Data center facility

Cipher Bear Facility

Cipher Mining · Andrews. Every figure below is individually sourced and dated.


Part of the tracked campus Cipher Stingray Data Center (AWS).

The story of Cipher Bear Facilityinherited from campus Cipher Stingray Data Center (AWS)
Announced capex
$810M
Tenant
Amazon Web Services

Every figure is one row in the ledger below with its source. Derived rows are pure arithmetic on the rows above (not new claims). Absent lines mean the fact isn't on record yet.

In clusterAndrews County(5)·Texas(607)

The deal

Inherited from campus Cipher Stingray Data Center (AWS).

developer
Cipher Mining · Developer and operator (Cipher Digital)
tenant
Amazon Web Services · 15-year lease for turnkey space and power
financier
Senior secured noteholders · $810M notes due 2031

Financial structure

Inherited from campus Cipher Stingray Data Center (AWS).

Stingray project financing (senior secured notes)
$810M. Backed by 15-year AWS lease with rent escalators company filing
Senior secured notes financing (construction)
$810M. $810M senior secured notes due 2031 to fund construction/completion of Stingray company filing

Investment, workforce and specs

Inherited from campus Cipher Stingray Data Center (AWS).

Capex
AWS lease underpins up to several billion dollars of contracted lease revenue; includes annual rent escalators and Amazon.com parent guarantees source

Power

Inherited from campus Cipher Stingray Data Center (AWS). Live grid demand and drought overlay only render on the campus page.

Power source
grid
Grid operator
ERCOT
Interconnection

Facility record

operating

Status

crypto hpc

Type

Andrews

Location

40 MW

Critical IT

On the data center map

Free to use on your site, with a link back to DEPLOY.

Evidence

Each fact traces to a source. This is what a verified record looks like next to an unsourced directory listing.

  • criticalItMw: 40 (reported) · source · operational per public record
  • note: Located near Andrews, Texas; connected to the electrical grid; 49% JV interest via Bear LLC (with WindHQ) (verified) · source
  • record: Cipher Bear Facility (reported) · source

Timeline

  1. Aug 2026
    First recorded
    Added to the DEPLOY registry as a sourced facility record
  2. Sep 2026
    Current: operating

Facility-tier record. For campus-scale announced-vs-energized tracking see the data center index. DEPLOY is neutral infrastructure: what is claimed, what is verified, and when.

Common questions

What is Cipher Bear Facility?
Cipher Bear Facility is a data center facility record on the DEPLOY registry, in Andrews. Every fact on the record is individually sourced and dated.
Who operates Cipher Bear Facility?
Cipher Mining operates Cipher Bear Facility, per the sourced record on the DEPLOY registry.
Is Cipher Bear Facility operating?
Cipher Bear Facility is recorded as operating on the DEPLOY registry, with 40 MW of critical IT capacity. Each figure traces to a source.
How verified is the data on Cipher Bear Facility?
A human editor has reviewed this record for the indexed registry. Every rendered fact shows its source: this is what a verified record looks like next to an unsourced directory listing.

Deploy Watch

Track Cipher Bear Facility on Deploy.

We notify you when operating status, capacity, or the operator changes against a sourced record.

Cite this page

DEPLOY. (2026). Cipher Bear Facility: data center facility record. Retrieved September 27, 2026, from https://registry.deploy.report/datacenters/facilities/cipher-bear-andrews-texas

More citation formats (MLA, Chicago, BibTeX) →
CC BY 4.0

The verified data on this page is available under a Creative Commons Attribution 4.0 license: reuse the facts freely, with attribution to DEPLOY (deploy.report). The prose, design, and any imagery are not included and keep their own rights.

Machine-readable surfaces