xAI Tulane Road Site (Second Memphis Data Center)
xAI · Memphis. Every figure below is individually sourced and dated.
Part of the tracked campus xAI Colossus (Memphis).
- Announced capex
- $18B
- Grid
- Grid connected in stages: the TVA board approved 150 MW on 7 November 2024, requested through Memphis Light, Gas and Water, which was upgrading the site to 50 MW in the meantime. xAI committed $24 million to build a new substation for the additional load, recovered by MLGW through monthly rebates before it takes ownership. Fourteen mobile Voltagrid generators of 2.5 MW each, about 35 MW in total, covered the gap.
- GPUs
- 200K 200,000 H100/H200
- Cost per MW
- $9M/MW
Every figure is one row in the ledger below with its source. Derived rows are pure arithmetic on the rows above (not new claims). Absent lines mean the fact isn't on record yet.
In clusterTennessee(54)
The deal
Inherited from campus xAI Colossus (Memphis).
Financial structure
Inherited from campus xAI Colossus (Memphis).
- Reported buildout cost
- $18B journalist report
Investment, workforce and specs
Inherited from campus xAI Colossus (Memphis).
- GPUs
- 200,000 H100/H200 source
Power
Inherited from campus xAI Colossus (Memphis). Live grid demand and drought overlay only render on the campus page.
- Power source
- behind the meter gas
- Interconnection
- Grid connected in stages: the TVA board approved 150 MW on 7 November 2024, requested through Memphis Light, Gas and Water, which was upgrading the site to 50 MW in the meantime. xAI committed $24 million to build a new substation for the additional load, recovered by MLGW through monthly rebates before it takes ownership. Fourteen mobile Voltagrid generators of 2.5 MW each, about 35 MW in total, covered the gap.
- Water
- Cooled with treated wastewater (about 3 million gallons/day) piped from the purpose-built Colossus Water Recycling Plant, avoiding an equivalent draw on Memphis drinking water; on-site power is from methane gas turbines.
Solaris on-site gas turbines, 1.10 GW gas, Under construction. About 400 MW currently serving xAI; Solaris expects over 1.1 GW operating for xAI by Q2 2027.
Facility record
On the data center map
Evidence
Each fact traces to a source. This is what a verified record looks like next to an unsourced directory listing.
Timeline
- Aug 2026First recordedAdded to the DEPLOY registry as a sourced facility record
- Sep 2026Current: planned
Facility-tier record. For campus-scale announced-vs-energized tracking see the data center index. DEPLOY is neutral infrastructure: what is claimed, what is verified, and when.
Common questions
What is xAI Tulane Road Site (Second Memphis Data Center)?
Who operates xAI Tulane Road Site (Second Memphis Data Center)?
Is xAI Tulane Road Site (Second Memphis Data Center) operating?
How verified is the data on xAI Tulane Road Site (Second Memphis Data Center)?
Deploy Watch
Track xAI Tulane Road Site (Second Memphis Data Center) on Deploy.
We notify you when operating status, capacity, or the operator changes against a sourced record.
Cite this page
DEPLOY. (2026). xAI Tulane Road Site (Second Memphis Data Center): data center facility record. Retrieved September 27, 2026, from https://registry.deploy.report/datacenters/facilities/xai-tulane-road-memphis-shelby-tn
More citation formats (MLA, Chicago, BibTeX) →The verified data on this page is available under a Creative Commons Attribution 4.0 license: reuse the facts freely, with attribution to DEPLOY (deploy.report). The prose, design, and any imagery are not included and keep their own rights.
Machine-readable surfaces
- Markdown mirror: /datacenters/facilities/xai-tulane-road-memphis-shelby-tn.md
- JSON-LD: embedded in this page’s head
- REST API: /v1/datacenters/facilities/xai-tulane-road-memphis-shelby-tn
- Data documentation: /data
- Query this programmatically: Deploy MCP