Data center campus
SoftBank/OpenAI Sakai AI Data Center (former Sharp LCD plant)
SoftBank/OpenAI Sakai AI Data Center is an AI data center campus developed by SoftBank Group in Osaka, Sakai. 0.15 GW of capacity has been announced; none is energized yet. The gap is what this page tracks: what is claimed versus what is actually built, each figure dated and sourced.
Under construction · SoftBank Group · Brownfield · other · Sakai, Osaka, Japan
Capacity: announced vs energized
Announced-to-energized gap: 0.15 GW. Every figure below is a single dated, sourced claim. Current best per series resolves by evidence tier, then date. See the methodology.
Promised online: 2025. 9 months past the claimed date, with no energized capacity on record. Claimed by SoftBank (source).
| Source | ||||
|---|---|---|---|---|
| Announced | 0.15 GW | 2025-03-14 | reported | journalist report |
| Announced | 0.25 GW | 2025-03-14 | claimed | journalist report |
| Announced | 0.40 GW | 2024-06-07 | reported | company filing |
| Energized | 0 GW | 2025-03-14 | reported | journalist report |
Key facts
Lifecycle
Announced
Energized
Developer
Location
Grid
Land
Announced-to-energized gap
On the data center map
Every tracked data center is on this map, centered on SoftBank/OpenAI Sakai AI Data Center. Pan or zoom out to see how close rivals are building.
Approximate pin. We hold a city-level coordinate for this campus, not a verified site coordinate, so the marker shows the city rather than the parcel. The satellite strip and building outlines stay off until the site coordinate is sourced.
- Announced capex
- $676M
- Cost per MW
- $5M/MW
Every figure is one row in the ledger below with its source. Derived rows are pure arithmetic on the rows above (not new claims). Absent lines mean the fact isn't on record yet.
The deal
- offtaker
- OpenAI · Partner via SB OpenAI Japan JV; Cristal Intelligence workloads
- utility
- Sharp Corporation · Seller of the former Sakai LCD factory (brownfield)
- developer
- SoftBank Group · Purchaser and operator of the site
- operator
- SoftBank Corp. · SoftBank Corp. (KK) constructing/operating the Sakai data center.
- operator
- SB OpenAI Japan · 50:50 JV of OpenAI and SoftBank promoting 'Cristal Intelligence'; anchor use of the Sakai capacity.
Power
- Power source
- grid
- Grid operator
- other
- Interconnection
Why here
SoftBank/OpenAI Sakai AI Data Center sits on brownfield in Osaka, Sakai. It connects to the other grid, draws on grid power. This siting summary is composed from the record's held fields, not speculation; see methodology.
Financial structure
- Purchase of former Sharp Sakai plant
- $676M. Property acquisition (100bn yen) journalist report
- Estimated full-scale investment (Nikkei calc, ~100k GPUs)
- $6.7B. Nikkei estimate; not committed/confirmed journalist report
- Sharp Sakai plant acquisition
- $676M. ~100 billion yen paid by SoftBank for the former Sharp LCD plant/land converted to the AI data center. journalist report
Regulatory paper trail
The filings and rules on record for this site and its jurisdiction, most recent first. Each is a sourced, dated artifact you can follow to the primary document.
Timeline
- Aug 2026party addedoperator: SB OpenAI Japan
- Sep 2026Current: Under construction
Sources
- SoftBank buys $676M old Sharp plant for its OpenAI collab in Japan
- SoftBank buys former Sharp factory for $676m to build AI data center in Osaka, Japan
- SoftBank, OpenAI to run AI agents at former Sharp LCD plant
7cc3015d-47e3-41e5-b9f1-3f120ead46ef · Tracked with DEPLOY's verified-vs-claimed methodology. Every term is defined in the glossary. Announced numbers are claims, not built capacity.
Head-to-head
Common questions
What is SoftBank/OpenAI Sakai AI Data Center (former Sharp LCD plant)?
How much power will SoftBank/OpenAI Sakai AI Data Center (former Sharp LCD plant) use?
Who is building SoftBank/OpenAI Sakai AI Data Center (former Sharp LCD plant)?
Is SoftBank/OpenAI Sakai AI Data Center (former Sharp LCD plant) operating yet?
How verified is the data on SoftBank/OpenAI Sakai AI Data Center (former Sharp LCD plant)?
Deploy Watch
Track SoftBank/OpenAI Sakai AI Data Center (former Sharp LCD plant) on Deploy.
We notify you when energized capacity, lifecycle state, or a new dated capacity claim changes against primary-source evidence, not when the developer issues a press release.
Cite this page
DEPLOY. (2026). SoftBank/OpenAI Sakai AI Data Center (former Sharp LCD plant): AI data center campus record. Retrieved September 27, 2026, from https://registry.deploy.report/datacenters/softbank-openai-sakai-osaka
More citation formats (MLA, Chicago, BibTeX) →The verified data on this page is available under a Creative Commons Attribution 4.0 license: reuse the facts freely, with attribution to DEPLOY (deploy.report). The prose, design, and any imagery are not included and keep their own rights.
Machine-readable surfaces
- Markdown mirror: /datacenters/softbank-openai-sakai-osaka.md
- JSON-LD: embedded in this page’s head
- REST API: /v1/datacenters/softbank-openai-sakai-osaka
- Data documentation: /data
- Query this programmatically: Deploy MCP