# Project Cardinal Data Center Campus — Yorkville

AI data center campus tracked on DEPLOY: announced-vs-energized capacity, each figure dated and sourced.

- **Canonical ID:** 1b2f6d79-9113-487a-aa09-6819682ce056
- **Type:** AI data center campus
- **Location:** Yorkville, Illinois, United States
- **Lifecycle state:** permitted
- **Announced capacity (GW):** 1.8

## Capacity ledger (append-only, dated, sourced)

- announced: 1.8 GW · reported · as of 2026-03-11 · https://www.yorkville.il.us/906/Project-Cardinal-Data-Center-Campus-Anne

## Parties


## Common questions


**What is Project Cardinal Data Center Campus — Yorkville?**

Project Cardinal Data Center Campus — Yorkville is an AI data center campus tracked on the DEPLOY registry, located in Yorkville. DEPLOY records its capacity as a dated, sourced ledger: announced gigawatts versus actually energized gigawatts, never a press-release total.

**How much power will Project Cardinal Data Center Campus — Yorkville use?**

Project Cardinal Data Center Campus — Yorkville has 1.80 GW of announced capacity on the DEPLOY registry; no energized capacity is yet recorded. Each figure is individually dated and sourced.

**Is Project Cardinal Data Center Campus — Yorkville operating yet?**

As of the most recent verification on the DEPLOY registry, Project Cardinal Data Center Campus — Yorkville is permitted. DEPLOY tracks the lifecycle from announced through energized, so the current state reflects sourced evidence, not the original announcement.

**How verified is the data on Project Cardinal Data Center Campus — Yorkville?**

A human editor has reviewed this record for the indexed registry. Every capacity figure is an append-only, dated claim resolved to the highest-evidence tier; superseded claims are kept but excluded from the current view.

## Sources

- Project Cardinal Data Center Campus (case PZC 2025-08): https://www.yorkville.il.us/906/Project-Cardinal-Data-Center-Campus-Anne
- Yorkville data center approval comes after nearly 6-hour meeting: https://www.shawlocal.com/kendall-county-now/2026/03/12/
- Yorkville data center approval comes after almost 6-hour contentious City Council meeting: https://www.shawlocal.com/kendall-county-now/2026/03/12/yorkville-data-center-approval-comes-after-nearly-6-hour-contentious-city-council-meeting/
- Project Cardinal - Water Usage memo, Burns & McDonnell: https://www.yorkville.il.us/DocumentCenter/View/11747

Canonical: https://registry.deploy.report/datacenters/pioneer-project-cardinal-yorkville-illinois
JSON: https://registry.deploy.report/v1/datacenters/pioneer-project-cardinal-yorkville-illinois