Musk Colossus inventory post","sourceName":"X (@SawyerMerritt)","publishedAt":"2026-09-24"},{"url":"https://www.spacex.com/assets/sites-pages/assets/Memphis-Local-Impact-Report.pdf","title":"Memphis Local Impact Report (SpaceX Mid-South)","sourceName":"SpaceX (official PDF)","publishedAt":"2026-09-25"},{"url":"https://www.spacex.com/assets/sites-pages/assets/Southaven-Local-Impact-Report-web.pdf","title":"Southaven Local Impact Report (SpaceX Mid-South)","sourceName":"SpaceX (official PDF)","publishedAt":"2026-09-25"}],"reviewNote":null,"createdAt":"2026-08-17T17:02:25.186Z","updatedAt":"2026-09-25T21:01:34.344Z","location":{"id":"1ffe2451-a057-475c-a4a9-f6ef8b9015a9","name":"Memphis","slug":"memphis-tennessee","kind":"city","parentLocationId":"bf4be660-c16f-4e4a-90a5-13a4bacb0e82","region":"Tennessee","lat":35.05,"lng":-90.03,"reviewStatus":"reviewed","aliases":[],"collisionRisk":"high","reviewNote":null,"createdAt":"2026-08-17T17:02:24.805Z","updatedAt":"2026-08-21T03:20:12.226Z"},"parties":[{"id":"60a53931-d570-4746-8d55-199bde30523a","dataCenterId":"c174e6dd-1a31-4984-be75-5ca3adf7aafa","companyId":null,"externalName":"Solaris Energy Infrastructure","role":"utility","structureNotes":"On-site gas turbine fleet powering the campus behind the meter.","createdAt":"2026-08-17T17:02:30.052Z","company":null},{"id":"34dc8fe9-154b-4a7e-a3bb-f3823f5e180a","dataCenterId":"c174e6dd-1a31-4984-be75-5ca3adf7aafa","companyId":"a9609061-00fd-4d9b-9b2d-ce2d772ab825","externalName":"Nvidia","role":"chip_supplier","structureNotes":"555,000 Nvidia GPUs at full 2 GW.","createdAt":"2026-08-17T17:02:29.293Z","company":{"id":"a9609061-00fd-4d9b-9b2d-ce2d772ab825","name":"NVIDIA","slug":"nvidia"}},{"id":"e33f5e8e-6f4c-494d-90ec-5f2767eb91c4","dataCenterId":"c174e6dd-1a31-4984-be75-5ca3adf7aafa","companyId":"d7bc30aa-e892-42f7-a58a-e172534fec48","externalName":"xAI","role":"developer","structureNotes":"Owner and operator.","createdAt":"2026-08-17T17:02:28.532Z","company":{"id":"d7bc30aa-e892-42f7-a58a-e172534fec48","name":"xAI","slug":"xai"}}],"capacityClaims":[{"id":"60e1bcca-863d-43f2-87b0-96329ae0b22d","dataCenterId":"c174e6dd-1a31-4984-be75-5ca3adf7aafa","series":"announced","valueGw":2,"asOf":"2026-01-15T12:00:00.000Z","sourceUrl":"https://www.techzine.eu/news/infrastructure/137578/xai-expands-colossus-megadata-center-to-2-gigawatts/","sourceType":"press_release","evidenceTier":"claimed","supersedesId":null,"note":"Musk's announced 2 GW total-capacity target.","createdAt":"2026-08-17T17:02:25.915Z"},{"id":"baf1e855-3460-4871-844b-062e7fa81f91","dataCenterId":"c174e6dd-1a31-4984-be75-5ca3adf7aafa","series":"energized","valueGw":1,"asOf":"2026-06-30T12:00:00.000Z","sourceUrl":"https://introl.com/blog/xai-colossus-2-gigawatt-expansion-555k-gpus-january-2026","sourceType":"journalist_report","evidenceTier":"reported","supersedesId":null,"note":"On the order of 1 GW of AI compute operating across the combined sites, mid-2026.","createdAt":"2026-08-17T17:02:26.833Z"}],"financialClaims":[{"id":"21a11991-e1a7-4a70-92a4-7185f72109cb","dataCenterId":"c174e6dd-1a31-4984-be75-5ca3adf7aafa","kind":"capex","label":"Reported buildout cost","valueUsd":"18000000000","capUsd":null,"conditions":null,"asOf":"2026-01-15T12:00:00.000Z","sourceUrl":"https://introl.com/blog/xai-colossus-2-gigawatt-expansion-555k-gpus-january-2026","sourceType":"journalist_report","evidenceTier":"reported","createdAt":"2026-08-17T17:02:27.763Z"}],"metricClaims":[{"id":"5c64ea7b-7f99-4269-9f6b-2f770d56b06e","dataCenterId":"c174e6dd-1a31-4984-be75-5ca3adf7aafa","metricType":"gpu_count","valueNumeric":200000,"valueText":"200,000 H100/H200","unit":null,"grantingJurisdiction":null,"asOf":"2026-01-01T00:00:00.000Z","sourceUrl":"https://en.wikipedia.org/wiki/Colossus_(data_center)","sourceType":"press","evidenceTier":"reported","supersedesId":null,"note":null,"createdAt":"2026-08-18T21:53:37.215Z"}],"powerProjects":[{"id":"52b0f101-eb80-4118-aca4-af8368fd6d75","dataCenterId":"c174e6dd-1a31-4984-be75-5ca3adf7aafa","name":"Solaris