xAI Colossus 2 Data Center

xAI Colossus 2 Data Center is an AI data center campus developed by xAI in Mississippi, Southaven. 1.20 GW of capacity has been announced; none is energized yet. The gap is what this page tracks: what is claimed versus what is actually built, each figure dated and sourced.

Partially energized · xAI · Southaven, Mississippi, United States


Capacity: announced vs energized

Announced-to-energized gap: 1.20 GW. Every figure below is a single dated, sourced claim. Current best per series resolves by evidence tier, then date. See the methodology.

Promised online: 2026. 3 months away. Claimed by xAI (reported) (source).

xAI Colossus 2 Data Center capacity claims
Source
Announced1.20 GW2026-06-01reportedjournalist report

Key facts

1.20 GW

Announced

0 GW

Energized

xAI

Developer

1

Facilities tracked

Reported facts

Structured facts sourced from citations already on this record. Each fact traces to a source in the References section below.

Operator
xAI
Primary workload
Grok training expansion of the Memphis-area Colossus complex
Announced capacity
~1.2 GW; combined with Colossus 1 targets ~2 GW
Lifecycle
Partially energized (2026)
On-site gas turbines
46 turbines (~495 MW) reported operating without air permits; 41 additional turbines permitted March 2026
Cooling water source
Drinking water, ~1.3M gallons/day early 2026 (site sits too far from wastewater plant)
Planned wastewater treatment
~$80M plant to reuse ~13M gallons/day of wastewater
State investment claim
Reported multi-billion; described as largest private-sector investment in Mississippi history
Regulatory scrutiny
SELC and state regulators flagged unpermitted gas turbines operating on-site
GPU mix + Q4 GB300 ramp (Musk-stated Sep 2026)
Musk-stated (company-stated): Colossus 2 = 110k GB200 + 440k GB300, with another 220k GB300 fully operational the following week, another 220k in November, and maybe another 220k GB300 by late December. Cap: founder X ramp plan; not an independent energization confirmation
Tesla Megapacks 3.3 GWh (company-stated Sep 2026)
Company-stated (company-stated; browser-confirmed Sep 25 2026): Colossus II grid-connected battery pack will provide 3.3 GWh, described as enough to power Memphis for about two hours and as America's largest grid-connected battery pack. Cap: SpaceX Mid-South primary. Sawyer Merritt separately paraphrased these as Tesla Megapacks; that Megapack/Tesla brand wording is not on the SpaceX Mid-South page and is recorded only as a secondary paraphrase, not as company-stated
Regional investment / jobs / tax (company-stated Sep 2026)
Company-stated (company-stated; Sawyer extract Sep 25 2026): since joining the community in 2024, SpaceXAI is investing more than $90 billion in the region; estimated 2026 tax revenue $60M+; 7,500 local jobs supported. Cap: company community page; independent economic-impact audit not reviewed
Clean water recycling plant $360M (company-stated Sep 2026)
Company-stated (company-stated; Sawyer extract Sep 25 2026): SpaceXAI is investing $360 million at no cost to the city in a clean water recycling plant designed to process up to 10 million gallons of wastewater a day and offset ~3.64 billion gallons a year from the Memphis Aquifer. NOTE: existing DC fact 'Planned wastewater treatment' still lists a prior ~$80M / ~13M gallons/day figure from earlier reporting; this $360M claim is a newer dated company-stated update, not a silent overwrite of the older reported figure. Cap: company Mid-South page; plant status and final capacity not independently verified here
Memphis substations $35M + $20M (company-stated Sep 2026)
Company-stated (company-stated; Sawyer extract Sep 25 2026): in Memphis, SpaceXAI is investing $35 million in a 150 MW substation to support MLGW and another $20 million in a second substation, both at no cost to MLGW or homeowners. Cap: company community page claim
Temporary turbines remove-by July 2027 (company-stated Sep 2026)
Company-stated (company-stated; Sawyer extract Sep 25 2026): under an agreed order with the Mississippi Department of Environmental Quality, all remaining temporary turbines must be removed by July 2027; SpaceXAI says it is already taking units offline and expects to complete removal well ahead of that deadline. Cap: company Mid-South page summarizing the DEQ agreed order; DEQ primary order text not attached this pass
Campus scale (Mid-South company-stated Sep 2026)
Company-stated (company-stated; browser-confirmed Sep 25 2026): campus described as over 2.5 million feet, millions of GPUs, and over two gigawatts of compute. Cap: SpaceX Mid-South community page campus framing; distinct from Musk-stated GPU mix/ramp facts
GPUs planned 1M+ (Mid-South company-stated Sep 2026)
Company-stated (company-stated; browser-confirmed Sep 25 2026): Colossus II page figure lists GPUs planned: 1M+. Cap: SpaceX Mid-South page figure; distinct from Musk-stated Colossus 2 mix + Q4 GB300 ramp detail already on this record

On the data center map

Every tracked data center is on this map, centered on xAI Colossus 2 Data Center. Pan or zoom out to see how close rivals are building.

