Data center campus
HUMAIN (Riyadh & Dammam flagship data centers)
HUMAIN is an AI data center campus developed by HUMAIN in Riyadh Province, Riyadh. 1.90 GW of capacity has been announced; none is energized yet. The gap is what this page tracks: what is claimed versus what is actually built, each figure dated and sourced.
Under construction · HUMAIN · Private land · Saudi Electricity Company (SEC) · Riyadh, Riyadh Province, Saudi Arabia
Capacity: announced vs energized
Announced-to-energized gap: 1.90 GW. Every figure below is a single dated, sourced claim. Current best per series resolves by evidence tier, then date. See the methodology.
Promised online: Q2 2026. 3 months past the claimed date, with no energized capacity on record. Claimed by HUMAIN (Saudi PIF) (source).
| Source | ||||
|---|---|---|---|---|
| Announced | 1.90 GW | 2026-01-01 | claimed | journalist report |
| Energized | 0 GW | 2026-07-31 | reported | journalist report |
| Under construction | 0.20 GW | 2026-01-01 | reported | journalist report |
Key facts
Lifecycle
Announced
Energized
Developer
Location
Land
Announced-to-energized gap
On the data center map
Every tracked data center is on this map, centered on HUMAIN. Pan or zoom out to see how close rivals are building.
Approximate pin. We hold a city-level coordinate for this campus, not a verified site coordinate, so the marker shows the city rather than the parcel. The satellite strip and building outlines stay off until the site coordinate is sourced.
- Announced capex
- $10B
- GPUs
- 18K 18,000 GB300
- Cost per MW
- $5M/MW
Every figure is one row in the ledger below with its source. Derived rows are pure arithmetic on the rows above (not new claims). Absent lines mean the fact isn't on record yet.
The deal
- financier
- Public Investment Fund (PIF) · Sole owner / sovereign backer.
- chip supplier
- Nvidia, AMD, Qualcomm · Nvidia 18,000 GB300 (Riyadh) + hundreds of thousands more; $10B AMD deal; Qualcomm up to 200MW.
- construction
- MIS (Middle East Specialized Cables / contractor consortium) · Awarded HUMAIN AI data center construction project.
- developer
- HUMAIN · PIF-owned sovereign AI company, launched May 2025.
Power
- Power source
- grid
- Grid operator
- Saudi Electricity Company (SEC)
- Interconnection
Silicon on site
Every AI chip publicly attributed to HUMAIN (Riyadh & Dammam flagship data centers) on the DEPLOY registry. Quantity hints are unstructured because underlying disclosures vary by an order of magnitude. Source links per row.
Why here
HUMAIN sits on private land in Riyadh Province, Riyadh. It connects to the Saudi Electricity Company (SEC) grid, draws on grid power. This siting summary is composed from the record's held fields, not speculation; see methodology.
Financial structure
- Debt financing framework to develop up to 250MW
- $1.2B. Up to $1.2bn financing framework to fund additional AI data center capacity. journalist report
- AMD strategic AI infrastructure deal
- $10B. Multi-year AMD compute buildout; may become a JV with AMD equity in a Saudi fund. journalist report
Regulatory paper trail
The filings and rules on record for this site and its jurisdiction, most recent first. Each is a sourced, dated artifact you can follow to the primary document.
Investment, workforce and specs
- GPUs
- 18,000 GB300 source
Estimated compute: the claimed 18,000 GB300 chips are on the order of 20x the compute used to train a GPT-4-class model. Derived from the chip-count claim, not measured (basis).
Timeline
- Aug 2026party linkeddeveloper: linked externalName "HUMAIN" to company humain
- Sep 2026Current: Under construction
Sources
- Humain breaks ground two data centers, first facilities expected Q2 2026 · Data Center Dynamics
- Saudi AI venture Humain buys 18,000 Nvidia GB300 chips · Data Center Dynamics
- Nvidia to send 18,000 AI GPUs to Saudi Arabia's state-backed AI data centers · Tom's Hardware
- PIF-backed Humain secures up to $1.2bn to expand AI infrastructure · Arab News
68549634-6d59-45db-864b-212966f675e3 · Tracked with DEPLOY's verified-vs-claimed methodology. Every term is defined in the glossary. Announced numbers are claims, not built capacity.
Common questions
What is HUMAIN (Riyadh & Dammam flagship data centers)?
How much power will HUMAIN (Riyadh & Dammam flagship data centers) use?
Who is building HUMAIN (Riyadh & Dammam flagship data centers)?
Is HUMAIN (Riyadh & Dammam flagship data centers) operating yet?
How verified is the data on HUMAIN (Riyadh & Dammam flagship data centers)?
Deploy Watch
Track HUMAIN (Riyadh & Dammam flagship data centers) on Deploy.
We notify you when energized capacity, lifecycle state, or a new dated capacity claim changes against primary-source evidence, not when the developer issues a press release.
Cite this page
DEPLOY. (2026). HUMAIN (Riyadh & Dammam flagship data centers): AI data center campus record. Retrieved September 27, 2026, from https://registry.deploy.report/datacenters/humain-saudi-arabia
More citation formats (MLA, Chicago, BibTeX) →The verified data on this page is available under a Creative Commons Attribution 4.0 license: reuse the facts freely, with attribution to DEPLOY (deploy.report). The prose, design, and any imagery are not included and keep their own rights.
Machine-readable surfaces
- Markdown mirror: /datacenters/humain-saudi-arabia.md
- JSON-LD: embedded in this page’s head
- REST API: /v1/datacenters/humain-saudi-arabia
- Data documentation: /data
- Query this programmatically: Deploy MCP