on-site gas turbines","type":"gas","capacityGw":1.1,"lifecycleState":"under_construction","sourceUrl":"https://newsletter.semianalysis.com/p/xais-colossus-2-first-gigawatt-datacenter","evidenceTier":"reported","note":"About 400 MW currently serving xAI; Solaris expects over 1.1 GW operating for xAI by Q2 2027.","createdAt":"2026-08-17T17:02:27.374Z"}],"facilities":[{"slug":"xai-tulane-road-memphis-shelby-tn","name":"xAI Tulane Road Site (Second Memphis Data Center)","status":"planned","criticalItMw":null,"facilityType":"hyperscale"}],"incidents":[],"events":[{"id":"00336e66-d718-4606-8ba6-473b9be96f88","dataCenterId":"c174e6dd-1a31-4984-be75-5ca3adf7aafa","eventType":"party_added","series":null,"oldValue":null,"newValue":null,"claimId":null,"detail":"utility: Solaris Energy Infrastructure","occurredAt":"2026-08-17T17:02:30.449Z","createdAt":"2026-08-17T17:02:30.449Z"},{"id":"8985d0b7-0e18-4621-8e21-52c5a8be3629","dataCenterId":"c174e6dd-1a31-4984-be75-5ca3adf7aafa","eventType":"party_added","series":null,"oldValue":null,"newValue":null,"claimId":null,"detail":"chip_supplier: Nvidia","occurredAt":"2026-08-17T17:02:29.669Z","createdAt":"2026-08-17T17:02:29.669Z"},{"id":"69b9942e-cbcb-4687-804d-40744313da90","dataCenterId":"c174e6dd-1a31-4984-be75-5ca3adf7aafa","eventType":"party_added","series":null,"oldValue":null,"newValue":null,"claimId":null,"detail":"developer: xAI","occurredAt":"2026-08-17T17:02:28.919Z","createdAt":"2026-08-17T17:02:28.919Z"},{"id":"3fbb036b-2d89-4cea-a625-375e6249d679","dataCenterId":"c174e6dd-1a31-4984-be75-5ca3adf7aafa","eventType":"financial_recorded","series":null,"oldValue":null,"newValue":null,"claimId":null,"detail":"capex: Reported buildout cost","occurredAt":"2026-08-17T17:02:28.148Z","createdAt":"2026-08-17T17:02:28.148Z"},{"id":"1eb36bcb-1b41-4da1-893d-529d1ec34a54","dataCenterId":"c174e6dd-1a31-4984-be75-5ca3adf7aafa","eventType":"capacity_changed","series":"energized","oldValue":null,"newValue":"1","claimId":"baf1e855-3460-4871-844b-062e7fa81f91","detail":null,"occurredAt":"2026-08-17T17:02:27.140Z","createdAt":"2026-08-17T17:02:27.140Z"},{"id":"65659623-ceb9-4c0f-b6e9-d9dd0e9c2f6b","dataCenterId":"c174e6dd-1a31-4984-be75-5ca3adf7aafa","eventType":"claim_recorded","series":"energized","oldValue":null,"newValue":"1","claimId":"baf1e855-3460-4871-844b-062e7fa81f91","detail":"reported · journalist_report","occurredAt":"2026-08-17T17:02:26.992Z","createdAt":"2026-08-17T17:02:26.992Z"},{"id":"1e6b48b8-a0c0-4a65-b5ae-987d0141c24a","dataCenterId":"c174e6dd-1a31-4984-be75-5ca3adf7aafa","eventType":"capacity_changed","series":"announced","oldValue":null,"newValue":"2","claimId":"60e1bcca-863d-43f2-87b0-96329ae0b22d","detail":null,"occurredAt":"2026-08-17T17:02:26.244Z","createdAt":"2026-08-17T17:02:26.244Z"},{"id":"f2b2d3f6-ac22-42b2-849e-f7b6386045ea","dataCenterId":"c174e6dd-1a31-4984-be75-5ca3adf7aafa","eventType":"claim_recorded","series":"announced","oldValue":null,"newValue":"2","claimId":"60e1bcca-863d-43f2-87b0-96329ae0b22d","detail":"claimed · press_release","occurredAt":"2026-08-17T17:02:26.071Z","createdAt":"2026-08-17T17:02:26.071Z"}],"capacity_picture":{"announced_gw":2,"contracted_gw":null,"under_construction_gw":null,"energized_gw":1,"announced_minus_energized_gw":1,"by_series":{"announced":{"valueGw":2,"asOf":"2026-01-15T12:00:00.000Z","evidenceTier":"claimed","sourceUrl":"https://www.techzine.eu/news/infrastructure/137578/xai-expands-colossus-megadata-center-to-2-gigawatts/"},"contracted":null,"under_construction":null,"energized":{"valueGw":1,"asOf":"2026-06-30T12:00:00.000Z","evidenceTier":"reported","sourceUrl":"https://introl.com/blog/xai-colossus-2-gigawatt-expansion-555k-gpus-january-2026"}}},"jsonLd":{"@context":"https://schema.org","@type":"Place","name":"xAI Colossus (Memphis)","url":"https://registry.deploy.report/datacenters/xai-colossus-memphis","geo":{"@type":"GeoCoordinates","latitude":35.0601,"longitude":-90.1522},"address":{"@type":"PostalAddress","addressLocality":"Memphis"}}}