DEPLOYDatabase

Data center campus

Meta Talavera de la Reina Data Center Campus (Torrehierro)

Meta Talavera de la Reina Data Center Campus is an AI data center campus developed by Meta in Toledo (Castilla-La Mancha), Talavera de la Reina. 0.25 GW of capacity has been announced; none is energized yet. The gap is what this page tracks: what is claimed versus what is actually built, each figure dated and sourced.

Under construction · Meta · other · Talavera de la Reina, Toledo (Castilla-La Mancha), Spain


Capacity: announced vs energized

Announced-to-energized gap: 0.25 GW. Every figure below is a single dated, sourced claim. Current best per series resolves by evidence tier, then date. See the methodology.

Promised online: 2030. 50 months away. Claimed by Meta / local planning reports (source).

Meta Talavera de la Reina Data Center Campus (Torrehierro) capacity claims
Source
Announced0.25 GW2024-06-01reportedjournalist report

Key facts

0.25 GW

Announced

0 GW

Energized

Meta

Developer

Spain

Location

other

Grid

0.25 GW

Announced-to-energized gap

Reported facts

Structured facts sourced from citations already on this record. Each fact traces to a source in the References section below.

Project scope
Zarza Networks (Meta-owned): about 191 ha at Torrehierro Fase 2, Talavera de la Reina
Building program
102 ha parcel; two data center buildings; 72,705 sq m permanent buildings
Investment (company-claimed)
About €750M, including €685M for data center construction
Design (company-claimed)
Dry-air cooling cuts water need about 80%; LEED; 100% renewable
Permits (reported, Sep 2026)
Reparcelation approved Aug 2026; guarantee posted Sep 2 2026, toward building licenses

On the data center map

No mappable coordinate is recorded for Meta Talavera de la Reina Data Center Campus (Torrehierro) yet. Location: Talavera de la Reina.

The story of Meta Talavera de la Reina Data Center Campus (Torrehierro)
Announced capex
$1.1B
Jobs
250 permanent reported
Derived
Cost per MW
$5M/MW
Cost per job
$4M per permanent job

Every figure is one row in the ledger below with its source. Derived rows are pure arithmetic on the rows above (not new claims). Absent lines mean the fact isn't on record yet.

The deal

utility
Red Electrica / Redeia · Developing the 220 kV substation at Calera y Chozas
developer
Meta · Developer and operator; Meta's fourth European data center

Power

Power source
grid
Grid operator
other
Interconnection

220 kV substation at Calera y Chozas (Red Electrica/Redeia), grid, Under construction. Grid interconnection for the campus

Why here

Meta Talavera de la Reina Data Center Campus is in Toledo (Castilla-La Mancha), Talavera de la Reina. It connects to the other grid, draws on grid power. This siting summary is composed from the record's held fields, not speculation; see methodology.

Financial structure

Meta investment 2024-2030 (~EUR 1.03bn)
$1.1B journalist report

Investment, workforce and specs

Permanent jobs
~250 direct operational jobs source
Water (gal/day)
~600 million litres of drinking water per year (reported) source

Timeline

  1. Aug 2026
    party added
    utility: Red Electrica / Redeia
  2. Nov 2026
    Current: Under construction

Sources

6e1e64cb-aa2a-424b-8dfe-59d1535ae1e9 · Tracked with DEPLOY's verified-vs-claimed methodology. Every term is defined in the glossary. Announced numbers are claims, not built capacity.

Head-to-head

Common questions

What is Meta Talavera de la Reina Data Center Campus (Torrehierro)?
Meta Talavera de la Reina Data Center Campus (Torrehierro) is an AI data center campus tracked on the DEPLOY registry, located in Talavera de la Reina. DEPLOY records its capacity as a dated, sourced ledger: announced gigawatts versus actually energized gigawatts, never a press-release total.
How much power will Meta Talavera de la Reina Data Center Campus (Torrehierro) use?
Meta Talavera de la Reina Data Center Campus (Torrehierro) has 0.25 GW of announced capacity on the DEPLOY registry; no energized capacity is yet recorded. Each figure is individually dated and sourced.
Who is building Meta Talavera de la Reina Data Center Campus (Torrehierro)?
Meta is recorded as a party to Meta Talavera de la Reina Data Center Campus (Torrehierro) on the DEPLOY registry. The full party list, with each role, is on the record.
Is Meta Talavera de la Reina Data Center Campus (Torrehierro) operating yet?
As of the most recent verification on the DEPLOY registry, Meta Talavera de la Reina Data Center Campus (Torrehierro) is under construction. DEPLOY tracks the lifecycle from announced through energized, so the current state reflects sourced evidence, not the original announcement.
How verified is the data on Meta Talavera de la Reina Data Center Campus (Torrehierro)?
This record has been checked against its cited sources by automated agents for the indexed registry; it has not been individually reviewed by a person. Every capacity figure is an append-only, dated claim resolved to the highest-evidence tier; superseded claims are kept but excluded from the current view.

Deploy Watch

Track Meta Talavera de la Reina Data Center Campus (Torrehierro) on Deploy.

We notify you when energized capacity, lifecycle state, or a new dated capacity claim changes against primary-source evidence, not when the developer issues a press release.

Cite this page

DEPLOY. (2026). Meta Talavera de la Reina Data Center Campus (Torrehierro): AI data center campus record. Retrieved November 12, 2026, from https://registry.deploy.report/datacenters/meta-talavera-de-la-reina

More citation formats (MLA, Chicago, BibTeX) →
CC BY 4.0

The verified data on this page is available under a Creative Commons Attribution 4.0 license: reuse the facts freely, with attribution to DEPLOY (deploy.report). The prose, design, and any imagery are not included and keep their own rights.

Machine-readable surfaces