Free to use on your site, with a link back to DEPLOY.
The story of xAI Colossus 2 Data Center
Announced capex
$80M
Derived
Cost per MW
$67K/MW

Every figure is one row in the ledger below with its source. Derived rows are pure arithmetic on the rows above (not new claims). Absent lines mean the fact isn't on record yet.

In clusterMississippi(27)

The deal

developer
xAI · Owner and operator of Colossus supercomputer campuses
operator
xAI

Power

Power source
behind the meter gas
Interconnection
Water
Sits too far from the wastewater plant and draws millions of gallons/day of drinking water (about 1.3M gal/day as of early 2026); xAI has announced an ~$80M treatment plant to reuse ~13M gal/day of wastewater. Powered by on-site natural gas turbines.

Colossus 2 on-site gas turbine fleet, 0.49 GW gas, Partially energized. ~46 turbines (~495 MW) reported operating; 41 additional turbines permitted March 2026

County water status: Moderate drought (D1) in DeSoto County, week of 2026-09-22 (US Drought Monitor). Data centers are large water users for cooling; this is the neutral local water picture.

Silicon on site

Every AI chip publicly attributed to xAI Colossus 2 Data Center on the DEPLOY registry. Quantity hints are unstructured because underlying disclosures vary by an order of magnitude. Source links per row.

  1. Blackwell generation for Colossus 2 expansion

    reported

    SemiAnalysis

Why here

xAI Colossus 2 Data Center is in Mississippi, Southaven. It draws on behind the meter gas power. This siting summary is composed from the record's held fields, not speculation; see methodology.

Financial structure

Reported multi-billion investment (largest private-sector in state history)
Aggregate figures vary across reports journalist report
Planned wastewater treatment plant (Colossus 2)
$80M press

Regulatory paper trail

The filings and rules on record for this site and its jurisdiction, most recent first. Each is a sourced, dated artifact you can follow to the primary document.

NHTSA Recall: Zoox Robotaxi Software Update for Heavy Smoke Visibility (26E044)operational restriction · 2026-07-15 · United States
FCC Proposed Fines Against Drone Companies (July 2026)other · 2026-07-10 · United States
FAA Proposed Rule: Enabling Supersonic Overland Flight (July 2026)operational restriction · 2026-07-02 · United States

Investment, workforce and specs

Facilities at this campus

Timeline

  1. Aug 2026
    party added
    operator: d7bc30aa-e892-42f7-a58a-e172534fec48
  2. Sep 2026
    Current: Partially energized

Sources

1135eddf-79b2-4cde-aa07-753c2624341f · Tracked with DEPLOY's verified-vs-claimed methodology. Every term is defined in the glossary. Announced numbers are claims, not built capacity.

Head-to-head

Common questions

What is xAI Colossus 2 Data Center?
xAI Colossus 2 Data Center is an AI data center campus tracked on the DEPLOY registry, located in Southaven. DEPLOY records its capacity as a dated, sourced ledger: announced gigawatts versus actually energized gigawatts, never a press-release total.
How much power will xAI Colossus 2 Data Center use?
xAI Colossus 2 Data Center has 1.20 GW of announced capacity on the DEPLOY registry; no energized capacity is yet recorded. Each figure is individually dated and sourced.
Who is building xAI Colossus 2 Data Center?
xAI is recorded as a party to xAI Colossus 2 Data Center on the DEPLOY registry. The full party list, with each role, is on the record.
Is xAI Colossus 2 Data Center operating yet?
As of the most recent verification on the DEPLOY registry, xAI Colossus 2 Data Center is partially energized. DEPLOY tracks the lifecycle from announced through energized, so the current state reflects sourced evidence, not the original announcement.
How verified is the data on xAI Colossus 2 Data Center?
A human editor has reviewed this record for the indexed registry. Every capacity figure is an append-only, dated claim resolved to the highest-evidence tier; superseded claims are kept but excluded from the current view.

Deploy Watch

Track xAI Colossus 2 Data Center on Deploy.

We notify you when energized capacity, lifecycle state, or a new dated capacity claim changes against primary-source evidence, not when the developer issues a press release.

Cite this page

DEPLOY. (2026). xAI Colossus 2 Data Center: AI data center campus record. Retrieved September 27, 2026, from https://registry.deploy.report/datacenters/xai-colossus-2-southaven-mississippi

More citation formats (MLA, Chicago, BibTeX) →
CC BY 4.0

The verified data on this page is available under a Creative Commons Attribution 4.0 license: reuse the facts freely, with attribution to DEPLOY (deploy.report). The prose, design, and any imagery are not included and keep their own rights.

Machine-readable surfaces